Batzer Construction, Inc. v. John Boyer

129 P.3d 773, 204 Or. App. 309, 2006 Ore. App. LEXIS 209
CourtCourt of Appeals of Oregon
DecidedFebruary 15, 2006
Docket00-2145-L-1; A119350
StatusPublished
Cited by108 cases

This text of 129 P.3d 773 (Batzer Construction, Inc. v. John Boyer) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Batzer Construction, Inc. v. John Boyer, 129 P.3d 773, 204 Or. App. 309, 2006 Ore. App. LEXIS 209 (Or. Ct. App. 2006).

Opinion

*311 ARMSTRONG, J.

Defendant appeals a judgment for plaintiffs in a contract action. He assigns error to the trial court’s grant of a directed verdict for plaintiffs on their claim and on his counterclaims. Plaintiffs cross-assign error to the trial court’s ruling that defendant’s counterclaims were not time barred by ORS 12.110(1), the general tort statute of limitation. We affirm.

Defendant and plaintiffs built buildings for lease to the United States Postal Service (USPS). Each party performed specific tasks to further that endeavor. Defendant found suitable land, purchased the land, and handled most of the negotiations with the USPS. The plaintiffs prepared bids and, if the USPS accepted the bids, constructed the buildings. The bids consisted of a per annum rent amount that plaintiffs and defendant calculated based on estimates of how much it would cost to build the buildings. After the USPS accepted a bid, it could alter the building plans that formed the basis for the bid. If the change would increase the cost of the project, defendant and plaintiffs, as co-owners, could submit a change order to the USPS for the additional cost. If the USPS accepted the proposed change order, it would pay the additional cost resulting from the change rather than recalculate the lease to reflect the increased cost of the building. If the USPS rejected the change order, then the change that it had requested would not be made.

In 1997, defendant and plaintiffs agreed to end their business ventures and divide their jointly held assets between them. As part of that agreement, plaintiffs received the sole rights to some of the land and a number of buildings that the parties had co-owned. Defendant received the sole rights to the balance of the land and a number of buildings that the USPS had agreed to lease. However, when the agreement became effective, the buildings that defendant received had not been completed. The parties’ contract addressed that by providing that plaintiffs would ££build post offices in Turner, Corvallis, and Toledo, Oregon for [defendant] at a price equal to ¡plaintiffs’] cost including attributed liability insurance costs.” (Emphasis added.) A handwritten note in the margin of the contract indicates that liability insurance *312 costs were to be the sole item of overhead and profit paid to plaintiffs for work on the buildings. Both parties initialed the note.

After the parties divided their jointly owned assets, plaintiffs completed the three buildings. However, plaintiffs spent more to build the buildings than the total of the estimates on which the bid amounts were based, insurance expenses, and the amount paid by the USPS for approved change orders. Defendant refused to pay plaintiffs for costs that exceeded that total. In response, plaintiffs brought this breach of contract action, alleging that it had cost $95,366.08 more to construct the buildings than defendant had paid for them and seeking a judgment for that amount plus prejudgment interest. Defendant, in turn, alleged various counterclaims against plaintiffs. In answer to those counterclaims, plaintiffs alleged, among other things, that defendant’s claims were time barred because they actually were tort claims that were subject to a two-year statute of limitation rather than the six-year statute that applies to contract claims.

At trial, defendant took the position that the term “[plaintiffs] cost” was ambiguous and that the circumstances underlying the formation of the contract revealed that the term meant the cost estimates on which the bids were based plus approved change orders. After defendant had presented all of his evidence on the meaning of the term “[plaintiffs’] cost” and on most of his counterclaims, plaintiffs moved for a directed verdict on their claim against defendant, arguing that the term “[plaintiffs’] cost” in the parties’ contract could be interpreted only to mean the expenses that plaintiffs had incurred to construct the buildings. 1 Plaintiffs also moved for a directed verdict on defendant’s counterclaims, arguingthat *313 defendant had not proved his damages and that his claims were time barred. The court granted plaintiffs’ motion for a directed verdict on plaintiffs’ contract claim and most of defendant’s counterclaims. In making that ruling, the court concluded that the term “[plaintiffs’] cost” was unambiguous and that the evidence presented by defendant did not render the term ambiguous. The trial court concluded that “[plaintiffs’] cost” meant all of the expenses that plaintiffs had incurred in constructing the buildings. The court also concluded that, even if the term “[plaintiffs’] cost” were ambiguous, defendant was nevertheless responsible for submitting change orders to the USPS and had failed to do so. After receiving additional evidence on defendant’s remaining counterclaim, the court determined that plaintiffs were liable to defendant for $8,000 on that counterclaim and that defendant was liable to plaintiffs for $95,366.08 plus prejudgment interest. The court entered judgment accordingly.

