St. Louis S. F. R. Co. v. Farmers' Union Gin Co.

1912 OK 505, 125 P. 894, 34 Okla. 270, 1912 Okla. LEXIS 394
CourtSupreme Court of Oklahoma
DecidedJuly 18, 1912
Docket1425
StatusPublished
Cited by16 cases

This text of 1912 OK 505 (St. Louis S. F. R. Co. v. Farmers' Union Gin Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Louis S. F. R. Co. v. Farmers' Union Gin Co., 1912 OK 505, 125 P. 894, 34 Okla. 270, 1912 Okla. LEXIS 394 (Okla. 1912).

Opinion

Opinion by

HARRISON, C.

(after stating the facts as above). There are two distinct causes of action alleged. The court instructed the jury on each. The jury returned a general verdict for $1,000. No objection is urged against the form of the verdict; hence the defective features are deemed to have been waived. While not saying whether a judgment based upon such a verdict would be reversed if properly presented, yet we would suggest that a better practice in suits of this character would be to return separate findings as to each separate cause of action. ^

“In general, where two causes of action are submitted to the jury at the same time, a general verdict for the plaintiff should not be returned.” (22 PI. & Pr. 849.)

It is a settled rule in Missouri that this form of verdict is reversible error. In Seibert et al. v. Allen, 61 Mo. 482, Justice Hough, in delivering the opinion of the court on this question, says:

*274 “There were two "counts, each containing a separate and distinct cause of action, and a single verdict would have been improper. In Mooney v. Kennett, 19 Mo. 554, Judge Scott said: ‘A general finding for the defendant on a petition containing several causes of action may be sustained; but, where the finding is for the plaintiff, every consideration of propriety requires that there should be a verdict in each cause of action, and these will all be blended in one judgment.’ Clark v. Railroad, 36 Mo. 216; Pitts v. Fugate, 41 Mo. 405; Collins v. Dulle, 45 Mo. 269; Bigelow v. Railroad, 48 Mo. 510; Owens v. Railroad, 58 Mo. 394.”

Had there been separate findings in each cause of action in the case at bar, the judgment could have been so modified as to obviate another trial; but in its present form it is impossible to ascertain upon what particular facts the verdict is based. We cannot say what issues were found, or whether the verdict is responsive to all the issues involved, and inasmuch as the jury was instructed to take into consideration improper elements of damage in reaching its verdict, and inasmuch as evidence tending to establish improper elements was admitted, we are constrained to reverse the judgment rather than establish an unsafe precedent.

As to the damages alleged to have been sustained by defendant’s failure to- put in the switch, in the first cause of action, we think each item alleged was a proper element of damage, and that the evidence fairly supports the allegations. It is contended by counsel for plaintiff in error that there was no evidence tending to support the averment that the switch was to be put in within 30 days. Without passing upon this contention, we will sajr that, under the circumstances in this case, it does not matter whether the defendant company made a definite promise to complete the switch in 30 days or not. The railroad company had induced the gin company to locate its plant on the railroad company’s right of way rather than have it located on the right of way of a competing road. Having acceded to defendant’s wishes in this regard, the gin company requested that a switch be laid to the gin site, so as to facilitate the handling of the gin machinery and material; and the shipping of cotton and seed from the gin. The railroad company agreed for a stipulated price to lay the switch. The price was agreed upon and money paid to the com *275 pany on the day the contract was made. The contract was made July 11th and the track was not completed until November 1st. This, in the absence of some plausible excuse, was an unreasonable delay. Under the agreement the gin company was to do the grading necessary for the switch. This was done within ten days after the contract, and in a manner satisfactory to the railroad, and was accepted by the road. The laying of the switch required but one day’s time, after a delay of over three months from the time the grading was completed. And, after the track was laid, there was another delay of. about three weeks in putting in a frog by which the tracks were connected, the putting in of which required only about one hour’s time. This delay, in our judgment, is closely akin to willfulness, and the only excuse offered is that the road had been unable to get the rails any sooner, and that after the rails were laid it required three weeks more to get a frog. This excuse, in the absence of any showing as to what efforts had been made to get them, is not sufficient to justify the delay. The fulfillment of this contract within a reasonable time is implied by law, whether a definite time was fixed by the contract or not. The railroad had full knowledge of the object and purpose of this switch. It had induced the plaintiff to locate its gin at this point in order to procure the shipping of plaintiff’s machinery and material and the products of the gin. It should not be heard to deny knowledge of the purpose of the gin, nor to deny knowledge of the importance of completing the switch within a reasonable time so that the gin could be put in operation by the beginning of the ginning season. The agent of the railroad company who contracted to put in the switch was definitely informed of the importance of having it ready before the arrival of the gin machinery. It was about 40 days after the contract was made before the machinery arrived, and had to be hauled to the gin site by wagons. Inasmuch as. it required but one day to put in the switch when the work was finally begun, in the absence of some showing for the delay, we think the defendant was guilty of negligence and should respond for the damages resulting therefrom.

