STATE, ETC. v. McGuire Architects-Planners

245 N.W.2d 218, 309 Minn. 519, 1976 Minn. LEXIS 1575
CourtSupreme Court of Minnesota
DecidedAugust 6, 1976
Docket46521
StatusPublished
Cited by2 cases

This text of 245 N.W.2d 218 (STATE, ETC. v. McGuire Architects-Planners) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STATE, ETC. v. McGuire Architects-Planners, 245 N.W.2d 218, 309 Minn. 519, 1976 Minn. LEXIS 1575 (Mich. 1976).

Opinion

MacLaughlin, Justice.

This is an appeal from a judgment of the district court confirming an arbitrator’s award. The principal issues are whether the Minnesota Department of Administration may validly include an arbitration clause in a state contract and, if so, whether the arbitration clause may name the governor as the arbitrator with final and binding authority to settle disputes arising under the contract. We hold that the Department of Administration may properly include arbitration clauses in its state contracts. Further, while we disapprove of the practice of designating the governor as arbitrator, we find under the facts of this case that appellant has not been prejudiced by the operation of the clause *521 and has failed to properly preserve its objection to the appointment of the arbitrator. Accordingly, we affirm.

On December 10, 1971, appellant, McGuire Architects-Planners, Inc., entered into a contract with the State of Minnesota wherein appellant agreed to furnish architectural and engineering services for the design and construction of a parking structure to be known as the Centennial Parking Ramp. This contract contained the following arbitration clause:

“Arbitration
“In case any dispute or controversy arises between CONSULTANT and State out of any provisions herein contained, such dispute or controversy shall be referred to the Governor of the State of Minnesota for arbitration and his decision shall be final and binding on both parties.”

On May 29,1973, the state entered into a contract with Kraus-Anderson of Minneapolis, Inc., wherein Kraus-Anderson agreed to complete the general construction of the Centennial Parking Ramp. 1 On October 15, 1974, construction of the parking ramp was delayed to correct a design anomaly. On June 4, 1975, the state served appellant with a written demand for arbitration of a dispute relating to the question of whether a time extension should be given to Kraus-Anderson for completing construction *522 of the ramp. Although the arbitration clause named the governor as arbitrator, the governor declined to act as arbitrator and instead designated the American Arbitration Association (AAA) to arbitrate the dispute. The AAA in turn appointed an attorney to act as 1 , arbitrator in the dispute. Although appellant objected that the arbitration clause was invalid, and that thus arbitration was inappropriate, it did not employ the statutory procedure outlined in Minn. St. 572.10 to challenge the appointment of the arbitrator. 2

While this arbitration proceeding was pending, the state made a written demand on both appellant and Kraus-Anderson for joint arbitration of other contract disputes. This demand sought arbitration of all contract disputes among the parties except the previous dispute between appellant and the state regarding the question of a time extension. When appellant and Kraus-Anderson refused to jointly arbitrate, the state made a motion in district court under Minn. St. 572.09 to compel joint arbitration. On September 22, 1975, Ramsey County District Court Judge Edward D. Mulally issued an order compelling joint arbitration. Appellant’s petition to this court for discretionary review of this order was denied, but on appellant’s renewed petition this court stayed the joint arbitration proceedings pending disposition of the appeal in the instant case.

On October 17, 1975, the arbitrator in the instant case made an award favorable to the state on the issue of whether a time extension should be given to Kraus-Anderson. The state then petitioned the district court for an order confirming the award. Appellant moved to vacate the arbitrator’s award principally on *523 the ground that the arbitration clause was invalid. The trial court concluded that the validity of the arbitration clause had already been determined in the prior proceeding before Judge Mulally and that therefore appellant was barred from relitigat-ing the issue. Appellant appeals from the judgment confirming the arbitrator’s award.

The issues raised on this appeal are:

(1) Whether appellant is barred from challenging the validity of the arbitration clause;

(2) whether the arbitration clause in the state contract is void because it constitutes a waiver of the state’s sovereign immunity ;

(3) whether the arbitration clause in the state contract is void because it names the governor to act as' arbitrator.

The threshold issue is whether appellant may properly challenge the validity of the arbitration clause on this appeal. Although the trial court concluded that appellant was barred from litigating the validity of the clause, we hold that appellant may properly raise the issue on this appeal. Respondent argues that Judge Mulally’s order compelling arbitration collaterally estops appellant from relitigating the validity of the arbitration clause in the instant case. We note that Judge Mulally’s order was a nonappealable interlocutory order and that the validity of the contested arbitration clause involved a question of law. We hold that a nonappealable interlocutory order on a question of law can have no estoppel effect on a separate pending cause of action. See, Kanne v. Minneapolis & St. Louis Ry. Co. 33 Minn. 419, 23 N. W. 854 (1885); In re Application of Schaefer, 287 Minn. 490, 178 N. W. 2d 907 (1970); United States v. Moser, 266 U. S. 236, 45 S. Ct. 66, 69 L. ed. 262 (1924).

Neither is appellant barred by Minn. St. 572.19, subd. 1(5), from litigating the validity of the arbitration clause. That section provides in pertinent part:

“Subdivision 1. Upon application of a party, the court shall vacate an award where:
* * * * *
*524 “(5) There was no arbitration agreement and the issue was not adversely determined in proceedings under section 572.09 and the party did not participate in the arbitration hearing without raising the objection.” (Emphasis supplied.)

The trial court concluded that the validity of the arbitration clause was determined adversely to appellant in a § 572.09 proceeding, and even though this determination was made in the course of a different arbitration action it nevertheless barred appellant from raising the issue in the instant case. Consequently, the trial court never directly ruled on the validity of the arbitration clause. We conclude that the reference in Minn. St. 572.19, subd. 1(5), to proceedings under § 572.09 was intended to include only proceedings under § 572.09 which had occurred in the course of the same arbitration action. The purpose of the statute’s reference to § 572.09 proceedings is to prevent a party from relitigating an issue which had already been presented and rejected at a previous stage in the same action. Once an issue has been presented and rejected on its merits in the same action, there is no need to relitigate it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minton Construction Corp. v. Commonwealth
494 N.E.2d 1031 (Massachusetts Supreme Judicial Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
245 N.W.2d 218, 309 Minn. 519, 1976 Minn. LEXIS 1575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-etc-v-mcguire-architects-planners-minn-1976.