On appeal, defendant first assigns error to the trial court’s grant of plaintiffs’ motion for directed verdict on plaintiffs’ breach of contract claim. Specifically, defendant argues that the court erred in concluding that the term “[plaintiffs] cost” is unambiguous. As at trial, defendant’s theory on appeal is that the meaning of the term “[plaintiffs’] cost” as the parties used it in their agreement is ambiguous in light of the circumstances underlying the formation of the contract.

“A contract provision is ambiguous if it has no definite significance or if it is capable of more than one sensible and reasonable interpretation [.]” Deerfield Commodities v. Nerco, Inc., 72 Or App 305, 317, 696 P2d 1096, rev den, 299 Or 314 (1985). Although neither party addresses it, we first must examine the threshold issue whether a trial court can consider the circumstances underlying the formation of a contract to determine whether the terms of the contract are ambiguous.

ORS 41.740 codifies the parol evidence rule and, in relevant part, provides:

“When the terms of an agreement have been reduced to writing by the parties, it is to be considered as containing all those terms, and therefore there can be, between the parties and their representatives or successors in interest, *314 no evidence of the terms of the agreement, other than the contents of the writing, except where a mistake or imperfection of the writing is put in issue by the pleadings or where the validity of agreement is the fact in dispute. However, this section does not exclude other evidence of the circumstances under which the agreement was made, or to which it relates, as defined in ORS 42.220, or to explain an ambiguity, intrinsic or extrinsic, or to establish illegality or fraud.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moody and Zhang
345 Or. App. 776 (Court of Appeals of Oregon, 2025)
State v. Verrall
344 Or. App. 752 (Court of Appeals of Oregon, 2025)
Tozer v. Katerra Construction LLC
344 Or. App. 204 (Court of Appeals of Oregon, 2025)
Carroll v. Lane County
340 Or. App. 514 (Court of Appeals of Oregon, 2025)
Frost v. Jacobs
Court of Appeals of Oregon, 2024
Dadu and Dadu
323 Or. App. 499 (Court of Appeals of Oregon, 2022)
Farnsworth v. Meadowland Ranches, Inc.
519 P.3d 153 (Court of Appeals of Oregon, 2022)
Allison v. Dolich
518 P.3d 591 (Court of Appeals of Oregon, 2022)
Ram Investments v. West Union Development
510 P.3d 958 (Court of Appeals of Oregon, 2022)
Brown Contracting, Inc. v. ODOT
504 P.3d 1195 (Court of Appeals of Oregon, 2022)
Rudder v. Hosack
506 P.3d 1156 (Court of Appeals of Oregon, 2022)
Creekside Homeowners Assn. v. Creekside Golf Course
505 P.3d 15 (Court of Appeals of Oregon, 2021)
Yee v. Yee
495 P.3d 1285 (Court of Appeals of Oregon, 2021)
Pistol Resources, LLC v. McNeely
496 P.3d 28 (Court of Appeals of Oregon, 2021)
Patel v. Siddhi Hospitality, LLC
495 P.3d 693 (Court of Appeals of Oregon, 2021)
Sause and Schnitzer
493 P.3d 1071 (Court of Appeals of Oregon, 2021)
Baertlein and Stocks
464 P.3d 433 (Court of Appeals of Oregon, 2020)
Bush v. City of Prineville (A165637)
457 P.3d 324 (Court of Appeals of Oregon, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
129 P.3d 773, 204 Or. App. 309, 2006 Ore. App. LEXIS 209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/batzer-construction-inc-v-john-boyer-orctapp-2006.