Butler Lumber Co. v. United States

73 Ct. Cl. 270, 1931 U.S. Ct. Cl. LEXIS 225, 1931 WL 2442
CourtUnited States Court of Claims
DecidedDecember 7, 1931
DocketNo. J-547
StatusPublished
Cited by1 cases

This text of 73 Ct. Cl. 270 (Butler Lumber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler Lumber Co. v. United States, 73 Ct. Cl. 270, 1931 U.S. Ct. Cl. LEXIS 225, 1931 WL 2442 (cc 1931).

Opinion

Booth, Chief Justice:

On March 3, 1927, the following jurisdictional act was approved (44 Stat. 1812) :

“An Act Giving jurisdiction to tiie Court of Claims to hear and determine the claim of the Butler Lumber Company, Incorporated.
“Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That the Court of Claims of the United States be, and hereby is, given jurisdiction to hear and determine the claim of the Butler Lumber Company, Incorporated, Richmond, Virginia, for damages resulting from the furnishing of piling in the erection of a fueling station on Craney Island, in Norfolk Harbor, Virginia, which station was erected [282]*282under a contract dated May 21, 1921, between W. S. Rendle and the United States Shipping Board representing the United States of America.”

The plaintiff, a Virginia corporation, seeks a judgment under the foregoing statute, predicating its right upon the facts about which there is no serious disagreement. On May 21, 1921, the United States Shipping Board entered into a written contract with W. S. Rendle for the construction at Craney Island, near Norfolk, Virginia, of certain concrete foundations. The work exacted the use of a large number of timber piles of different dimensions, and to secure the same the prime contractor, Rendle, contracted with Albert C. Place, of Boston, Mass., to supply the needed material. Place, on May 25,1921, contracted in writing with the plaintiff to furnish the piling he had agreed with Rendle to furnish, the same to be cut and delivered in accord with Place’s contract with Rendle. The plaintiff proceeded promptly and diligently to perform its contract; piling was supplied as per contract; a considerable number were inspected, approved, and delivered by plaintiff at the site of the work. In addition to the piling inspected and delivered, the plaintiff had on hand in the James River in condition to raft to the site of the work the piling called for by its contract.

On August 29, 1921, the plaintiff, in response to a request, to the Government inspector to inspect the piling then on hand and undelivered, was informed by him that he had been ordered by the Government constructing engineer in charge of the contract work to make no further inspection of plaintiff’s piling. No further inspection of plaintiff’s piling was ever made, which resulted in a loss to the plaintiff of its entire value. The piling through lapse of time became water-logged, rotten, and therefore utterly valueless. The plaintiff endeavored to dispose of it while in good condition but was unable to do so. This suit is for the recovery of a judgment for $61,010.96, the contract value-of the piling.

The plaintiff’s contention is centered upon the course of dealing and treatment received by it from the prime con[283]*283tractor, Rendle; the subcontractor, Place; and the responsible officials of the Shipping Board. The defendant contests the plaintiff’s right, basing its defense upon an assertion that the special jurisdictional act serves only to afford the plaintiff a judicial forum in which the claim may be-prosecuted, without intent to confess liability; and inasmuch as an act of Congress afforded the plaintiff means of redress, for its loss, there being no privity of contract between the plaintiff and the Government, the claim fails under the-general, principles of law. United States v. Mille Lac Band of Indians, 229 U. S. 498; Stanton & Jones v. United States, 68 C. Cls. 379. The plaintiff, on the other hand, insists that the special jurisdictional act, construed in the light of the committee report reporting the same to Congress, was intended to and did confer upon this court juris-' diction of an action sounding in tort. We agree with the-defendant’s contentions in so far as they extend to the obvious intent of Congress to afford the plaintiff a judicial forum for the adjudication of its rights and the necessity of the plaintiff to establish its case in accord with existing legal principles, but we disagree as to the effectiveness of the defense predicated upon the theory of no privity of contract and a complete remedy at law under the act of 1905. Inasmuch as the act of February 24, 1905 (33 Stat. 811), becomes an extremely important factor in the decision of this, case, we quote the following pertinent provisions thereof:

“ That hereafter any person or persons entering into a-formal contract with the United States for the construction, of any public building, or the prosecution and completion of any public work, or for repairs upon any public building or public work, shall be required, before commencing-such work, to execute the usual penal bond, with good and sufficient sureties, with the additional obligation that such contractor or contractors shall promptly make payments to-all persons supplying him or them with labor and materials, in the prosecution of the work provided for in such contract; and any person, company, or corporation who has furnished labor or materials used in the construction or repair of any public building or public work, and payment for which has not been made, shall have the right to intervene and be made a party to any action instituted by the [284]*284United States on the bond of the contractor, and to have their rights and claims adjudicated in such action and judgment rendered thereon, subject, however, to the priority of the claim and judgment of the United States. If the full amount of the liability of the surety on said bond is insufficient to pay the full amount of said claims and demands, then, after paying the full amount due the United States, the remainder shall be distributed pro rata among said interveners. If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person, or persons supplying the contractor with labor and materials shall, upon application therefor, and furnishing affidavit to the department under the direction of which said work has been prosecuted that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, be furnished with a certified copy of said contract and bond, upon which he or they shall have a right of action, and shall be, and are hereby, authorized to bring suit in the name of the United States in the circuit court of the United States in the district in which said contract was to be performed and executed, irrespective of the amount in controversy in such suit, and not elsewhere, for his or their use and benefit, against said contractor and his sureties, and to prosecute the same to final judgment and execution: Provided, That where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until after the complete performance of said contract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later: * *

Undoubtedly there was no privity of contract between the plaintiff and the Government and if the case was dependent upon this fact the plaintiff’s petition would have to be dismissed. The plaintiff does not contend to the contrary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ross v. United States
102 Ct. Cl. 151 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ct. Cl. 270, 1931 U.S. Ct. Cl. LEXIS 225, 1931 WL 2442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-lumber-co-v-united-states-cc-1931.