State Ex Rel. Dept. of Education v. Vantage Technologies

261 P.3d 17, 243 Or. App. 557, 2011 Ore. App. LEXIS 857
CourtCourt of Appeals of Oregon
DecidedJune 22, 2011
Docket07C12927; A141945
StatusPublished

This text of 261 P.3d 17 (State Ex Rel. Dept. of Education v. Vantage Technologies) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Dept. of Education v. Vantage Technologies, 261 P.3d 17, 243 Or. App. 557, 2011 Ore. App. LEXIS 857 (Or. Ct. App. 2011).

Opinion

*559 WOLLHEIM, J.

This action arose out of a contract between the State of Oregon, acting through the Department of Education (DOE or the state), and defendant Vantage Technologies Knowledge Assessment, LLC (Vantage), for the provision and administration of software for standardized testing of K-12 students in Oregon schools through the Oregon Technology Enhanced Student Assessment (TESA) system. After the contractual relationship soured, Vantage gave notice of termination of the contract, and DOE sued for breach of contract. Vantage brought counterclaims for breach of contract and breach of the implied duty of good faith and fair dealing. A jury found that Vantage did not breach its contractual duty to DOE, and DOE does not challenge that part of the judgment. The jury also found in favor of Vantage on its counterclaims, and DOE appeals, assigning error to several rulings of the trial court, all of which stem from the trial court’s determination that the parties’ contract was ambiguous as to the material issue in dispute and that its meaning should be submitted to the jury. We conclude that the trial court did not err in submitting the question to the jury and affirm.

The factual background leading up to this litigation is largely undisputed. In March 2001, DOE entered into a contract with Vantage under which Vantage agreed to provide assessment software used to administer standardized testing to students in Oregon schools, to score the tests, and to provide reports regarding the test scores. The testing was necessary to allow Oregon to comply with the requirements of the federal No Child Left Behind Act of 2001, as well as with state statutory requirements for periodic student assessment. ORS 329.075; ORS 329.085.

The initial contract, executed March 6, 2001, provided that Vantage’s software would support 540,292 individual tests per school year, with up to 1,000 concurrent test takers — i.e., the number of students who could use the system simultaneously — when fully implemented. Section 11, paragraph 11.2, of the contract provided:

“Should DOE deliver more than 110% (594,321) of the base volume tests in any contract year (July 1 through June 30) *560 DOE will enter into good faith negotiations with Vantage to establish a new pricing structure.”

The contract provided that, in the first phase of the contract, Vantage would support at least 1,000 concurrent users. In the second phase, Vantage would support 3,000 concurrent users. By Phase III, the 2002-03 school year, the system would support 5,000 concurrent users.

The contract had a “not-to-exceed” clause that limited DOE’s liability for the initial five years of the contract:

“Unless this contract is otherwise amended in writing by the parties, the DOE shall not be obligated under this contract to pay more than Three Million One Hundred Seventy Nine Thousand, Six Hundred Dollars (US $3,179,600) in the aggregate for the Services under this Agreement, unless otherwise amended under the terms of Section 11.”

The contract expressly provided that DOE would pay for services only as provided in the contract:

“Vantage is not obligated to perform any services, and DOE has not contracted for and will have no obligation to pay for any services, except as set forth in this agreement.”

The contract contained an integration clause stating that it “constitutes the entire Agreement between the Parties.”

Exhibit B of the contract was entitled “TESA WORK PRODUCTS AND CONTRACT DELIVERABLES,” and set out in chart form the project activities deliverable for the first three phases of the contract, as well as the payment schedule for each activity. Exhibit B included this paragraph:

“Total costs each year may not exceed:
“Phase I, (January 19,2001 through June 30, 2001) $ 617,400 “Phase II, (July 1, 2001 through June 30, 2002) $ 509,200
“Phase III, (July 1, 2002 through June 30 2003) $ 513,000
“(July 1, 2003 through June 30, 2004) $ 770,000
“(July 1,2004 through June 30, 2005) $ 770,000”

The contract was amended almost every year to accommodate the parties’ changing needs and requirements. The amendments resulted in additional activities deliverable and in additional costs and revisions to Exhibit B. The amendment that is central to this dispute is Amendment A5, *561 dated May 29, 2004. Amendment A5 states in its second paragraph that “[t]he Contract is hereby amended as follows (new language is indicated by underlining and deleted language is indicated by brackets): SEE ATTACHED.” Paragraph 4 of Amendment A5 states, “Except as expressly amended above, all other terms and conditions of original contract are still in force and effect.”

The AMENDMENT CONTINUATION PAGE described the amendments to the contract and included the following provisions:

“b. The following changes deal with Phase V July 1, 2004 through June 30, 2005
“Phase V Financial Impact explanation:
“Phase V (July 1, 2004 through June 30, 2005) currently is for $770,000. This change increases the Phase V amount by $381,000 to a total of $1,151,000
“EXHIBIT B Page 4:
“The parties hereby agree that the total amount of the Phase V will be increased by $381,000 in accordance with the additional deliverables:
“1. The limit of 500,000 tests is removed from the contract now there is no limit.
“2. Increasing from 5,000 to 10,000 concurrent users upon third party certification 9/1/04 $160,000
“3.
“4. Sample tests on an additional server using the existing application $15,000
“5. Display a block of reading items $54,000
“6. Other modifications $52,000
“Phase V (July 1, 2004 through June 30, 2005) operations will not exceed the $770,000 as described in the original contract.
’’The payment and deliverable schedule is set forth below:
“a. TESA program and system set up and tuning: 9/1/04 $77,000
*562 “b. Live operations of 1000 students 9/15/04 $30,000
“c. Weekly status meetings with DOE project director 10 monthly billings totaling $130,000
“d. Monthly Status Reports (by 5th working day) 10 monthly billings totaling $140,000
“e.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yogman v. Parrott
937 P.2d 1019 (Oregon Supreme Court, 1997)
EVENSON MASONRY INCORPORATED v. Eldred
543 P.2d 663 (Oregon Supreme Court, 1975)
Harnisch v. College of Legal Arts, Inc.
259 P.3d 67 (Court of Appeals of Oregon, 2011)
Dalton v. Robert Jahn Corp.
146 P.3d 399 (Court of Appeals of Oregon, 2006)
Batzer Construction, Inc. v. John Boyer
129 P.3d 773 (Court of Appeals of Oregon, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
261 P.3d 17, 243 Or. App. 557, 2011 Ore. App. LEXIS 857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-dept-of-education-v-vantage-technologies-orctapp-2011.