Starks Mechanical, Inc. v. New Albany-Floyd County Consolidated School Corp.

854 N.E.2d 936, 2006 Ind. App. LEXIS 2055, 2006 WL 2846981
CourtIndiana Court of Appeals
DecidedOctober 6, 2006
Docket22A01-0510-CV-480
StatusPublished
Cited by12 cases

This text of 854 N.E.2d 936 (Starks Mechanical, Inc. v. New Albany-Floyd County Consolidated School Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Starks Mechanical, Inc. v. New Albany-Floyd County Consolidated School Corp., 854 N.E.2d 936, 2006 Ind. App. LEXIS 2055, 2006 WL 2846981 (Ind. Ct. App. 2006).

Opinion

OPINION

BAKER, Judge.

Appellant-defendant Starks Mechanical, Inc., (Starks) appeals from the trial court's order granting summary judgment in favor of appellee-plaintiff The New Albany-Floyd County Consolidated School Corporation (School) on the School's declaratory judgment complaint against Starks. Specifically, Starks argues that the trial court misinterpreted the parties' contract and that there is a genuine issue of material fact rendering summary judgment inappropriate.

Additionally, the School cross-appeals from the trial court's order denying the School's motion to strike Starks's designated evidence in opposition to the School's summary judgment motion. Finding that summary judgment in favor of the School was proper even if the trial court properly denied the motion to strike, we affirm the judgment of the trial court.

FACTS

On June 5, 2002, Starks entered into a contract (Contract) with the School to provide mechanical and plumbing services in connection with the expansion, renovation, and improvement of the School's Hazel-wood Middle School property. Starks was to provide all labor, material, equipment, and related items needed for the installation, testing, and use of the mechanical and plumbing systems in accordance with the plans and design specifications set forth in the Contract.

Starks discovered a number of alleged material defects in the design specifications and plans provided by the School. Thus, on July 17, 2002, Starks sent a Request for Information (RFT) to the Construction Manager to provide notice of the *938 design defects and accompanying delays and to request time extensions and change orders. Starks proceeded to submit numerous RFIs to the Construction Manager as construction progressed to provide notice of other problems allegedly caused by the defects in the design specifications and plans. In essence, the School instructed Starks to proceed with construction and to correct any design defects. Thus, Starks hired an engineer to review the design specifications and plans and to recommend changes to be made to the documents.

Starks did not include costs for redesign in the many RFIs it submitted to the Construction Manager. On April 29, 2004, as construction neared completion, Starks submitted "Payment Application No. 28.1" to the School and included a line item entitled "Engineering Deficiencies" for the amount of $1,342,598.88. Appellant's Am. App. p. 142, 155. This payment application was the first notice the School received of Starks's claim for additional payment although the claim admittedly arises from alleged design deficiencies dating back to 2002.

Starks had not previously requested a Change Order for additional payment for engineering until May 5, 2004, when it submitted a Change Order Request for $1,342,598.88 attributed to "engineering deficiencies." Id. at 148, 157-59. The School denied Starks's Change Order Request, and on February 15, 2005, Starks reduced its claim for additional payment to $1,200,690.91 and submitted a Revised Change Order Request, which the School denied.

On April 4, 2005, the School filed a complaint against Starks seeking a declaratory judgment that Starks is not entitled to additional payment under the Contract because it failed to provide timely written notice of its claim as required by the Contract. The School pointed to a number of Contract provisions supporting its argument:

4.7 CLAIMS AND DISPUTES
4.7.1 Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims must be made by written notice. The responsibility to substantiate Claims shall rest with the party making the Claim.
wooo
4.7.3 Time Limits on Claims. Claims by either party must be made within 14! 1 days after occurrence of the event giving rise to such Claim or within 14 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner. In the case of continuing delay, the Claim along with estimated associated costs must be updated weekly and submitted to the Construction Manager for the duration.
[[Image here]]
4.1.7 Claims for Additional Cost. If the Contractor wishes to make [a] Claim *939 for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work....
#oosk ock
8.3. DELAYS AND EXTENSIONS OF TIME
8.3.1 If the Contractor is delayed at any time in progress of the Work by an act or neglect of the Owner's own forces . or by changes ordered in the Work . then the Contract Time shall be extended by Change Order for such reasonable time as the Architect may determine.
8.3.2 Claims relating to time shall be made in accordance with the applicable provisions of paragraph 4.7.
8.3.3 This Paragraph 8.3 does not preclude the recovery of damages for delay by either party under other provisions of the Contract Documents.

Appellant's Am.App. p. 63, 68-69, 91 (emphases added).

On May 3, 2005, the School filed a motion for summary judgment, arguing that pursuant to the terms of the Contract, Starks failed to provide timely written notice of its claim for additional payment and that, consequently, the School was entitled to declaratory judgment as a matter of law. On June 7, 2005, Starks filed its response and designation of evidence in opposition to the School's summary judgment motion. On June 29, 2005, the School filed a motion to strike Starks's untimely designation of evidence.

On September 7, 2005, the trial court held a hearing on, among other things, the School's motions for summary judgment and to strike Starks's designated evidence in opposition thereto. Following the hearing, on October 3, 2005, the trial court denied the School's motion to strike and granted the School's motion for summary judgment. 2 Starks now appeals the order granting summary judgment in favor of the School and the School cross-appeals the denial of its motion to strike.

DISCUSSION AND DECISION

I. Cross-Appeal

The School argues that the trial court erred in denying its motion to strike Starks's designated evidence in opposition to the summary judgment motion. We review a trial court's decision to admit or exclude evidence for an abuse of discretion. Utility Ctr., Inc. v. City of Fort Wayne,

Related

Cite This Page — Counsel Stack

Bluebook (online)
854 N.E.2d 936, 2006 Ind. App. LEXIS 2055, 2006 WL 2846981, Counsel Stack Legal Research, https://law.counselstack.com/opinion/starks-mechanical-inc-v-new-albany-floyd-county-consolidated-school-indctapp-2006.