Standard American Dredging Co. v. City of Oakland

262 F. 315, 1920 U.S. App. LEXIS 1561
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 5, 1920
DocketNo. 3336
StatusPublished

This text of 262 F. 315 (Standard American Dredging Co. v. City of Oakland) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard American Dredging Co. v. City of Oakland, 262 F. 315, 1920 U.S. App. LEXIS 1561 (9th Cir. 1920).

Opinion

HUNT, Circuit Judge.

This action involves the construction of certain clauses of a dredging contract between the Dredging Company, plaintiff in error, and the city of Oakland. The contract called for work specified as sections A, B, and C, and the present litigation arises out of work done within what is called section C, an approach channel in Oakland harbor. The specifications required that the approach channel here involved should be dredged to a depth of 25 feet below low tide, the bottom width to be not less than 300 feet, and that the cut in the section (C) should be continuous from the southeasterly end of section B. “Top widths of said section shall be such as slopes may assume.” Included in the specifications was the following paragraph;

“Material dredged from below the specified depths or from beyond the specified areas as marked out by the city engineer, and side slopes therefrom at rates not flatter than one vertical to four horizontal, will be estimated at half the actual volume of excavation and paid for accordingly: Provided, however, that no payment mil be made for material dredged from below a depth of one Coot below the specified depth, nor from a distance of more than ten feet beyond said flattest limits of slope for said specified areas to be dredged. All material must be removed down to the depths specified over the whole area to be dredged.”

Over 37,000 cubic, yards of. material were excavated on the side slopes in the area not flatter than one vertical to four horizontal, which was estimated at half the actual volume of excavation and paid [316]*316for accordingly. The Dredging Company contended that it was entitled to full rates, but the District Court found in favor of the defendant city.

The annexed diagram, Figure 1, illustrates the situation, and we use the general explanation of the situation given in another, but similar, case hereinafter cited.

In the cut a section of vertical plan of the channel is represented. The rectangle A B C D represents the specified area as marked out by the city engineer, having a width of 350 feet and vertical sides of 25 feet in height. By the plan the dredging is to be performed within this area and the material is to be removed therefrom; the side “slopes” being such as the material naturally “assumes” in the course of operations. The lines E B, K B, D B, M B, N B, Q D, P D, and F D represent some of the side slopes from the specified area assumed by the material in the course of the dredging operations; B E and F D being lines at the angle of one vertical to four horizontal, the flattest limits for each payment as allowed. The actual side slopes, however, may lie without this limit, and the lines G, H, H I, and I J represent the extreme of pay work; that is to say, an excess depth of one foot and an access width on each side of the channel of 10 feet beyond the one by four slope. The line R S is drawn to indicate the actual channel dredged, as was in places the case, beyond the horizontal and vertical limits for which payment could be made.

No dispute arises concerning excavation performed within the area of main channel A B C D. Certain other matters as to payments for material are conceded, so that the question for decision narrows to this: Is payment due for material dredged from the side slopes that is not within the lines EBACDF upon the basis of full measurement or half measurement of the quantity removed?

In the solution of the matter we have been greatly aided by the careful and analytical opinion of the District Court of Appeal of California in Standard American Dredging Co. v. City of Oakland, 30 Cal. App. 237, 157 Pac. 833, an action involving the same question upon the same contract and between the same parties as are now herein before the court; the only difference being that the suit in the state court was brought to recover upon a different installment claimed to be due. After discussion of the features of the contract work, the .court, through Judge Chipman, said:

"It seems to us that the natural and grammatical construction of the specifications is, as claimed by defendant, and as was held by the lower court, that three classes of material were to be subjected to half measurement and paid for accordingly, namely: ‘(1) Material dredged from below the specified [317]*317depth’; that is, depths that were definitely fixed — as in the charnel. ‘(2) Material dredged from the specified area as marked out by the city engineer': that is. beyond the fixed lines of the channel. “(3) Side slopes therefrom (from the specified area) at rates not ilatter than one vertical_to four horizontal, with a proviso that no payment, would be made for material dredged beyond certain vertical and horizontal lines.’ That is, the phrase, ‘will he estimated at half the actual volume of excavation,’ is qualified by what precedes it and relates to dredging ‘below specified depths,’ to dredging ‘from beyond the specified areas,’ and to ‘side slopes therefrom [from the specified area] at rates not flatter than one vertical to four horizontal.’ And the limiting clause which follows seems to confirm this view, for it expressly provides ‘that no payment will be made for material dredged from a depth of one foot below the specified depth nor from a distance of more than 10 feet beyond said flattest limits of slope for said specified areas to be dredged.’ The parties understood that side slopes were inevitable, and dredging to some extent below specified depths, for the exact depth could not always be maintained, and so a limit as to depth beyond which no payment would be made was provided for. and a one-half rate was fixed for dredging on slopes not flatter than one to four, and no payment would be made for material dredged ‘from a distance of more than 10 feet beyond’ this slope of one to four. We are unable to accept plaintiff’s construction, for by it there would be no material subject to half measurement, except such as was situated beyond the area specified by the city engineer and also beyond ‘the side slopes therefrom.’ Grammatically, as the specifications are phrased and punctuated, the verb ‘will he estimated’ had for its subject material ‘from beyond the specified depths’ and from beyond the specified areas, and, as a further subject, the ‘side slopes.’ ”

The Dredging Company argues that the meaning of the contract and specifications is that the words “specified area” necessarily refer to the area theretofore specified in the specifications, namely, the area included between the bottom width of 350 feet and the top width such as the slopes may assume. They also say that difficulty with respect to the words “specified areas” has arisen from the parenthetical insertion of the words “as marked out by the city engineer” between the words “specified areas” and the words “side slopes therefrom,” and they contend that the disjunctive “or” separates the phrase “material dredged from below the specified depths” from tfie phrase “material dredged from beyond the specified areas,” and that the conjunctive “and” conjoins the phrase “material dredged from beyond the specified areas” with the phrase “side slopes therefrom.”

We cannot adopt this reasoning. The omission to include the word “beyond” before the words “side slopes” indicates that the parties did not intend to provide that the material subject to half measurement should be only that which was removed from an area lying both beyond the specified areas as marked out by the city engineer and beyond the side slopes therefrom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard American Dredging Co. v. City of Oakland
157 P. 833 (California Court of Appeal, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
262 F. 315, 1920 U.S. App. LEXIS 1561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-american-dredging-co-v-city-of-oakland-ca9-1920.