Stabile v. McCarthy

145 N.E.2d 821, 336 Mass. 399, 1957 Mass. LEXIS 654
CourtMassachusetts Supreme Judicial Court
DecidedNovember 13, 1957
StatusPublished
Cited by51 cases

This text of 145 N.E.2d 821 (Stabile v. McCarthy) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stabile v. McCarthy, 145 N.E.2d 821, 336 Mass. 399, 1957 Mass. LEXIS 654 (Mass. 1957).

Opinion

Cutteb, J.

This is an action to recover a deposit made at the time of the signing by the plaintiff, on February 11, 1955, of an agreement for the purchase of twenty-seven acres of land in Wilmington. The deed was to be delivered, and the balance of the purchase price paid, on April 22,1955.

The agreement contained the following special provision: “This agreement is subject to the right of the buyer in the event that he shall have been unable to obtain the approval of. the Wilmington Planning Board of his proposed subdivision .of the . . . premises prior to the date ... set for performance ... at his option to cancel this agreement and claim the return of his deposit, in which event this agreement shall terminate without further obligation on the part of either party

The plaintiff waived formal tender of the deed by the defendants and sought, under the provision just quoted, to cancel the agreement and obtain return of the deposit. This the defendants refused.

The relevant testimony, summarized in the bill of exceptions, was to the following effect. The plaintiff, after Febru *401 ary 11,1955, caused an engineer to prepare a “working plan” of subdivision of the land, showing twenty-nine house lots on twenty-seven acres. This plan, as introduced in evidence, still had “considerable engineering work ... to be done” on it before it could be presented for the board’s approval. The plaintiff and others had six conversations with the building inspector of Wilmington, at one of which the engineer was present. Although he attempted to meet with the planning board, he did not succeed in speaking with all members of the board between the date of the execution of the agreement and the date set for passing papers. He did meet twice with the town manager and once with a health officer of the town known as the sanitarian.

As a result of his talk with the sanitarian, who gave him instructions on test procedures, the plaintiff made percolation tests (which the sanitarian declined to make himself because no definitive plan approved by the planning board had been referred to the board of health) at various points on the land to determine its suitability for septic tanks and cesspools. Some of these tests met the standards outlined to him by the sanitarian and some did not.

The plaintiff made no formal application to the planning board for approval of his subdivision plan between February 11 and April 22, 1955. The plan could not be approved by the planning board because it showed that each of seven out of twenty-nine lots had an area of less than the 22,500 square feet per lot required by the planning board’s regulations. The plaintiff failed to go forward with his plan because “the results of the percolation tests were so poor that he didn’t believe the plan could be accepted.” He stated that “he concluded that his . . . tests would be unacceptable as a result of his conversations 1 with the . . . sanitarian and his meetings with . . . the building inspector.”

*402 The sanitarian testified in substance that the percolation tests made by the plaintiff were performed (except for the season in which they were made) in customary manner and that some of them indicated that septic tanks installed on part of the land in its then state would not have functioned properly. However, there is no indication in the record that the sanitarian saw the results of the tests prior to April 22, 1955, the date set for the conveyance. Regulations of the planning board provide that no residential subdivision will be approved unless the board determines, after adequate investigation by the sanitarian, that the land can be used for residential purposes without danger to health.

The case was heard by a judge of the Superior Court sitting without a jury. He made subsidiary findings of fact and an ultimate finding for the plaintiff in an amount slightly in excess of the deposit. The defendants duly saved excep-. tians (a) to the trial judge’s refusal to give their sixth requested ruling that there was “no evidence ... to warrant a finding that the plaintiff made a reasonable effort to obtain the approval of his . . . subdivision by the” board and (b) to the trial judge’s conclusion 2 that “on all the evidence . . . the plaintiff was excused from . . . further effort to make a plan . . . because of the virtual condemnation of the site by the sanitarian and his declaration that the board of health would not approve it.”

1. The plaintiff in his brief in effect concedes that he was bound to use reasonable efforts to obtain planning board approval. The trial judge so ruled. The ruling was correct. The special provision, although ambiguous, was inserted to free the plaintiff of obligation to purchase by giving the plaintiff the power to cancel the agreement, upon the hap *403 pening of a condition precedent, namely, “that he shall have been unable to obtain the approval of the . . . planning board” (emphasis supplied).

