Starry Skies Ranch, L.P., Jo Arc Resources, Inc., and Sally Blackie-Sengel v. Chappell Hill Construction, Co. a Texas for Profit Corporation

Court of Appeals of Texas·Decided October 31, 2024·No. 01-22-00760-CV·Published

Opinion

Opinion issued October 31, 2024.

In The

Court of Appeals

For The

First District of Texas

for breach of contract after Appellants failed to pay costs and retainage Chappell Hill contends were due under the construction contract. The jury found in favor of Chappell Hill on its breach of contract claim, and the trial court rendered judgment awarding Chappell Hill $352,022.47 in damages and $838,688.61 in trial and appellate attorney’s fees.

On appeal, Appellants argue (1) there is no evidence supporting the jury’s finding that they breached the construction contract, (2) the trial court abused its discretion by prohibiting them from introducing evidence concerning other construction defects that were settled prior to trial, and (3) the trial court abused its discretion by awarding Chappell Hill its attorney’s fees.

We affirm the trial court’s judgment.

Background

On March 6, 2012, Appellant Sally Blackie-Sengel, though her entities Appellants Starry Skies Ranch, L.P. and Jo Arc Resources, Inc. (collectively, “Blackie”), hired Appellee Chappell Hill Construction, Co. (“CHC”) to build a home for Blackie-Sengel in Washington County, Texas. Blackie’s architect, Ben Boettcher with BBA Architects, LP (“BBA”), designed the 20,000 square foot residence, which was to be built on a on a 205 acre tract. Among other things, and relevant to this appeal, the house included a 3,000 square foot detached garage, a 5,500 square foot deck, and a pool.

Blackie1 and CHC executed a construction contract for the project consisting of the following documents: (1) a Standard Form of Agreement Between Owner and Construction Manager as Constructor (AIA Document A134 – 2009), and Revisions and Additional Provisions to the same document (collectively, “Standard Agreement”); and (2) the General Conditions to Contract for Construction (AIA Document A201-2007), and Revisions and Additional Provisions to the same document (collectively, “General Conditions”). We refer to the Standard Agreement and the General Conditions collectively as the Contract.

Three and a half years after construction on the house began, Blackie-Sengel fired Boettcher, the BBA architect for the project. The project continued without an architect until, eleven months later, Blackie-Sengel hired Suzanne Labarthe as Boettcher’s replacement. Two weeks after Blackie-Sengel hired Labarthe, CHC issued a Certificate of Substantial Completion and provided Blackie-Sengel with the certificate and a punch list identifying items that needed completion or correction before the home was fully complete. Labarthe, however, refused to certify the project as substantially complete because she believed there were still issues with the pool, the floor of the detached garage, the deck, the soffits, and the interior doors of the house that precluded the home from being substantially complete.

1 Appellants Blackie-Sengel and Starry Skies Ranch, L.P. executed the contract with CHC.

After a month had passed and Labarthe had yet to certify the project as substantially complete, CHC sent to Blackie Payment Application 48 (“PayApp 48”) for work performed on the project. PayApp48 included, among other things, costs for work on the pool and a charge for a second superintendent. CHC also sent to Blackie Payment Application 49 (“PayApp 49”) for a portion of the retainage withheld under the Contract. CHC claimed that it was entitled to a portion of the retainage because it had achieved substantial completion, and Blackie and Labarthe’s actions were materially delaying final completion of the home. According to CHC, Blackie breached the contract and materially delayed final completion of the project by delaying the hiring of a replacement architect for eleven months, hiring a replacement architect that had no knowledge or experience with the project, failing to follow the project’s close out procedures, and failing to cooperate with CHC’s efforts to finally complete the house.

Labarthe certified partial payment to CHC for PayApp 48, withholding approximately $10,000 attributable to costs for work on the pool and a second superintendent, and she refused to certify any payment for PayApp 49. Despite Labarthe’s failure to certify payment in full for PayApp 48 and PayApp 49, CHC continued to correct or complete the items identified on its punch list, including issues with the pool, the floor of the detached garage, the deck, the soffits, and the interior doors of the house. When Blackie continued to refuse to pay the outstanding

amounts due under PayApp 48 and PayApp 49, CHC sued Blackie for breach of contract.

