Standard Bank, Plc v. Runge, Inc.

443 F. App'x 347
CourtCourt of Appeals for the Tenth Circuit
DecidedOctober 6, 2011
Docket10-1045
StatusUnpublished
Cited by3 cases

This text of 443 F. App'x 347 (Standard Bank, Plc v. Runge, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Bank, Plc v. Runge, Inc., 443 F. App'x 347 (10th Cir. 2011).

Opinion

ORDER AND JUDGMENT *

TERRENCE L. O’BRIEN, Circuit Judge.

Standard Bank, PLC appeals from the district court’s grant of summary judgment in favor of engineering firm Runge, Inc., d.b.a. Pincock, Allen & Holt (PAH). Standard filed tort claims against PAH for preparing an allegedly flawed viability report in connection with Standard’s financing of a coal mine that went bankrupt. The district court concluded the claims were barred by the economic loss rule. We affirm.

BACKGROUND

In 2005, Bronco Hazleton, Co., a wholly owned subsidiary of Bronco Energy Fund, Inc. (Bronco) entered into a contract to purchase the Hazleton coal mine in Indiana for $25 million. Royal Bank of Scotland (RBS), which was to provide the financing for the deal, required an evaluation by an independent engineer as part of its due diligence. To that end, RBS contacted PAH and instructed it to deal directly with Bronco. When Bronco retained PAH as the independent engineer, it made an immediate payment of $35,000 to be credited toward PAH’s fees.

The contract 1 between Bronco and PAH required PAH to perform its work at Ha-zleton “in accordance with the standard of care of its profession, which means generally accepted professional practices, in the same or similar localities, related to the nature of the work accomplished, at the time the services are performed.” (R. Vol. 6 at 1188.) It limited PAH’s total liability to the greater of the- amount of fees paid under the contract or $50,000 but offered the possibility of increased exposure to liability in exchange for a higher fee. The contract explicitly said no third party beneficiaries were intended and required each party to obtain written permission from the other before disclosing the contents of the report to outsiders. PAH presented a preliminary report to Bronco in August 2005. [Vol. 1 at 32] Included in the report was pointed language saying Bronco had retained PAH and “PAH has prepared this report for use by RBS as RBS evaluates the merits of the Hazelton venture.” (R. Vol. 1 at 37).

RBS pulled out of the deal on September 26, 2005, the day before closing. A few days later, an independent broker mentioned the deal to Standard, which stepped in to provide financing. Internal documents show Standard was projecting a 69% internal rate of return on the trans *349 action. Standard, like RBS, required a report from an independent engineer. RBS “release[d]” the contractors it had used to perform the due diligence, including PAH, to Standard. (R. Vol. 7 at 1513.) In November 2005, PAH submitted a report nearly identical to the one provided to RBS. It was “[prepared for Standard” and the recitals were amended to read, “PAH, in its role as IE [independent engineer], intends that this report will be used by Standard as Standard evaluates the merits of the Hazelton venture.” (R. Vol. 1 at 98,103.) The total amount of the loan was $35 million. The transaction closed in December 2005 and PAH’s outstanding fees were paid out of the funds Standard loaned to Bronco, but listed under “Lender Transaction Expenses.” (R. Vol. 7 at 1461.)

In January 2006, Standard started the process of syndicating the loan. In connection with its plan to market the project to other banks, it asked PAH to change the recitals in its report. Standard wanted the language saying Bronco had retained PAH to be replaced by language less likely to cause other banks to be concerned about PAH’s independence. PAH complied. Its new report contained no reference to Bronco having retained it; instead it simply said PAH had been retained as an independent engineer to perform work on behalf of Standard and other potential lenders evaluating the mine. Standard was unable to syndicate the loan because the mine soon failed and Bronco declared bankruptcy in May 2006, less than six months after the purchase.

By March 2006 serious problems with the mine became evident. Standard alleges the problems should have been, but were not, flagged in PAH’s report. 2 Standard retained another engineering firm to reevaluate the mine (that firm, incidentally, limited its liability to Standard to the amount of its fee). Standard attempted to rescue the mine by providing Bronco with debtor-in-possession financing. The efforts were unsuccessful.

In September 2007, Standard sued PAH for negligent misrepresentation and professional negligence. The parties later filed cross-motions for summary judgment. Concluding the economic loss rule barred Standard’s claims, the district court entered summary judgment in favor of PAH.

DISCUSSION

“We review a grant of summary judgment de novo.” Grantham v. Ohio Cas. Co., 97 F.3d 434, 435 (10th Cir.1996) (citation omitted). Whether Colorado’s economic loss rule applies to bar a claim is a question of law also subject to de novo review. 3 Level 3 Commc’ns, LLC. v. Liebert Corp., 535 F.3d 1146, 1162 (10th Cir.2008).

The Colorado Supreme Court adopted the economic loss rule in Town of Alma v. AZCO Construction, 10 P.3d 1256, 1264 (Colo.2000). “[A] party suffering only economic loss from the breach of an express *350 or implied contractual duty may not assert a tort claim for such a breach absent an independent duty of care under tort law.” Id. “The scope of this rule includes third-party contract beneficiaries who may have a cause of action for breach of contractual duties.” Id. at n. 12. The application of the rule focuses on the source of the duty alleged to have been breached. Id. at 1263.

In Town of Alma, the town and several individuals sued AZCO for shoddy workmanship on the town’s water distribution system. Id. at 1258. Appearing to depart from an earlier trend in its case law, the Colorado Supreme Court decided the economic loss rule barred the plaintiffs’ tort claims. Id. at 1264-65. The court concluded the claims were based on the duties stated in the construction contract and not on an independent tort duty. Id. at 1264. As it was the first case to apply the economic loss rule, the court felt the need to reconcile its earlier, seemingly inconsistent, cases, which did not discuss (or even mention) the rule. It distinguished the cases on the following bases: (1) the common law duty underlying the tort in one case was not limited where the contract did not address the duty of care (the standard of workmanship); (2) the duty underlying the tort in another was entirely separate from the duty created by the contract between the parties, and (3) in the third case policy concerns required finding a builder had an independent duty to act without negligence in constructing a residence. 4 Id. at 1265-66.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
443 F. App'x 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-bank-plc-v-runge-inc-ca10-2011.