Standard Sprinkler Corp. v. State, No. Cv 91 0510150 (Jun. 20, 1994)
This text of 1994 Conn. Super. Ct. 6771 (Standard Sprinkler Corp. v. State, No. Cv 91 0510150 (Jun. 20, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The period in question began in June, 1988 and ended on October 20, 1989, when the plaintiff was finally authorized to proceed with the work. The plaintiff satisfactorily completed the work and has been paid in full the contract price of $37,532.00. It now claims, however, additional damages due to improper delays caused by the State.
At the outset in June of 1988 the State asked for bids on this project. On June 14, 1988 the plaintiff was advised that it was the successful bidder as follows:
"June 9, 1988
As low bidder . . . your firm was awarded the contract for Project #B-1 etc. Before proceeding a design must be submitted to this agency for approval by the State Fire Marshall's office."
Thereafter there ensued a series of conferences and letters concerning a controversy arising from the engineering and cosmetic features of the contract. There was a dispute as CT Page 6772 to the placing of the sprinkler heads. From the exhibits submitted however, it is difficult to lay the blame for the delays on any one party, because they appear to have been caused in part by both. That the engineering features were disputable and controversial is indicated by the fact that the engineering company engaged, by the plaintiff offered suggestions which in a sense corrected or enlarged upon the design submitted by Standard Sprinkler. In summary it is difficult to place the blame on any one party.
In the instant case, however, there was no delay caused by the defendant as previously stated. Actually there was no performance of the contract in effect until after the plaintiff had finally submitted a design satisfactory to the defendant. Thereafter, the contract was completed without delay or fault of the State. Where there is "no suspension of work, no idle time and no uncertain periods of delay . . . use of the Ichleay formula to calculate home office overtime is not permissible. C.B.C. Enterprises Inc. v. U.S.,
Standard Sprinkler also asserts that the contract came into being back in June of 1988. It is true that it was then informed that it was the successful bidder. However, the so-called award of the contract was not an unqualified one. CT Page 6773 Rather, the notification required that the plaintiff submit a design of the project that would meet with the approval of the State Fire Marshall. That approval was not obtained until a much later date.
Judgment with costs may enter in favor of the defendant.
John M. Alexander State Judge Referee
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
1994 Conn. Super. Ct. 6771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-sprinkler-corp-v-state-no-cv-91-0510150-jun-20-1994-connsuperct-1994.