The Trial Court Proceedings A. Motion in Limine In May 2017, CHC sued Blackie for breach of contract. Blackie asserted a general denial and counterclaimed against CHC for various alleged construction defects, including defects based on pool leaks, discolored soffits, and stains on the deck of the house. CHC filed third-party claims against the subcontractors and materialmen who performed work associated with the counterclaims. According to Blackie, “[t]he defects were the heart of the substantive litigation for the majority of the life of the suit.”

The suit was initially tried to a jury on September 7, 2021. Prior to trial, the parties filed a joint motion in limine. Upon consideration of the joint motion, the trial court issued an order in limine which, among other things, prohibited Blackie from mentioning settled construction defects, except for defects that existed as of March 31, 2017. The order stated:

SETTLED CONSTRUCTION DEFECTS: Defendants and their attorneys are prohibited from mentioning, referring, or presenting evidence on any affirmative claims for construction defects that have been settled or that have not been expressly referred to in Defendants’

live pleadings. This limine does not preclude Defendants from presenting evidence of relevant construction defects that existed as of March 31, 2017 and to argue the same as a defense to payment under the terms of the construction contract at issue in this suit.

The first trial ended in a mistrial due to a family medical emergency. Blackie and CHC subsequently settled Blackie’s counterclaims and CHC nonsuited its corresponding third-party claims against the subcontractors and materialmen before the second trial commenced on April 25, 2022.

Days before the second trial commenced, Blackie filed a motion to amend the order in limine to prohibit both parties from presenting evidence regarding affirmative claims for construction defects that had been settled. Blackie’s proposed order in limine stated:

SETTLED CONSTRUCTION DEFECTS: Any mention, reference, or presentation of evidence on any affirmative claims for construction defects that have been settled or that have not been expressly referred to in Defendants’ live pleadings.

The trial court denied Blackie’s motion to amend the order in limine and trial commenced. B. The Trial 1. Ray Andrejczak Ray Andrejczak is a project manager with CHC, a general contractor located in Washington County that works on commercial and residential construction projects. In 2011, CHC owner Walt Schoenvogel met with BBA architect Boettcher and Blackie-Sengel to discuss construction of the home Boettcher was then designing for Blackie-Sengel.

In March 2012, Blackie hired CHC as the general contractor for the project and they executed the Contract setting forth the parties’ respective obligations. Andrejczak served as CHC’s project manager on the project and Brian Brantley served as the project superintendent. Under the terms of the Contract, Blackie agreed to pay CHC on a cost-plus basis, meaning CHC would be paid for the Cost of the Work plus a 10% construction manager’s fee. Section 5.1 and 5.1.1 of the Standard Agreement provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Starry Skies Ranch, L.P., Jo Arc Resources, Inc., and Sally Blackie-Sengel v. Chappell Hill Construction, Co. a Texas for Profit Corporation, (Tex. Ct. App. 2024).

Starry Skies Ranch, L.P., Jo Arc Resources, Inc., and Sally Blackie-Sengel v. Chappell Hill Construction, Co. a Texas for Profit Corporation (Starry Skies Ranch, L.P., Jo Arc Resources, Inc., and Sally Blackie-Sengel v. Chappell Hill Construction, Co. a Texas for Profit Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Haggar Clothing Co. v. Hernandez
164 S.W.3d 386 (Texas Supreme Court, 2005)
DiGiuseppe v. Lawler
269 S.W.3d 588 (Texas Supreme Court, 2008)
City of Houston v. Hildebrandt
265 S.W.3d 22 (Court of Appeals of Texas, 2008)
Horizon/CMS Healthcare Corporation v. Auld
34 S.W.3d 887 (Texas Supreme Court, 2000)
M7 CAPITAL LLC v. Miller
312 S.W.3d 214 (Court of Appeals of Texas, 2010)
Croucher v. Croucher
660 S.W.2d 55 (Texas Supreme Court, 1983)
Parker Drilling Co. v. Romfor Supply Co.
316 S.W.3d 68 (Court of Appeals of Texas, 2010)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Downer v. Aquamarine Operators, Inc.
701 S.W.2d 238 (Texas Supreme Court, 1985)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)
RM Crowe Property Services Co. v. Strategic Energy, L.L.C.
348 S.W.3d 444 (Court of Appeals of Texas, 2011)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
State v. Central Expressway Sign Associates
302 S.W.3d 866 (Texas Supreme Court, 2009)
El Apple I, Ltd. v. Olivas
370 S.W.3d 757 (Texas Supreme Court, 2012)
Turner v. Duggin
532 S.W.3d 473 (Court of Appeals of Texas, 2017)