State Ex Rel. Barnard-Curtiss Co. v. District Court

121 P.2d 419, 113 Mont. 107, 1942 Mont. LEXIS 6
CourtMontana Supreme Court
DecidedFebruary 21, 1942
DocketNo. 8,255.
StatusPublished
Cited by3 cases

This text of 121 P.2d 419 (State Ex Rel. Barnard-Curtiss Co. v. District Court) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Barnard-Curtiss Co. v. District Court, 121 P.2d 419, 113 Mont. 107, 1942 Mont. LEXIS 6 (Mo. 1942).

Opinion

MR. JUSTICE ANDERSON

delivered the opinion of the court.

The relator, Barnard-Curtiss Company, a Minnesota corporation, is defendant in an action pending in the district court of Granite county, brought by C. A. Metcalf, to recover an amount which he claims as owing to him for work done on a dam construction project. Barnard-Curtiss Company had the con *109 tract for building the dam and Metcalf had been employed ‘and had done work in clearing the reservoir site of timber and brush. Ernest Maehl had likewise been employed in the same work; both had received pay from Barnard-Curtiss as the work progressed. Each made demand on Barnard-Curtiss for a sum claimed as a balance owing. Each brought separate suit against Barnard-Curtiss for the amount claimed, the basis of each suit being the clearing of the reservoir site, each claiming to have been hired or to have had a contract to do the work.

The amount sued for in each case was about the same, something over $3,000. Both cases were removed to the federal district court on the ground of diversity of citizenship. Metcalf dismissed his case and brought two new actions in the state court covering the same demand as was all first included in one action, each less than $3,000, thus avoiding removal to the federal court. In the case here involved the amount sued for is $2,990.

The Maehl case was tried in the federal district court resulting in a verdict and judgment for the plaintiff. On appeal to the circuit court of appeals the judgment was affirmed. (Barnard-Curtiss Co. v. Maehl, 9 Cir., 117 Fed. (2d) 7.) Shortly after its affirmance relator paid the judgment.

The Metcalf case, in relation to which the present proceeding has been instituted, was carried along and held in abeyance during the time of the disposition of the Maehl case.

In the Maehl case an attempt was made by the defendant Barnard-Curtiss Company to make Metcalf a party to the action, but this the court did not allow. In the trial of that case Metcalf was called as a witness by the defendant. From his testimony it appeared that he and Maehl had been dealing together for the job of clearing the dam site and reservoir site and that they had both worked on the job.

The relator’s answer filed in the Metcalf case shortly after its commencement was a general denial, and it also alleged that the work done by Metcalf was not as contractor but as em *110 ployee of the relator and for which he had been paid in full. After paying the judgment in the Maehl case the relator applied’ to the court for leave to amend its answer in the Metcalf case so as to set up the Maehl judgment and its payment as a defense. In the proposed amended answer, and a supplemental answer, a partnership between the two claimants is alleged and the pleas of payment, res adjudicata and estoppel are set up, based on the Maehl judgment and the payment of that judgment, and Metcalf’s testimony in the trial of the Maehl case. The court refused leave to make the amendment.

In the proceeding here the relator complains that it has been deprived of the right and opportunity to interpose a good defense; that the refusal of leave to amend was without justification and arbitrary; that there is no adequate relief by appeal nor by any other ordinary process, and relator seeks-relief from this court by exercise of the power of supervisory control.

Upon relator’s petition an order to show cause was issued. In response thereto the district court has made its return setting up as reasons for refusing the leave applied for that the relator had had ample opportunity to present its defense, that its application to amend its answer was not timely made, that the entire affirmative matter contained- in the proposed answers is insufficient in law as a defense and incompatible with sworn statements theretofore made in the ease by the defendant, that the application was not made in good faith, that granting the leave to amend would be prejudicial to plaintiff, and would not be in furtherance of justice but in contravention thereof, and that it would encourage the production of false evidence by the relator.

Amendments of pleadings after issue joined are, by statute, left to the discretion of the trial court. (Sec. 9187, Rev. Codes.) Liberality in allowing amendments is the rule, it being generally stated that, while an application to amend is addressed to the sound, legal discretion of the trial court, the rule is to allow, and the exception to deny, amendments. *111 (State ex rel. Gold Creek Mining Co. v. District Court, 99 Mont. 33, 43 Pac. (2d) 249.) A simple direct statement of the rule is that, while it is in the discretion of the trial court whether an amendment may be made, the amendment should be allowed unless there is good reason for its refusal.

The liberal policy is general under the Codes as is pointed out in Bancroft’s Code Pleading, page 736, section 511, where it is said that: “The Codes and the courts alike favor a broad liberality, rather than severely technical tendencies on this subject. Hence it is a rule generally that, in furtherance of justice, amendments to pleadings should be liberally allowed; and courts should be especially liberal toward defendants in allowing amendments.”

In considering whether the amendments here sought should have been allowed, the liberal rule must be applied as the law, and the question then is whether the trial court, in refusing to allow the amendments, kept within that rule.

As appears to us, the only ground of refusal that needs to be specially considered is whether the application to amend and file supplemental answer was timely made. Defendant’s answer was filed on November 18, 1939, after the judgment in the Maehl Case. Respondents say that all of the facts which furnish the basis for the allegation of the partnership relation then already had happened, but nevertheless no point was made thereof in the answer then filed. Also, that relator took no steps toward interpleader or other proceeding to bring the cases together. That not until February, 1941, after the case was set for trial, did the relator make any point of the matter now sought to be pleaded as an additional defense. The general complaint is that the relator did not act in good faith; that it resorted to dilatory tactics to delay and avoid trial of the ease; that it did not proceed with diligence in seeking to make the amendment, and therefore is not now in position to assert any right in the matter as against the trial court’s refusal of leave to amend.

The uncertainty of the relation between the two claimants, *112 Maehl and Metcalf, and the controversy between them over the matter which was the subject of litigation in the two cases, left the relator in a position where it might well want to have final disposition of the one case before going to trial with the other. Seeking postponement of the trial of the Metcalf Case

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh v. Kennedy
147 P.2d 425 (Montana Supreme Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
121 P.2d 419, 113 Mont. 107, 1942 Mont. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-barnard-curtiss-co-v-district-court-mont-1942.