*276 In the second cause of action, wherein the wrong measure of damages was applied, the elements of which being the expense of maintaining idle hands, expense of a trip to Dallas, amount paid as attorney’s fee, damages done to cotton piled on the ground, and interest on borrowed money, it is contended by plaintiff in error that the loss alleged to have been sustained by piling the cotton on the ground, and the interest paid on the borrowed money with which such cotton was purchased, are not elements of damage for which the law holds defendant liable, for the reason that such losses are too remote and conjectural and were not contemplated by the parties at the time the' shipping contract was made, and that the court erred in admitting evidence in support of such allegations and instructing the jury to take such elements into consideration, in fixing the amount of damage. In support of such contention, a great number of authorities are cited, among the leading of which are: C., R. I. & P. Ry. Co. v. Broe, 16 Okla. 25, 86 Pac. 441; Franklin v. Louisville & N. Ry. Co. (Ky.) 116 S. W. 765; Texas & Pacific Ry. Co. v. Hassell, 23 Tex. Civ. App. 681, 58 S. W. 54; Gulf, C. & S. F. Ry. Co. v. Gilbert, 4 Tex. Civ. App. 366, 23 S. W. 320; Priestly v. Northern Indiana & Chicago Ry. Co., 26 Ill. 205, 79 Am. Dec. 369; C., R. I. & P. Ry. Co. v. Planters' Gin & Oil Co., 88 Ark. 77, 113 S. W. 352; Harvey v. C. & P. R. Co., 124 Mass. 421, 26 Am. Rep. 673.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tulsa Municipal Airport Trust v. National Gypsum Co.
551 P.2d 304 (Court of Civil Appeals of Oklahoma, 1976)
Osborn v. Commanche Cattle Industries, Inc.
545 P.2d 827 (Court of Civil Appeals of Oklahoma, 1975)
Miller v. Judd
1967 OK 140 (Supreme Court of Oklahoma, 1967)
City of Enid v. Crow
1957 OK 211 (Supreme Court of Oklahoma, 1957)
St. Louis-San Francisco Ry. Co. v. Kittrell
1953 OK 38 (Supreme Court of Oklahoma, 1953)
Bunch v. Perkins
1947 OK 149 (Supreme Court of Oklahoma, 1947)
Alton Railroad Co. v. Oklahoma Furn. Mfg. Co.
1942 OK 60 (Supreme Court of Oklahoma, 1942)
Davon Oil Co. v. Steele
1940 OK 27 (Supreme Court of Oklahoma, 1940)
H. F. Wilcox Oil & Gas Co. v. Allen
1937 OK 249 (Supreme Court of Oklahoma, 1937)
Stakis v. Dimitroff
1931 OK 653 (Supreme Court of Oklahoma, 1931)
Lutyen v. Ritchie
218 P. 430 (Idaho Supreme Court, 1923)
Chicago, R, I. & P. R. Co. v. Fontron Loan & Trust Co.
1923 OK 172 (Supreme Court of Oklahoma, 1923)
Rogers v. Benford
1921 OK 343 (Supreme Court of Oklahoma, 1921)
White v. Louisville N. R. Co.
79 So. 508 (Alabama Court of Appeals, 1918)
Chapman v. . Fargo
119 N.E. 76 (New York Court of Appeals, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
1912 OK 505, 125 P. 894, 34 Okla. 270, 1912 Okla. LEXIS 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-louis-s-f-r-co-v-farmers-union-gin-co-okla-1912.