Stanton v. United States

68 Ct. Cl. 379, 1929 U.S. Ct. Cl. LEXIS 271, 1929 WL 2552
CourtUnited States Court of Claims
DecidedOctober 21, 1929
DocketNo. H-215
StatusPublished
Cited by8 cases

This text of 68 Ct. Cl. 379 (Stanton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanton v. United States, 68 Ct. Cl. 379, 1929 U.S. Ct. Cl. LEXIS 271, 1929 WL 2552 (cc 1929).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

The court’s jurisdiction to adjudicate this case is conferred by the terms of the following special act of Congress approved February 12, 1927, to wit:

Be it enacted by the Senate and House of Befresentatwes of the United States of America m Congress assembled, That Stanton and Jones are hereby authorized to bring suit against the United States under contract with the engineer’s office, dated June 12, 1918, for revetment work, Pelican Bend, Missouri River, to recover whatever damages or losses which they may have suffered through action by governmental agencies in commandeering, purchasing, moving, or causing to be moved from the Missouri River the fleet of the Kansas City Missouri River Navigation Company, or of any other action of governmental agencies which resulted in any loss to the claimants. Jurisdiction is hereby conferred upon the Court of Claims of the United States to hear, consider, and determine such action and to enter decree or judgment against the United States for the amount of any loss or damages as may be found to have been suffered by the said Stanton and Jones under the said contract, if any: Provided, That such action shall be brought and commenced within four months from the date this act becomes effective.”

The plaintiffs repeat a contention oftentimes made, that the only issue in the case, made so by the special act, “is the amount of such damages and losses.” In other words, the Government by the act concedes liability, and all that remains for the court to do is to assess the loss. With this contention we are disinclined to agree. Special jurisdictional [390]*390acts are not always clear. This one is not distinctly obscure. A suit is authorized under a contract, granting the right to recover damages suffered, if any, by reason of specified interferences with the contractor’s performance of the same, or iby the action of governmental agencies in forestalling completion of the contract work. Judgment, if any, is to be predicated upon loss or damages “under said contract, if any.” What the act provides is a forum to which the plaintiffs may resort, with the right to have the cause of action adjudicated and determined. We fail to discover in the language of the act an acknowledgment of liability; on the contrary, taken as a whole, the statute indicates an intent to transfer a contention advanced in Congress from that forum to a judicial forum; where the plaintiffs’ contractual rights may be adjudicated according to law. If Congress intended to simply ascertain the facts, the way was open under section 151 of the Judicial Code. On the contrary, both Houses of ‘Congress, with the approval of the President, confer a jurisdiction which sets forth the subject matter to be adjudicated •as well as the origin of the claim and the causes alleged to have resulted in loss and damage. United States v. Mille Lac Indians, 229 U. S. 498, 500.

The plaintiffs contracted to perform specified revetment work at Pelican Bend, in the Missouri Biver. The contract was dated June 12, 1918, and was to be completed in twelve working months, which eliminated the months of December, -January, and February, if, in the opinion of the Government’s representative in charge, work could not be continued ■during these periods. Work was commenced by the contractor on October 14, 1918, and through extensions granted ¡should have been completed by November 26, 1919. The «contract originally contemplated the construction of 11,750 ffeet of revetments to be placed in what was designated the upper and lower sections of the bend, and on March 9, 1920, an amending agreement was entered into, conferring the right upon the Government to increase or decrease the length of the work not in excess of 30 per cent of the original length. On December 13, 1920, the plaintiffs by letter requested the Government to annul the contract for the construction of the revetments designed for the upper section [391]*391of the bend, citing the apparent difficulties in the way of the proper completion of this portion of the work. On January 18, 1921, the Government officials acceded to the plaintiffs’ request and a supplementary agreement was entered into whereby the plaintiffs were relieved from further performance of the contract, and settled with them on the basis of approximately 6,000 feet of completed work on the lower section, in consideration of which the plaintiffs released the United States from claims arising out of the contract, including anticipated profits. See Finding XX. The plaintiffs were thereafter paid the sum of $101,998.19 and the Government purchased material on hand to the extent of $19,106.20, Finding XXI.

The record discloses that when the plaintiffs submitted their bid for the work they were not adequately equipped to perform the same. The specifications warned the contractors to visit the site and ascertain the difficulties inherent in the work. Mr. Jones, one of the partners, was not only an experienced engineer but perfectly familiar from past experience with work of this character. He knew what was essential in the way of equipment to perform the contract and also what the firm possessed. Realizing the imperative necessity for additional facilities in the matter of transportation of materials, particularly concrete blocks, an effort was made to complete an arrangement with the Kansas City Missouri River Navigation Company to convey the same from Gasconade to Pelican Bend at T cents per block. The arrangement was never consummated, for on July 30, 191’8, the aforementioned navigation company entered into negotiations with the United States Railroad Administration for the sale of its fleet and its transfer to the Mississippi River. The plaintiffs stress this so-called interference of the Government, and rely principally upon it for a large portion of the amount of damages claimed. Obviously such a claim is not sustainable under the law. The plaintiffs had .made no contract with the navigation company to transport its blocks. The most that is claimed is an arrangement to perform the service for 1 cents per block, a sum claimed to be less than the actual cost. True, the plaintiffs may have submitted their bid upon the basis of this cost, but assuredly they may not [392]*392be beard to complain of an error of judgment in nowise attributable to the Government. But aside from this, the record discloses and the court finds that plaintiffs’ losses were not attributable to the loss of the services of the navigation company’s fleet. This contract was entered into during the war. Plaintiffs knew of existing conditions and should have anticipated impending difficulties, which, as a matter of fact, seems to have been done, for the record firmly establishes that the plaintiffs had available, at the point of necessity more concrete blocks than they had use for, and that the taking of the fleet in nowise contributed toward delay or undue expense. So that, granting in all aspects the contention of the plaintiffs as to the jurisdictional act, the claim for loss due to the taking of the fleet is without merit. It is manifestly impossible to compute a loss upon the basis of what happened in comparison with what might have happened. The. plaintiffs fail to establish a binding obligation with the navigation company to transport blocks at a given price, and afford the court no more than preliminary negotiations looking toward an uncompleted transaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fillman v. United States
355 F.2d 632 (Court of Claims, 1966)
California v. United States
119 F. Supp. 174 (Court of Claims, 1954)
Grant v. United States. Lewis v. United States
192 F.2d 482 (Fourth Circuit, 1951)
Hawkins v. United States
96 Ct. Cl. 357 (Court of Claims, 1942)
Gates v. United States
87 Ct. Cl. 358 (Court of Claims, 1938)
Shearer v. United States
87 Ct. Cl. 40 (Court of Claims, 1938)
Butler Lumber Co. v. United States
73 Ct. Cl. 270 (Court of Claims, 1931)
Randall v. United States
71 Ct. Cl. 152 (Court of Claims, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
68 Ct. Cl. 379, 1929 U.S. Ct. Cl. LEXIS 271, 1929 WL 2552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanton-v-united-states-cc-1929.