Stanton v. State

103 Misc. 221
CourtNew York Court of Claims
DecidedApril 15, 1918
DocketNo. 2623-A
StatusPublished
Cited by2 cases

This text of 103 Misc. 221 (Stanton v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanton v. State, 103 Misc. 221 (N.Y. Super. Ct. 1918).

Opinion

Cunningham, J.

The claimant,- on August 1, 1913, made a contract with the state of New York, through the state highway commissioner, for the improvement of the highway known as Millhrook Village County Highway No. 1114, by the construction of a road of the grouted bituminous macadam type. The claim originally aggregated $6,877.88, with interest from March 15, 1915, but has been duly amended in such manner that the total amount of it is $6,744.29. It is predicated on the alleged improper and unlawful refusal of the state highway commissioner to include in the final estimate and to allow and pay for various items of work and materials, and for certain alleged changes of materials required by the commissioner in the performance by the claimant of the contract. There are six items and briefly they are as follows:

(1) That the engineers of the highway department required the claimant to construct the top course 3y2 inches thick, whereas the contract provided for such a course 3 inches thick, requiring 400 additional cubic yards of top course macadam at the contract unit price of $4.25 per cubic yard, a total of.......................... $1,700 00

(2) That the said engineers required the claimant to construct the road 16.4 feet wide, whereas- the contract required the road to be 16 feet wide,' thus requiring 52.2 additional cubic yards of sub-base at the contract unit price of $1.90, $93.10; and 63 additional cubic yards of sub-base at the [223]*223contract unit price of $1.90 per cubic yard, $119.70; and 49 additional cubic yards of top course at the contract unit price of $4.25 per cubic yard, $208.25; a total of........ $421 05

(3) That the commissioner and his representatives refused to allow the use of certain bituminous material A, which, claimant alleged, complied with the contract specifications and compelled the claimant to use certain other bituminous material A, resulting in an increased cost to the claimant for said material of................. 287 80

(4) That the last mentioned conduct of the state highway commissioner and his representatives caused a delay of six weeks in the completion of the top course, damaging the claimant in the sum of............ 331 00

(5) That the claimant was induced by the commissioner and his representatives to believe, and did believe, that certain local stone known as shale could be used in the construction of the sub-base, but that the latter refused to permit the claimant to use same and required stone other than the local stone or shale to be used for sub-base, resulting in increased cost to the claimant therefor in the sum of $2,162.24. That this alleged improper action on the part of the state highway commissioner and his representatives caused an increase of cost to claimant for the top course stone of $1,837.20, a total of..................... 3,999 44

(6) Printing claim, estimated at........ 5 00

Total........................ $6,744 29

===

[224]*224Item (1).

Several interesting problems naturally are suggested by this inquiry:

(a) Would this item, if allowed, cause the contract expense to exceed the original estimate? If it would, there could be no recovery without an amendment of the original estimate, as provided by the statute. Highway Law, § 130, subd. 9. There is no evidence on this subject, and the state did not raise the question, so we are not concerned with it.

(b) Is a supplemental contract a necessary prerequisite to recovery for this work? The statute provides that state and county highways shall be constructed or improved “ by contract,” and all contingencies arising during the prosecution of the work shall be provided for to the satisfaction of the commission, and as may be agreed upon in the original* or by a supplemental contract, executed by the commission.” This would seem to leave no room for recovery for so-called extra work. It is clearly the intention of the statute to provide that there shall be no recovery for work done or materials furnished, unless they are provided for in the original contract, or by a supplemental agreement executed by the commission. The purpose is obvious. It is to prevent the creation of a liability against the state by the conduct of the contractor without, or with, the cognizance and co-operation of state employees, other than the commissioner. The power to increase the amount of work to be done and compensation to be paid is centered in the- commissioner, who must act by supplemental agreement if the state is to be obligated. The duty of the contractor is clear. It is to perform his original contract and, if ordered to do more, he has the right to insist on the execution of a- supplemental agreement, or he may refuse to comply with any direc[225]*225tions outside the limitations and purview of his original agreement. This particular contract is consonant with the statutory provision, but is more ample and explicit in its terms. It provides, paragraph 4, page 5, “ The state * * * reserves the right to make such additions * * * as it deems necessary, making an allowance * * * therefor at the prices named in the proposal for. this work. * * * It is further agreed that any increase of quantities or extra work performed or materials furnished shall be covered by a supplemental contract as provided in chapter 30, Laws of 1909, and amendments thereto.” Again, on page 8 of the information for bidders ” it is stated, Whenever an increase of quantity * * * occurs, then such excess must be agreed upon in writing as provided in chapter 30 of the Ijows of 1909.” The other provisions in the contract, relating to the right of the state to increase quantities, must be construed with these provisions, and mean that the state, through the commission, has the right to require such increase, on the terms stated, to be provided for in a supplemental contract, to be executed by the commissioner and contractor. We conclude that there can be no recovery for any work performed or materials furnished, unless they were performed pursuant to the provisions of the original, or a supplemental, contract executed by the commissioner, and that no conduct of other employees of the state, or of the contractor himself, or of both, can create an obligation, binding upon the state, for work performed otherwise. The contractor has the right to refuse to comply with directions of an engineer to perform work not within his original or a supplemental agreement. If he obeys the engineer in such a case, his act is voluntary and does not bind the state to pay for it. The claimant testified that he knew this item was not required by his contract, but [226]*226he complied with the engineer’s direction to “ avoid friction ” with the latter.

(c) Did the contract permit the engineer to increase the thickness of the top course of the road from three to three and a half inches? If there was an actual increase here, then the engineer, as we have shown, had no power to require it, because it would be extra or additional work, requiring a supplemental agreement. The plans and specifications specifically provide for a top course three inches thick. And, further, the “ information for bidders ” specifically warned the contractor that such work would not be paid for. On page 3, it reads, “ No greater depth or width of stone, gravel or other kind of pavement will, however, be paid for than that called for in the plans and specifications. ’ ’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Rockwood
126 Misc. 542 (New York Supreme Court, 1925)
General Construction Co. v. State
104 Misc. 293 (New York State Court of Claims, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
103 Misc. 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanton-v-state-nyclaimsct-1918.