Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc.

CourtWest Virginia Supreme Court
DecidedOctober 18, 2013
Docket12-1400
StatusPublished

This text of Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc. (Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc., (W. Va. 2013).

Opinion

STATE OF WEST VIRGINIA SUPREME COURT OF APPEALS

Stantec Consulting Services, Inc., FILED Plaintiff Below, Petitioner October 18, 2013 RORY L. PERRY II, CLERK SUPREME COURT OF APPEALS vs) No. 12-1400 (Kanawha County 09-C-2192) OF WEST VIRGINIA

Thrasher Environmental, Inc., and Dayton Carpenter, Defendants Below, Respondents

MEMORANDUM DECISION

Petitioner Stantec Consulting Services, Inc., by counsel Michael J. Schessler, appeals the order from the Circuit Court of Kanawha County granting judgment as a matter of law to respondents during trial. Respondents Thrasher Environmental, by counsel Kathryn K. Allen, and Dayton Carpenter, by counsel John B. Cromer, filed a joint response to which petitioner filed its reply.

This Court has considered the parties’ briefs and the record on appeal. The facts and legal arguments are adequately presented, and the decisional process would not be significantly aided by oral argument. Upon consideration of the standard of review, the briefs, and the record presented, the Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision is appropriate under Rule 21 of the Rules of Appellate Procedure.

In June of 2005, petitioner entered into a contract with the West Virginia Department of Environmental Protection (“DEP”) to develop a reclamation plan and design water treatment facilities to eliminate problems associated with the uncontrolled mine drainage at an abandoned mine site in Upshur County. The work directive from the DEP to petitioner contained no mention of the acceptable water treatment facility effluent discharge limits. However, in its proposal to the DEP, petitioner agreed to prepare construction plans and specifications for mediation of mining related environmental problems and referenced an effluent discharge goal of .5 mg/l of iron daily average. Evidence presented at trial affirmatively established that the DEP self- imposed technology-based standard for iron effluent discharge limits from abandoned mine sites was 3.0 mg/l.

Petitioner, as prime engineer on the project, entered into a sub-consulting agreement with Thrasher Environmental, Inc. (“Thrasher”); the terms of that agreement are set forth in a letter dated July 6, 2005. This letter specifically states that the DEP proposes certain items to remove elevated iron concentrations to <0.5 mg/l iron average. However, this agreement also states that Thrasher was to design a water treatment process and plant to treat water containing 15 mg/l iron, 500 mg/l alkalinity, and a pH of 7.4 to 7.6 mg/l. Dayton Carpenter (“Carpenter”) agreed to

1 act as the consultant to petitioner. The sub-consulting services were only a portion of the engineering services undertaken by petitioner for the DEP. The sub-consulting agreement also provides that the results of water quality studies being conducted by the DEP approved environmental testing laboratory were to be reviewed by respondents.

The project was built in accordance with the design plans, and it was placed into operation in October of 2007. At that time, the iron concentration levels coming into the plant were approximately 3.0 mg/l, representing a change in condition from the design parameters set forth by petitioner.1 Monthly test results since March of 2008 show water flowing into the treatment facility contained iron concentrations of 2.0 mg/l of iron or less, with limited exceptions. The DEP complained that petitioner failed to deliver a facility that conformed to the .5 mg/l iron effluent goal referenced in the contract between petitioner and the DEP. Petitioner claims that the problem was caused by respondents’ negligent design of the water treatment plant, which constituted a breach of the sub-consulting agreement. Petitioner undertook modifications to the facility in an attempt to satisfy the demands of the DEP. Despite these modifications, evidence presented at trial shows that since the redesigned and modified plant has been operational, the DEP has refused to accept the facility, the plant has not consistently met the DEP’s goal of .5 mg/l iron, and has not been able to consistently run the designed capacity of water flow.

