General Construction Co. v. State

104 Misc. 293
CourtNew York Court of Claims
DecidedJuly 15, 1918
DocketClaim No. 2031-A
StatusPublished

This text of 104 Misc. 293 (General Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Construction Co. v. State, 104 Misc. 293 (N.Y. Super. Ct. 1918).

Opinion

Cunningham, J.

On March 20, 1911, the claimant General Construction Company entered into a contract with the commissioner of highways, under chapter 30 of the Laws of 1909, as amended, for the improvement of the Hollowville-Craryville County Highway No. 763 in Columbia county. On April 13, 1911, the General Construction Company duly assigned to the claimant Vincent Aderente all sums due or to become due to it under the contract, empowering Aderente to collect them, and to sue in its name. Subsequently, Aderente entered upon performance of the contract, and all the work done under it has been done by him. Various later assignments of funds due or to accrue under the contract were made by the General Construction Company, by Aderente, its attorney, to the claimant First National Bank of Albany, N. Y., and to the claimant Acme Road Machinery Company, of Frankfort, N. Y..

[295]*295The original contract provided for the construction of a bituminous macadam road of two courses of broken stone, each three inches thick in place. On April 29, 1912, after two miles of the road had been completed according to these specifications, a supplemental contract was entered into between the contractor and the state, changing the specifications and type of road, by providing for the construction of a six-inch sub-base of larger and heavier stone, in lieu of the lower three-inch course of broken stone originally provided.

In early August, 1913, the engineer in charge, one Biggi, reported the road for acceptance to his superior. A few days later, on August 11, 1913, the division engineer and the county engineer, superiors of Biggi, accompanied by the latter, examined the road for final inspection, and as a result presented a list of eleven items of work to be done by the contractor before acceptance. Subsequently, on November 8, 1913, the county engineer, the division engineer and representatives of the contractor again inspected the road, and as a result of this inspection the contractor was directed by the engineers to complete sixty-nine other items of work as a condition to acceptance. At the same time the engineers directed the contractor to increase the slope of an embankment at the Harlem railroad crossing, from a slope of one on one to a slope of one and one-half on one, and for that purpose to excavate the necessary earth from borrow pits and place it in the embankment. The last item of work was not necessitated by any fault of the contractor, or by any failure of the latter to erect the first embankment properly, but was due to an error in the original plans. The engineers promised that the contractor would be paid out of the funds available for the construction of the road, in order to [296]*296obviate payment from the maintenance fund available to the department, and the depletion of the latter fund. All the items of work which the engineers directed the contractor to perform were completed by December 18, 1913. Subsequently, on January 28, 1914, under a special agreement, the contractor did further work on the road, at the instance of the commissioner of highways, amounting, to $6,980.22. This work was completed and included in estimate No. 17, on March 20, 1914, and at that time the contractor was paid on account thereof, $5,964.59, leaving a balance for this work of $1,015.63. During the progress of highway construction, the contractor, by direction of the engineer in charge, decreased the grade of the crown of a hill three feet lower than shown on the plans forming a part of the contract, which excavation amounted to 1,121 cubic yards of rock and fifty-seven cubic yards of earth.' Elsewhere, in the course of the construction, the engineer in charge changed the line of the road laterally from that shown on the plans, and as a result the contractor was obliged to excavate in hard material, which was not actually rock, but which was more difficult to excavate than rock, and which was composed in large part of cemented gravel. The last estimate made by the commissioner of highways was on March 20,1914, and purported to include the work done to that date. At or about that time a payment was made on account to the contractor, the state retaining as the ten per cent provided by the contract to be retained until final acceptance the sum of $1,015.63, remaining unpaid' on the work done pursuant to the special agreement of January 28, 1914, and the sum of $10,151.31 on the work included in the original and first supplemental contracts, a total of $11,166.94, none of which has been paid.

On or about June 5, 1914, final acceptance not hav[297]*297ing been had, the then commissioner of highways, John N. Carlisle, sent two engineers from the office of his department to examine the road to determine if it had been properly and honestly constructed. These engineers, Culver and Cox, made eleven excavations in the road metal, four being in the two-mile portion consisting of two three-inch courses of broken stone, and the remainder in the other 5.14 miles of the road. Following is the result as shown in Culver’s report:

Station Top Total G. L...... 2f"...... 7" 654*.................... 12' wide C.L..... 2i"...... 74" C.L..... 24"...... 74" C.L..... 3i"...... 9" 14"...... 64" bottom. 5" shale C. L.~.... 3“....... Gravelly with considerable loam C.L..... 3"....... 74" gravelly clay or loam C.L..... 3"....... 64" 357 plus 00.............. C.L..... 3"....... 64" 328 plus 00.............. C.L..... 3"....... 6"

Later, Commissioner Carlisle had an interview with engineer-in-charge Biggi, and the commissioner testified, in substance,' that Biggi then admitted this report to be accurate, and asked to be allowed to resign, and that Biggi requested an opportunity to go to the road and measure the places mentioned, and that Carlisle then ordered an engineer ‘1 sent out there with Biggi and show him the report is correct. ’ ’

Biggi testified that he denied the report was correct, but told Carlisle that if it- was he would be glad to resign, and ought to be prosecuted, and that he urged that another engineer or engineers be sent out with him to ascertain the truth as to the measurements. As a result of their interview, and the request made [298]*298by Biggi, engineers Cox, Simmons and Biggi were sent out from the office of the commission to reexamine the excavations made by Culver and Cox, and to measure again the thickness of the courses composing the road metal. Cox and Simmons made a report of the measurements as follows:

Station Total thickness Top course Original required thickness Original required top 671 plus 60............. 81"........ 3"......... 9"....... 3" 643 plus 75............. 8|"........ 9"....... 3" 624 plus 50............. 2f......... 9"....... 3" 501 plus 50 (edge)....... 7 ......... 2?......... 9"....... 3" 473 plus 30............. 6*......... meas.).... 6"....... 3" 455 plus 50............. 8.......... 2»......... 9"....... 3" 417 plus or minus........ 81 (water in 3 (former in hole) meas.)

* Bottom course found crushed stone and gravel at this spot.

The following measurements, taken on the previous examination, we did not consider it necessary to check:

Station Total thickness Top course FT, Original required thickness Original required top 557 plus 50............. 9"......... 31"........ 9"....... 3" 380 plus 00............. 61......... 3Í......... 6........ 3 357 plus 00............. 3.......... 6........ 3 328 nlus 00............. 1 9*......... 3.......... 6........ 3 t

Mr. Biggi testified that these measurements were accurately taken, with the greatest care. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stanton v. State
103 Misc. 221 (New York State Court of Claims, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
104 Misc. 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-construction-co-v-state-nyclaimsct-1918.