The parties quite clearly intended a binding contract to purchase, not- a mere option (compare Proctor v. Union Coal Co. 243 Mass. 428, 432; C. J. Hogan, Inc. v. Atlantic Corp. 332 Mass. 322, 328) in the plaintiff to purchase without any obligation of affirmative action on his part. If the parties had intended no obligation on the plaintiff to take action they could have used a clause in the special provision importing no suggestion of obligation, inability or impossibility, or could have made the vendor’s obligation to convey and the vendee’s obligation to purchase “subject to” the granting of approval (compare Connor v. Rockwood, 320 Mass. 360; Livoli v. Stoneman, 332 Mass. 473, 475-476), instead of making inability to obtain planning board approval a condition precedent to the exercise of a right to cancel.

Since no subdivision plan existed when the agreement was signed, the plaintiff, in order to cancel, must show more than inability to obtain approval of a particular then existing plan. It must have been contemplated that he would prepare a plan conforming (as the plaintiff’s rough working plan did not) to the basic applicable zoning laws and planning board regulations, and that he would try reasonably to obtain planning board approval (if necessary, with adjustments, not involving disproportionate expense, to meet the board’s views) prior to the date set for the conveyance. Under the circumstances, the special provision implied that the plaintiff must do at least this much, before the condition precedent (inability to obtain approval) to cancellation would be satisfied. See Sorota v. Baskin, 334 Mass. 123 (especially request numbered 1 set forth at page 124, footnote 1, mentioned with approval at page 126). See also Lach v. Cahill, 138 Conn. 418, 422; Corbin, Contracts, § 570. Compare Eno Systems, Inc. v. Eno, 311 Mass. 334, 339; Eastern Paper & Box Co. Inc. v. Herz Manuf. Corp. 323 Mass. 138, 141-142.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCullough v. Chase Great Marsh LLC
Massachusetts Land Court, 2021
Ching v. Case
449 P.3d 1146 (Hawaii Supreme Court, 2019)
Banco Do Brasil, S.A. v. 275 Washington Street Corp.
889 F. Supp. 2d 178 (D. Massachusetts, 2012)
Rowan Companies, Inc. v. Wilmington Trust
305 S.W.3d 698 (Court of Appeals of Texas, 2010)
Boynton Yards Associates I, LLC v. Boynton Yard Lofts, LLC
25 Mass. L. Rptr. 205 (Massachusetts Superior Court, 2009)
TransCanada Power Marketing Ltd. v. Narragansett Electric Co.
542 F. Supp. 2d 127 (D. Massachusetts, 2008)
Love v. Pratt
833 N.E.2d 674 (Massachusetts Appeals Court, 2005)
Allen v. Kennedy
2003 Mass. App. Div. 185 (Mass. Dist. Ct., App. Div., 2003)
Bardon Trimount, Inc. v. Guyott
732 N.E.2d 916 (Massachusetts Appeals Court, 2000)
Wojtkun v. Dewolfe New England
12 Mass. L. Rptr. 149 (Massachusetts Superior Court, 2000)
Mervis v. Elm Street Realty Trust
1999 Mass. App. Div. 50 (Mass. Dist. Ct., App. Div., 1999)
Kulakowski v. Leavitt
1996 Mass. App. Div. 159 (Mass. Dist. Ct., App. Div., 1996)
Raphael v. Nagog Realty Corp.
1994 Mass. App. Div. 224 (Mass. Dist. Ct., App. Div., 1994)
Goodman v. Blum
1993 Mass. App. Div. 88 (Mass. Dist. Ct., App. Div., 1993)
Gilmore v. Dynamic U.S.A., Inc.
1992 Mass. App. Div. 100 (Mass. Dist. Ct., App. Div., 1992)
Renovest Co. v. Hodges Development Corp.
600 A.2d 448 (Supreme Court of New Hampshire, 1991)
Lopes v. Piacentini
551 N.E.2d 64 (Massachusetts Appeals Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
145 N.E.2d 821, 336 Mass. 399, 1957 Mass. LEXIS 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stabile-v-mccarthy-mass-1957.