State ex rel. Department of Highways v. Moseley

390 So. 2d 951
CourtLouisiana Court of Appeal
DecidedOctober 28, 1980
DocketNos. 14309 to 14314
StatusPublished
Cited by1 cases

This text of 390 So. 2d 951 (State ex rel. Department of Highways v. Moseley) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Department of Highways v. Moseley, 390 So. 2d 951 (La. Ct. App. 1980).

Opinion

FRED W. JONES, Judge.

In December, 1974 the State of Louisiana through the Department of Highways (“State”) filed three suits under La. R.S. 48:441 et seq. (“quick taking” statute) to expropriate certain property belonging to the defendants, either individually or jointly, for the purpose of widening Louisiana Highway 4 in Franklin Parish from a two-lane to a four-lane thoroughfare. In October, 1975 the State filed another three suits against the same defendants to expropriate additional property lying adjacent to that first taken in order to relocate utilities. These six suits were consolidated for the purpose of trial, which was had in 1978.

From a judgment in each of the suits in favor of the landowners, the State appealed. However, on appeal the State has conceded the correctness of the judgments in No. 14,309, No. 14,311, No. 14,312 and No. 14,313. Consequently, this appeal is concerned only with the lower court’s judgments in No. 14,310 and No. 14,314. The state argues that the awards to the defendants in those actions were excessive because the trial judge erred in:

(1) Employing erroneous square footages as to remainder areas for computation of severance damages.
(2) Failing to offset severance damages with amount of special benefits accruing to remainders after taking.
(3) Fixing value of land expropriated in second taking without deducting for diminution of value occasioned by first taking.

The trial court judgments contested in this appeal involve the property described on the pertinent state map as parcel 3-1 (for sake of clarity see sketch appended to this opinion). The original tracts from which this parcel was expropriated contained some 105 acres, with the parts taken comprising about 3 acres. Parcel 3-1 is described generally as beginning at the eastern corporate limits of Winnsboro, Louisiana and running east along the north side of La. Hwy. 4 for a distance of approximately 3000 feet, with varying depths.

Although each side presented the testimony of two expert witnesses, the trial judge apparently found most persuasive the testimony of Darrel V. Willet, one of defendants’ expert appraisers. For appraisal purposes this witness divided parcel 3-1 into three segments (as shown on the appended sketch). For segments 1 and 2, with which this appeal is concerned, Willet adopted a “front-use” approach to his land analysis, assuming a depth of 200 feet for the property fronting on the highway.

It was generally agreed that the highest and best use of the expropriated property was for commercial development and rural homesites.

After considering the testimony reláting to land values, and without wholly accepting any one set of appraisals, the trial judge fixed the value of the 22,238 square feet taken from segment 1 at 25$ per square foot and the value of the 39,200 square feet taken from segment 2 at 21<t per square foot.

Because the construction project entailed the creation of a much larger drainage ditch than had previously existed between [954]*954defendants’ properties and the highway, the trial judge found that in segment IB a lot with 420 feet frontage and 200 feet deep had been diminished in value by 5<t per square foot, and in segment 2 that a lot with 980 feet frontage and 200 feet deep had been diminished in value by the same amount per square foot.

The significant issues presented by this appeal will be discussed separately.

Computation of Damaged Remainder Area

The State argues that all of segment IB, measuring 420 feet frontage by 200 feet deep, contained 84,000 square feet. When the part taken (18,680 square feet) is subtracted, the balance is 65,320, which should have been the remainder on which the severance damage of 5<t per square foot was computed. Instead, the trial judge calculated severance damages in this segment on the basis of the entire 84,000 square feet.

The same argument is directed at the severance damage award made with reference to segment 2, which measured 980 feet frontage by 200 feet deep and contained 196,000 square feet, for which the trial judge allowed 5$ per square foot as severance damages. The State asserts that he should have deducted the part taken (39,200 square feet) and computed severance damages upon the remainder of 156,800 square feet.

It is well settled in our jurisprudence that the severance damage allowable as a result of an expropriation is the difference between the market value of the landowner’s remaining property immediately before and its diminished value immediately after the taking. State, Dept. of Highways v. Anderson, 356 So.2d 1086 (La.App. 2d Cir. 1978); State, Dept. of Highways v. Champagne, 371 So.2d 626 (La.App. 1st Cir. 1979); State v. Martin, 196 So.2d 63 (La. App. 3rd Cir. 1967).

However, where the evidence shows the landowner actually sustained damages to a particularly valuable portion of his tract, the award will be computed with reference to the before and after value of only the portion of the remainder suffering a loss in market value by reason of the taking. Dakin & Klein, Eminent Domain in Louisiana, p. 76 (1970).

In State v. Martin, supra, the State contended that the trial judge erred in permitting defendant’s experts to base their estimate of severance damages on the highest and best use of a typical lot measuring 100 feet by 200 feet. Rejecting this argument, the court explained that it interpreted the testimony of these experts to be “that the only severance damages sustained to the entire tract were those which related to this typical lot.”

Southwest Louisiana Electric Membership Corp. v. Beck, 299 So.2d 411 (La.App. 3rd Cir. 1974) was an expropriation suit for the construction of an electricity transmission line through the defendant’s property, taking about one acre out of a 15 acre tract. The court found severance damages “only in regard to the 200 foot swath of some 3.34 acres situated to the east of the right of way.”

In State, Dept. of Highways v. Westport Development Co., Inc., 332 So.2d 918 (La. App. 2d Cir. 1976), this court found no error in the method used by defendant’s appraisers to calculate severance damages because “the entire remainder was damaged only to the extent that the parcel between the two drainage servitudes was damaged.”

Implicit in Willet’s testimony in this case is that his calculation of severance damages was based upon a “front-use” tract, 200 feet deep, remaining after the first taking. The trial judge obviously accepted this testimony, concluding that the entire remainder containing in excess of 100 acres was damaged only to the extent that there was a diminution in value of the “front-use” lots measuring 200 feet deep after the first taking. Contrary to the State’s contention, he did not include the portions first taken in his severance damage computations, but simply brought this square footage from the rear and made it a part of the “front-use” lots. He committed no error by proceeding in this manner, since the cited jurisprudence fully supports that method of calculating severance damages.

[955]*955 Offset of Severance Damages by Special Benefits

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State, Department of Highways v. Modica
514 So. 2d 22 (Louisiana Court of Appeal, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
390 So. 2d 951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-department-of-highways-v-moseley-lactapp-1980.