Petitioner filed suit against respondents for negligence and breach of contract, seeking to recover the costs it claims it incurred to redesign and reconstruct the facility to meet the .5 mg/l iron level goal. On September 24, 2012, the action went to jury trial. At the close of petitioner’s case-in-chief, respondents jointly moved for judgment as a matter of law pursuant to Rule 50 of the West Virginia Rules of Civil Procedure. Following oral argument on the motion, the circuit court granted judgment as a matter of law in favor of respondents (defendants below) and entered its order on October 11, 2012. In that order, the circuit court found that respondents’ duty to petitioner is set forth in the contract between petitioner and respondents and that petitioner failed to introduce expert testimony to establish that respondents breached the standard of care in performing the duties they were contractually obligated to perform. The circuit court found that the design parameters and water quality and quantity characteristics were given to respondents by petitioner, and respondents were entitled to rely on the information provided in their performance of services. The court also found that neither respondent was a party to the contract between petitioner and the DEP. The circuit court concluded that respondents performed the scope of work set forth under their sub-consulting agreement with petitioner. Petitioner accepted the work performed by respondents and incorporated the plans and specifications into its engineering plans delivered to the DEP. The DEP accepted the plans and specifications and authorized petitioner to proceed with the project under the same. The circuit court further found that petitioner failed to introduce evidence to support a prima facie showing that the water treatment process designed by respondents breached the generally accepted standard of care for engineers practicing in the same locality under similar circumstances; that petitioner failed to make a prima facie showing that respondents’ actions or inactions were the proximate cause of the injuries asserted by petitioner; and that petitioner failed to make a prima facie showing that respondents breached their contract with petitioner. The court 1 As set forth herein, the influent iron level reportedly impacts the effluent iron level following treatment in the water treatment plant.

2 ultimately concluded that when viewed in the light most favorable to petitioner, there was no legally sufficient evidentiary basis for a reasonable jury to find for petitioner.2 It is from this order that petitioner appeals.

“The appellate standard of review for the granting of a motion for a [judgment as a matter of law] pursuant to Rule 50 of the West Virginia Rules of Civil Procedure is de novo. On appeal, this court, after considering the evidence in the light most favorable to the nonmoving party, will sustain the granting of a [judgment as a matter of law] when only one reasonable conclusion as to the verdict can be reached. But if reasonable minds could differ as to the importance and sufficiency of the evidence, a circuit court’s ruling granting a directed verdict will be reversed.” Syllabus Point 3, Brannon v. Riffle, 197 W.Va. 97, 475 S.E.2d 97 (1996).

Syl. Pt. 5, Smith v. First Cmty. Bancshares, Inc., 212 W.Va. 809, 575 S.E.2d 419 (2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
United States v. Timothy W. Markling
7 F.3d 1309 (Seventh Circuit, 1993)
In Interest of Tiffany Marie S.
470 S.E.2d 177 (West Virginia Supreme Court, 1996)
Tennant v. Marion Health Care Foundation, Inc.
459 S.E.2d 374 (West Virginia Supreme Court, 1995)
Brannon v. Riffle
475 S.E.2d 97 (West Virginia Supreme Court, 1996)
Fraternal Order of Police, Lodge No. 69 v. City of Fairmont
468 S.E.2d 712 (West Virginia Supreme Court, 1996)
Frymier-Halloran v. Paige
458 S.E.2d 780 (West Virginia Supreme Court, 1995)
Desco Corp. v. Harry W. Trushel Construction Co.
413 S.E.2d 85 (West Virginia Supreme Court, 1991)
Brown v. Gobble
474 S.E.2d 489 (West Virginia Supreme Court, 1996)
Woo v. Putnam County Board of Education
504 S.E.2d 644 (West Virginia Supreme Court, 1998)
Parkette, Inc. v. Micro Outdoors Advertising, LLC
617 S.E.2d 501 (West Virginia Supreme Court, 2005)
Aikens v. Debow
541 S.E.2d 576 (West Virginia Supreme Court, 2001)
State v. Stuart
452 S.E.2d 886 (West Virginia Supreme Court, 1994)
Hanlon v. Logan County Board of Education
496 S.E.2d 447 (West Virginia Supreme Court, 1997)
Kentucky Fried Chicken of Morgantown, Inc. v. Sellaro
214 S.E.2d 823 (West Virginia Supreme Court, 1975)
Tolley v. ACF Industries, Inc.
575 S.E.2d 158 (West Virginia Supreme Court, 2002)
Smith v. First Community Bancshares, Inc.
575 S.E.2d 419 (West Virginia Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/stantec-consulting-services-inc-v-thrasher-environ-wva-2013.