Standard Sanitary Manufacturing Co. v. Stump

278 S.W. 583, 212 Ky. 253, 1925 Ky. LEXIS 1115
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedDecember 18, 1925
StatusPublished
Cited by10 cases

This text of 278 S.W. 583 (Standard Sanitary Manufacturing Co. v. Stump) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Sanitary Manufacturing Co. v. Stump, 278 S.W. 583, 212 Ky. 253, 1925 Ky. LEXIS 1115 (Ky. 1925).

Opinion

OpinioN op the Court by

Judge Dietzman

Reversiug.

The appellees, O. A. Stump, I. M. Williams and Fannie ft. Williams, are the owners of a lot in Pikeville, Kentucky, on which in the spring of 1922 they were- erecting a hotel. They do not seem to have had any architect to supervise this building, nor do they seem to have had *254 any plans and specifications for the same, at least so far as the plumbing work was concerned. They had reached the point in the erection of the building where the “roughing in” part of the plumbing work became necessary. At this stage, the appellees did not even know what material they would need or what it would cost. They got in touch with W. B. Call, a local plumber, and also with the Belknap Hardware & Manufacturing Company, a wholesale house of Louisville, Kentucky. They were figuring with Call on the installation of the plumbing work, but it was necessary for them to procure the material from some other source as Call had no such stock on hand either in quantity or kind as called for by this job. A representative of the Belknap Company went to Pikeville and there figured with appellees and Call on what plumbing should go into the building and what material would be needed. The building was then at a standstill for want of the “roughing in” of the plumbing work, and it was imperative that quick delivery of the material be made in order that the construction work might go forward. The Belknap man could not promise an immediate delivery of the needed material, and negotiations 'between him and the appellees seem to have been suspended, although the record is not quite clear as to just what was the status between them. Shortly thereafter, the appellee Stump learned from Call that the latter usually purchased his supplies from the appellant, Standard Sanitary Manufacturing Company, and so he wrote a letter, which he had Call to' sign, to this company, addressed to its place of business in Huntington, W. Va., asking it to send a salesman to Pikeville. In response to this letter, appellant did send a salesman to Pikeville. At the request of the appellees, this salesman and Call figured for some three or four days on what the building needed, after which they made up a list of the material required with the prices of the various items thereof. After this list was completed, the salesman copied it on the usual order blanks of the appellant and then, together with Call, went into a conference with the appellees concerning it. Up to this point there is no controversy about the facts, 'but from here on the parties differ as to what took place. The appellees claim that in this conference, when it appeared that the cost of the materials as figured by the salesman came to $10,975.15, they inquired what the cost of installation would be and that Call then stated he would do this work for $2,550.00. *255 At appellee’s request the salesman then placed on the copy of the order which they later retained, under the total figure for the materials, this item: “Labor ■$2,550.00,” and then totaled the two as $13,525.15. The appellees retired to consider the figures. After some consideration, they proposed to give Call and the appellant the job if they would jointly agree to do a “turnkey” job for $13,000.00. Upon this, Call and the salesman conferred together and then so agreed to do a “turnkey” job for that amount. It was further agreed that the material included in the order should be shipped within a week’s time. On the other hand, appellant insists that no such agreement as appellees claim was made. Call and the salesman testify that when appellees requested that the cost of the labor and material be reduced to $13,000.00 the salesman replied that he had no authority to make any reduction in the price of the material, but Call then spoke up and agreed to do- the installation for $500.00 less than he had at first offered and so as to make the total job cost the appellees $13,000.00. They both emphatically state that there was no joint agreement on the part of the appellant and Call to furnish and install the material, but that the agreement to furnish the material by appellant was separate and distinct from the agreement to install it by Call. The}?- further testify that nothing was said or agreed about the time when the material was to be shipped or delivered. Thereafter the salesman sent the order for the material in to the office of appellant, but nothing appeared on this copy about the labor, installation or date of shipment. The manager of appellant’s branch at Huntington accepted the order as received by him and shipped the material in entire ignorance of any of appellees’ claims about a “turnkey” job or date of shipment. It is satisfactorily shown in the evidence that the material was not all delivered until the latter part of August or the early part of September, and that the appellees could not go ahead with their building until they had received such material. They then brought this suit against the appellant and Call, in which they averred that Call and the appellant had jointly agreed and contracted to furnish the material and install the plumbing system in appellees’ hotel; that appellant and Call had jointly agreed to deliver the material not later than the 9th day of May, 1923; that they and each of them had failed to deliver this material until the 25th of August, 1923, and that by reason of this delay appellees had *256 been damaged in the sum of $2,999.00. There also was a claim set np in an amended petition for fanlty installation, bnt this claim was later dismissed at the trial. After a demurrer to the petition had been overruled, appellant answered traversing the appellees’ petition and affirmatively pleading that the appellees had placed this order with appellant through a traveling salesman, who was without authority to make any such contract as appelleesclaimed. The answer of Call was simply a traverse. By agreement the affirmative allegations in the answer of the appellant were traversed of record and the case went to trial on the issues as thus raised. The jury returned a verdict against appellant in the sum of $1,600.00, and from the judgment entered on that verdict this appeal is prosecuted.

