Standard Iron Works v. Globe Jewelry & Loan, Inc.

330 P.2d 271, 164 Cal. App. 2d 108, 1958 Cal. App. LEXIS 1585
CourtCalifornia Court of Appeal
DecidedOctober 10, 1958
DocketCiv. 5873
StatusPublished
Cited by15 cases

This text of 330 P.2d 271 (Standard Iron Works v. Globe Jewelry & Loan, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Iron Works v. Globe Jewelry & Loan, Inc., 330 P.2d 271, 164 Cal. App. 2d 108, 1958 Cal. App. LEXIS 1585 (Cal. Ct. App. 1958).

Opinion

GRIFFIN, P. J.

Plaintiff-respondent Standard Iron Works, a corporation (hereinafter referred to as Standard) brought this action for damages against defendants and appellants Globe Jewelry and Loan, Inc., a corporation (hereinafter referred to as Globe), Globe Properties, and Harold Steekel, for claimed breach of contract. It was stipulated at the trial that in all dealing by defendant Steekel he was acting as agent and as an officer of defendant Globe and Globe Properties, and that said businesses were owned by Steekel and his wife.

Plaintiff corporation is engaged in the structural steel fabricating business in San Diego. Defendants owned unimproved property at the northwest corner of Fifth and Date streets, and in the latter part of 1955 they contemplated constructing a three-story office building thereon. They employed a Mr. Wheeler, an architect, to prepare architectural drawings for such a building, and he in turn employed one Ruskin, a structural engineer, to prepare the structural drawings. In January, 1956, these plans and drawings, providing for a three-story steel frame building with concrete basement were released for bid to certain general contractors, including one C. S. Larsen, who was the lowest bidder. Plaintiff had previously been furnished with the architectural and structural drawings for bidding on the steel work.

On February 10, 1956, when it was still contemplated by defendants that a general construction contract would be let to Larsen, a meeting, wherein Mr. Ruskin, Larsen, Steekel and his wife, one Seltzer, attorney for defendants, and one Dearth, vice president and representative of plaintiff were present, was held for the purpose of obtaining a contract for the structural steel necessary for the building. At that time there existed a steel shortage, and a threatened strike in the steel plants. Defendant Globe had a lease agreement with an insurance company to lease one-third of the floor space of the building, when completed, with a deadline of June, 1956. Its loan *111 ing agency required that at least 70 per cent of all space be leased by that time. Dearth had been requested by Larsen to attend this meeting. Based upon the architectural and structural drawings he was asked to submit two separate prices for the steel contract, one price for three floors and the other for two floors. Expecting that the contract would be entered into with Larsen as general contractor, plaintiff’s proposal (Exhibit 1) was originally made out for Larsen’s acceptance. At the meeting Dearth then learned that Larsen had not, as yet, been given the general construction contract. Apparently Steekel was reluctant to sign plaintiff’s proposal but because of the urgency for commencing construction of the building, and to be assured that the steel would be available as needed, he did, upon the advice of his counsel, sign the proposal at this meeting. Although Dearth claims that after he arrived he heard nothing about uncertainty in securing a loan to finance the entire contract, it appears that the question did arise. The necessity of obtaining the steel for a three-story building was uppermost in their minds and a conversation ensued as to the proper method of obtaining it. Apparently defendants agreed that plaintiff could go into the open market and obtain it at warehouse prices (a higher price) rather than at the mill (at lower prices with considerable delay in filling orders) and that plaintiff was authorized by the agreement signed to do so. The only question which remained in any doubt was a possible oral change in their plans as to whether plaintiff would proceed with the contract on the agreed basis of a three-story building or on the basis of a two-story building, and whether defendants were to notify plaintiff of their election “within a few days” (two or three). There is considerable confusion in the evidence on this subject and it is one of the principal arguments of defendants that the contract was uncertain and indefinite because defendants never informed plaintiff of their election, and that accordingly the contract (Exhibit 1) could not be a basis for a cause of action for claimed breach since its effectiveness was conditioned upon defendants ’ determining “within a few days” whether a two-story or a three-story building was to be erected. They cite such authority as Autry v. Republic Productions, Inc., 30 Cal.2d 144, 151 [180 P.2d 888]; Avalon Products, Inc. v. Lentini, 98 Cal.App.2d 177, 179 [219 P.2d 485]; Talmadge v. Arrowhead Reservoir Co., 101 Cal. 367 [35 P. 1000]; Lawrence Block Co. v. Palston, 123 Cal.App.2d 300, 308 [266 P.2d 856]; and *112 Mainieri v. Magnuson, 126 Cal.App.2d 426, 428 [272 P.2d 557].

The original contract (Exhibit 1) reads in part as follows:

“Standard Iron Works
“Proposal Date February 10, 1956 “Estimate No. 9374 — 1 & 2 “Job Globe Properties “Architect R. G. Wheeler and John Ruskin
Globe Properties, Inc.
“To C-ttA—Larsen 228 Broadway “■2057-lSurtz D. G. Dearth
“San Diego, California
“We agree to furnish, subject to the conditions on reverse side of this proposal:
Structural steel framing on the following basis:
‘ ‘ 3 Floors steel framing, no basement . . .
Erected in place Tax included sum of $56,400.00 “2 Floors steel framing, no basement . . .
Erected in place Tax included sum of 43,871.00 “These prices are based on quick delivery and all material coming from warehouses as source of supply.
“The foregoing pre-arehitectural sheets 1-9 dated 1/11/56; structural sheets S. — S ” dated 1/11/56 prepared by R. G. Wheeler (Signed) D. G. Dearth
“Terms: Progressive monthly payments, Net, 10th of month following date of' invoice.
“I (we) hereby accept the above Proposal this 10 day of Feb., 1956.
“Standard Iron Works “By Don G. Dearth “Sales Manager
“Globe Properties
“By Harold Steckel, Secy.”

The conditions referred to, on the reverse side of the proposal, are:

“This proposal contemplates the furnishing of steelwork in *113 strict accordance with and by the conditions and terms of the specifications and code of standard practice as adopted by the American Institute op Steel Construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lorrie Poublon v. C.H. Robinson Co.
846 F.3d 1251 (Ninth Circuit, 2017)
Tarquinio v. Franklin-McKinley School District
88 Cal. App. 3d 832 (California Court of Appeal, 1979)
Coleman Engineering Co. v. North American Aviation, Inc.
420 P.2d 713 (California Supreme Court, 1966)
B. C. Richter Contracting Co. v. Continental Casualty Co.
230 Cal. App. 2d 491 (California Court of Appeal, 1964)
Cutter Laboratories, Inc. v. Twining
221 Cal. App. 2d 302 (California Court of Appeal, 1963)
Blackburn v. Allen
218 Cal. App. 2d 30 (California Court of Appeal, 1963)
Bohman v. Berg
356 P.2d 185 (California Supreme Court, 1960)
King v. Associated Construction Corp.
183 Cal. App. 2d 818 (California Court of Appeal, 1960)
Kolton v. Nassar
99 N.W.2d 362 (Michigan Supreme Court, 1959)
Uhlmann v. North Whittier Highlands, Inc.
334 P.2d 1022 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
330 P.2d 271, 164 Cal. App. 2d 108, 1958 Cal. App. LEXIS 1585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-iron-works-v-globe-jewelry-loan-inc-calctapp-1958.