St. Croix Development, Inc. v. City of Apple Valley

446 N.W.2d 392, 1989 Minn. App. LEXIS 1092, 1989 WL 117185
CourtCourt of Appeals of Minnesota
DecidedOctober 10, 1989
DocketC3-89-649
StatusPublished
Cited by10 cases

This text of 446 N.W.2d 392 (St. Croix Development, Inc. v. City of Apple Valley) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Croix Development, Inc. v. City of Apple Valley, 446 N.W.2d 392, 1989 Minn. App. LEXIS 1092, 1989 WL 117185 (Mich. Ct. App. 1989).

Opinion

OPINION

PARKER, Judge.

The City of Apple Valley appeals a trial court judgment ordering it to rezone the subject property according to respondent developers’ petition for an amendment to the city’s zoning ordinance. The developers (St. Croix Development, Inc., Wellington Management, Inc., Steven Wellington and Mary McNellis), purchasers of two adjacent parcels of land in Apple Valley, brought suit for a declaratory judgment after the city denied their request for rezoning. On appeal the city argues that the trial court erred in finding that (1) the developers were proper parties to the petition for rezoning, and (2) the city’s denial of the rezoning request was arbitrary and capricious. We reverse on the latter ground.

FACTS

In February 1988 Steven Wellington, Mary McNellis and Steven Cheney executed a contingent purchase agreement for two undeveloped parcels of land in the City of Apple Valley. Cheney owned the subject property. Wellington and McNellis, officers of two development companies, intended to develop the property as the Palomino Townhouse Project. Wellington, McNellis and McNellis’ husband are the sole shareholders, officers and directors of their development corporations — Welling *395 ton Management, Inc., and St. Croix Development, Inc.

The subject property is adjacent to the intersections of County Road 38, Cedar Avenue and Pennock Avenue. While the property is zoned R-1A (large lot, single-family), the city’s comprehensive land-use plan designates the property as D-2 (residential, 1-6 units per acre) and D-3 (residential, 5-12 units per acre). The use plan assumes the existence of planned infrastructure, including roads. Although the plan shows that County Road 38 is a through street continuing west of the subject property, the county has not completed this road and there are no plans to construct this portion of the road before 1991. The county has not yet set aside funding for County Road 38.

In January 1988 the developers contacted city staff regarding a proposed development of the property. They worked with the city planning commission and made modifications as requested. In May 1988 they submitted to the city a petition to rezone the property “from R-1A to M-4 to allow up to 11 units per acre according to the land use plan and approval of the preliminary plat for same site.” The application for rezoning listed the petitioners as St. Croix Development, Inc., and Wellington Management, Inc. Wellington and McNellis signed the petition and Cheney signed as “owner if other than Petitioner.”

The city held two public hearings on rezoning for the Palomino Townhouse project. At the first hearing, neighbors to the proposed project complained that property values of their single-family homes would decline because of the high-density development and that the project would exacerbate an existing traffic problem on Pennock Avenue.

Complaints about traffic problems on Pennock Avenue predated the proposed project. In 1987, in response to citizen complaints, the city commissioned a traffic study of Pennock Avenue. At the time of the first public hearing on the project, the traffic engineer had not yet reported the study results to the city. When he finally presented an oral report to the council and city staff, the engineer confirmed the fact that there was a safety problem on Pen-nock Avenue.

The study showed that an average of 1,900 cars per day were using a section of the avenue which was designed to handle safely only 800 to 1,000 cars per day. Although the problem area is approximately one-half mile from the proposed townhouse project, the traffic study showed that cars entering and exiting Pennock Avenue at the western end of County Road 38 (Zoo Road) were a substantial cause of the traffic problem. This intersection is adjacent to the proposed Palomino project. The traffic engineer advised the city that there was no engineering solution for the problem on Pennock Avenue until such time as County Road 38 is completed west past Pennock. These facts are substantiated in the full written Pennock Avenue Traffic Report.

After the engineer’s presentation to the city council, a city staff member directed him to prepare an additional report on the impact of the Palomino Townhouse project on Pennock Avenue. In his report the engineer assumed a project density of 6.4 units per acre and completion of County Road 38 west of Pennock Avenue. He provided the city with a letter report which concluded that the traffic impact from the project would be “insignificant.” The engineer advised the city that if the project were designed to prohibit traffic from exiting the project onto Pennock Avenue, it would account for only 25 cars per day more than a development with a density of 2.5 units per acre.

Based on the engineer’s report, the city staff recommended city council approval of the rezoning request. The staff changed their recommendation when it was brought to their attention that the engineer’s report was based on incorrect assumptions, i.e., the completion of County Road 38 and an incorrect density factor.

The city council denied the developers’ rezoning request and adopted the following findings:

1. Existing Comprehensive Plan designations are currently under review *396 by the City as directed by the City Council on January 1, 1988. This review will not be complete until some time after January 1, 1989.
2.- The existing Comprehensive Land Use designations are based upon saturation development of the City and assume that all associated infrastructure improvements are complete. Construction of new County Road # 38 adjacent to the subject area will not be complete until after 1990.
* * * * * *
5. The predominant developed land use surrounding the subject area is that of detached single family homes under an “R-1C” zoning designation. Neighborhood sentiment expressed during the public hearing process expressed concern over the appropriateness and compatibility of a proposed . townhouse use in an area lacking a complete roadway network.
[[Image here]]
9. Development of the site under the standards of “M-l” and “M-2” zoning designations is premature.
******

The developers brought an action for declaratory judgment in Dakota County District Court. The court determined that the record of the city’s rezoning proceeding was inadequate and allowed the city to augment the record at trial.

The record of the proceedings prior to trial consisted of maps, staff reports, meeting agenda; correspondence, a traffic report, an eight-page synopsis of a public meeting, and the resolution and findings as adopted by the city council when it voted to deny the rezoning request. Because the city did not keep contemporaneous reports or recordings of meetings, it augmented the record at trial to include depositions and testimony of staff, council members and the traffic engineer. It is not clear whether the full written Pennock Avenue Traffic Study was available to the council prior to its vote; it was added to the record at trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Property Group, LLC v. City of Wayzata
Court of Appeals of Minnesota, 2016
Citizens for a Balanced City v. Plymouth Congregational Church
672 N.W.2d 13 (Court of Appeals of Minnesota, 2003)
Beca of Alexandria, L.L.P. v. County of Douglas Ex Rel. Board of Commissioners
607 N.W.2d 459 (Court of Appeals of Minnesota, 2000)
Trisko v. City of Waite Park
566 N.W.2d 349 (Court of Appeals of Minnesota, 1997)
2600 University Inn, LLC v. City of Minneapolis
556 N.W.2d 218 (Court of Appeals of Minnesota, 1996)
Wedemeyer v. City of Minneapolis
540 N.W.2d 539 (Court of Appeals of Minnesota, 1995)
SuperAmerica Group, Inc. v. City of Little Canada
539 N.W.2d 264 (Court of Appeals of Minnesota, 1995)
R.A. Putnam & Associates, Inc. v. City of Mendota Heights
510 N.W.2d 264 (Court of Appeals of Minnesota, 1994)
Uniprop Manufactured Housing, Inc. v. City of Lakeville
474 N.W.2d 375 (Court of Appeals of Minnesota, 1991)
Northpointe Plaza v. City of Rochester
457 N.W.2d 398 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
446 N.W.2d 392, 1989 Minn. App. LEXIS 1092, 1989 WL 117185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-croix-development-inc-v-city-of-apple-valley-minnctapp-1989.