Both at the close of the appellees’ case and at the close of the whole case the appellant made a motion for a peremptory instruction, which the court overruled. In this we think the court erred. The appellees knew?- at the time they were negotiating with appellant’s salesman that the appellant was engaged in the business of selling plumbing material and fixtures. The appellees also knew that they were dealing with the 'appellant through a traveling salesman. It is well established law that in the absence of express authority to the contrary a traveling salesman’s authority is limited to the soliciting of orders and transmitting them to his principal and that he has no implied authority to bind his principal by an absolute sale or contract. The authorities from this court supporting this principle are collected in the case of Nolin Milling Co. v. White Grocery Co., 168 Ky. 417, 182 S. W. 191. In this case, quoting from the- earlier case of John Matthews Apparatus Co. v. Renz & Henry, 22 Ky. Law Rep. 1528, 61 S. W. 9, we said:

“We -consider that the main and -only necessary question for us to determine is whether the transaction in question was a contract, or merely an offer or order, which either party was at liberty to decline before final acceptance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. Hollywood Race Ass'n
221 P.2d 558 (New Mexico Supreme Court, 1950)
Ritter v. Kentucky-Tennessee Light & Power Co.
151 S.W.2d 435 (Court of Appeals of Kentucky (pre-1976), 1941)
Chevrolet Motor Co. v. Pieper's Trustee
132 S.W.2d 926 (Court of Appeals of Kentucky (pre-1976), 1939)
Montgomery Ward & Co. v. Arbogast
81 P.2d 885 (Wyoming Supreme Court, 1938)
Flynn's v. Mullett
70 S.W.2d 978 (Court of Appeals of Kentucky (pre-1976), 1934)
International Shoe Co. v. Johnson
67 S.W.2d 505 (Court of Appeals of Kentucky (pre-1976), 1933)
Consolidated Grocery Co.'s Trustee in Bankruptcy v. Hadad
53 S.W.2d 951 (Court of Appeals of Kentucky (pre-1976), 1932)
Stevens v. Bailey
15 S.W.2d 263 (Court of Appeals of Kentucky (pre-1976), 1929)
Louisville Cement Co. v. Clell Coleman & Sons
300 S.W. 633 (Court of Appeals of Kentucky (pre-1976), 1927)
Peaslee-Gaulbert Company v. Rogers
295 S.W. 137 (Court of Appeals of Kentucky (pre-1976), 1927)

Cite This Page — Counsel Stack

Bluebook (online)
278 S.W. 583, 212 Ky. 253, 1925 Ky. LEXIS 1115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-sanitary-manufacturing-co-v-stump-kyctapphigh-1925.