St. Paul Fire & Marine Insurance v. Wittman Mechanical Contractors, Inc.

263 F. App'x 290
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 6, 2008
Docket06-2031
StatusUnpublished

This text of 263 F. App'x 290 (St. Paul Fire & Marine Insurance v. Wittman Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Paul Fire & Marine Insurance v. Wittman Mechanical Contractors, Inc., 263 F. App'x 290 (4th Cir. 2008).

Opinion

PER CURIAM:

On the morning of January 12, 2004, Wittman Mechanical Contractors, Inc., the mechanical subcontractor on a new house under construction in Loudoun County, Virginia, activated a propane gas line feeding the gas system in the house and turned on the furnace. Approximately one hour later, an explosion occurred, destroying the house. Experts concluded that the explosion resulted from a gas leak at the connection between the main gas pipeline in the basement and the spur gas pipeline running up to the kitchen island cooktop on the first floor.

Under the “scope of work” provision in the contract between Wittman Mechanical and the general contractor, Wittman Mechanical was responsible for installing and starting up the furnace, but it was not responsible for installing the gas pipeline system or testing it for leaks before the system was activated. Nonetheless, Witt-man Mechanical activated the gas pipeline system at the request of the general contractor and, before activating the system, did not test for leaks in the system.

The general contractor’s insurance company, St. Paul Fire & Marine Insurance Company (“St. Paul Insurance”) paid the loss and then commenced this subrogation action against Wittman Mechanical, alleging breach of warranty and negligence in activating the gas system and starting the furnace without testing for leaks.

Following a three-day trial, a jury found in favor of Wittman Mechanical on both claims. The district court, however, granted St. Paul Insurance’s post-trial motion for judgment notwithstanding the verdict, concluding that Wittman Mechanical *292 breached its express warranties by failing to perform a pressure test for leaks. The court thus entered judgment in favor of St. Paul Insurance for $445,685, plus interest.

We conclude on appeal that based on the “scope of work” clause in the subcontract between Wittman Mechanical and the general contractor, Wittman Mechanical was responsible only for a breach of warranty given in connection with installation of the furnace, which required Wittman Mechanical to perform a soap-and-water test * at the connection between the furnace and the gas line system, but not a pressure test on the entire gas pipeline system, which was required only of the contractor doing the gas pipeline work. Accordingly, we conclude that the jury could have concluded, based on the evidence at trial, that any failure by Wittman Mechanical to perform a soap-and-water test was not the cause of the explosion. We therefore vacate the judgment and remand to the district court with instructions to reinstate the verdict and enter judgment for Wittman Mechanical.

I

Wittman Mechanical was hired by Virginia Residential Construction, Inc., as a subcontractor to provide heating, ventilation, and air conditioning services to houses under construction in Loudoun County, including the house in question. Virginia Residential was a residential real estate developer in the Washington, D.C. metropolitan area and was the owner of and contractor for the house in question. The contract between Wittman Mechanical and Virginia Residential included a “scope of work” provision that required Wittman Mechanical to perform only the HVAC work, including the installation and starting of the furnace. But the contract did not include within the scope of the work any work related to installation and testing of the gas pipeline system. The contract provided that all gas pipeline work was to be performed by Peed Piping, another subcontractor retained by Virginia Residential.

After Peed Piping had initially installed the gas pipes in the house, Loudoun County inspectors performed an inspection of the pipes. This inspection required that all gas pipes in the house first be tied to an appliance, be capped off, or have a shut off valve. The county inspectors performed a pressure test to detect any leaks in the system by injecting a specified amount of air pressure into the pipes. Because the pipes held the pressure for 24 hours, the house’s system passed inspection and was approved in October 2003. Approximately three months passed, during which a spur gas line running from the main gas pipeline in the house’s basement to the island cooktop in the kitchen became disconnected. It was at this connection between the main gas pipeline and the spur line from which gas leaked, causing the explosion on January 12, 2004.

On the morning of January 12, 2004, Robert Casteel and Lloyd Henry Dignazio, employees of Wittman Mechanical, arrived at the house to install brackets for air conditioning units. At some point during the morning, Virginia Residential’s superintendent at the site, Russell Rolle, asked Casteel to start the furnace for warmth. By that time, Wittman Mechanical had already installed the furnace but had not started it up. After receiving permission from his supervisors at Wittman Mechanical, Casteel opened the line at the furnace *293 to bleed out air that could prevent the furnace from stai'ting. On doing this, he felt no pressure and smelled no gas, indicating to him that the line from the propane tank had not yet been activated. When Casteel advised Rolle of this fact, Rolle asked Casteel to activate the gas line leading from the propane tank to the house. This task, however, was one that did not fall within the scope of work for Wittman Mechanical. Nonetheless, feeling pressure from Rolle, Casteel called Witt-man Mechanical’s main office and asked permission to activate the line. Wittman Mechanical’s operations manager authorized Casteel to activate the line once he was informed that Rolle had assured Casteel that the gas pipeline system was ready to receive propane gas. Wittman Mechanical’s operations manager testified at trial that he had assumed that, based on Rolle’s request to activate the system and his assurance that the system was in good condition and ready to receive propane gas, Rolle was accepting responsibility for any adverse consequences that might arise from the activation of the system.

After conducting a visual inspection of the gas appliances in the house to confirm that the gas line valves were set in the off position, Casteel activated the propane gas line and started the furnace in the basement. In starting the furnace, Casteel did not perform any type of leak test, nor did he consult the manufacturer’s instruction manual that came with the furnace itself, testifying that he had never done so. He also testified that he was not aware of any codes or industry standards that he was required to follow before or after turning on the gas and starting the furnace.

The explosion occurred approximately one hour after Casteel activated the gas line and started the furnace.

Following the explosion, St. Paul Insurance, who was the insurer of Virginia Residential, paid Virginia Residential’s insurance claim and commenced this subrogation action against Wittman Mechanical for breach of warranty and negligence. After the jury returned a verdict in favor of Wittman Mechanical on both claims, St. Paul Insurance moved for a judgment under Federal Rule of Civil Procedure 50, and the district court granted the motion, awarding St. Paul Insurance $445,685, with interest at 9 percent from January 12, 2004.

Wittman Mechanical filed this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenkins v. Pyles
611 S.E.2d 404 (Supreme Court of Virginia, 2005)
Sawyer v. Comerci
563 S.E.2d 748 (Supreme Court of Virginia, 2002)
Baynard v. Malone
268 F.3d 228 (Fourth Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
263 F. App'x 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-paul-fire-marine-insurance-v-wittman-mechanical-contractors-inc-ca4-2008.