Sprint Spectrum L.P. v. Willoth

996 F. Supp. 253, 1998 U.S. Dist. LEXIS 2143, 1998 WL 84602
CourtDistrict Court, W.D. New York
DecidedFebruary 19, 1998
Docket6:97-cv-06473
StatusPublished
Cited by17 cases

This text of 996 F. Supp. 253 (Sprint Spectrum L.P. v. Willoth) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sprint Spectrum L.P. v. Willoth, 996 F. Supp. 253, 1998 U.S. Dist. LEXIS 2143, 1998 WL 84602 (W.D.N.Y. 1998).

Opinion

DECISION and ORDER

TELESCA, District Judge.

INTRODUCTION

Plaintiff, Sprint Spectrum, L.P. d/b/a Sprint PCS (“Sprint”), brings this action under the Federal Telecommunications Act of 1996 (“the Act”) and Article 78 of the New York Civil Practice Laws and Rules, seeking to annul a decision of the Town of Ontario (“the Town”) Planning Board which denied Sprint’s applications for site plan approval of three cellular towers in the Town. Sprint asks this Court to grant its applications and direct the Town’s Code Enforcement Officer to issue a permit for each site. Currently pending are the parties’ motions for summary judgment. For the reasons discussed below, plaintiffs motion is denied and defendants’ cross-motion for summary judgment is granted.

BACKGROUND

Sprint has obtained an exclusive license from the Federal Communications Commission (“FCC”) to provide digital personal communications services (“PCS”) for the Buffalo Major Trading Area (“MTA”), which encompasses most of Western New York, including the Town of Ontario.' Sprint paid $19,000,-000 for this ten-year FCC license, which requires it to provide PCS service to at least one-third of the population in the Buffalo MTA within five years of the issuance of its license. Sprint maintains that, in order to provide continuous uninterrupted service, it must develop an interconnected network of “cell sites” (i.e. antennae mounted on a pole or other structure) to provide overlapping *255 coverage in a grid pattern. The coverage area provided by each antenna depends on the height of the antenna, density of population, and local topography.

On May 21, 1996, Sprint filed with the Town of Ontario Planning Board three separate applications for site plan approval to construct cell sites at 426 Ridge Road, 6954 Slocum Road, and 193 County Line Road. Although Sprint’s applications sought individual permits to erect a 150-foot tall steel-gray “monopole” cell tower on each site, Sprint’s counsel conceded at oral argument that it was submitted on an all or nothing basis. The Town Planning Board discussed the applications at meetings and/or public hearings on June 11, 1996; July 9, 1996; August 13, 1996; September 4, 1996; September 17, 1996; May 20, 1997; July 8, 1997; August 26,1997; and September 25,1997.

After each meeting, Sprint submitted additional information or responses to public comments as requested by the Town. Sprint provided, among other things, simulated photos showing the proposed towers both with foliage on the surrounding trees and without foliage, as requested by the Town. Sprint also completed detailed Draft and Final Environmental Impact Statements which included computer-generated maps showing the proposed service areas at the Town’s request, as provided by the New York State Environmental Quality Review Act (“SEQRA”), Article 8, New York Environmental Conservation Law.

On September 25,1997, the Town made its final findings which were transcribed and filed with the Ontario County Clerk on October 1, 1997. The Town Planning Board denied all three of Sprint’s applications for site plan approvals based on its findings that (1) the Sprint project would have “a measurable and significant impact on property values”; (2) the “cumulative impact of multiple towers would have a significant environmental impact on the Town of Ontario”; and (3) there would be “visual impact from any tower that is visible over a wide area”.

The Board’s main concern was apparently Sprint’s unwillingness to consider alternatives (or, indeed, to even provide the Town with information about alternatives) with respect to the number, height, and placement of cell towers. Sprint made a business decision that the Town of Ontario should be classified as “suburban” and, thus, that a signal strong enough for “in-building” coverage ( — 99 dBm) was required. Accordingly, Sprint insisted upon the approval of all three towers as being necessary to provide adequate (i.e.“in-building”) coverage to the area it sought to service.

Sprint had classified the neighboring towns of Walworth and Macedón as “rural” and, thus, erected only one tower in each of those towns, which was sufficient to provide “in-vehicle” coverage ( — 103 dBm). The Town of Ontario Planning Board found that the population, topography, and other characteristics of Ontario were sufficiently similar to Walworth and Macedón that it should have also been classified as “rural” by Sprint, and that one tower would be sufficient. Sprint disputes the Town’s authority to challenge its business decision regarding the level of coverage it decided to provide. Sprint insists that this Court’s inquiry is limited to whether the Town’s action in denying all three site plans was “supported by substantial evidence contained in a written record.” 47 U.S.C. § 332(e) (7) (B) (iii).

DISCUSSION

The central issue is whether the Town of Ontario exceeded its authority in denying Sprint’s application for three cell towers on the basis that Sprint’s evidence demonstrated that a single tower could adequately perform the function necessary to provide the desired level of service to its cellular customers. Sprint insists that the question of adequacy of service in determining the number of towers necessary is not a permissible area of inquiry by the Town. The issue exemplifies the tension between the competing interests of local home rule and the implementation of the Federal Telecommunications Act of 1996. “The power of local governments to zone and control land use is undoubtedly broad and its proper exercise is an essential aspect of achieving a satisfactory quality of life in both urban and rural communities.” Schad v. Borough of Mount Ephraim, 452 U.S. 61, 68, 101 S.Ct. 2176, 2182, 68 L.Ed.2d 671 (1981).

*256 However, a local government’s power to regulate land use is not unlimited, especially with respect to “personal wireless services facilities” (i.e. cell towers). Cellular service facilities are entitled to special zoning consideration both under the Federal Telecommunications Act of 1996, 47 U.S.C. § 332, and New York law, which has classified cellular providers as “public utilities.” Cellular Telephone Co. v. Rosenberg, 82 N.Y.2d 364, 604 N.Y.S.2d 895, 624 N.E.2d 990 (1993).

The Telecommunications Act of 1996, 47 U.S.C. § 332

On February 8, 1996, President Clinton signed into law the Federal Telecommunications Act of 1996 (“the Act”), which has been characterized as “an unusually important legislative enactment” establishing national public policy in favor of reducing regulation and encouraging “the rapid deployment of new telecommunications technologies.” See Reno v. American Civil Liberties Union, — U.S. -, 117 S.Ct. 2329, 2337-38, 138 L.Ed.2d 874 (1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Medina v. T-Mobile USA, Inc.
123 Wash. App. 19 (Court of Appeals of Washington, 2004)
Site Acquisitions, Inc. v. Town of New Scotland
2 A.D.3d 1135 (Appellate Division of the Supreme Court of New York, 2003)
Sprint Spectrum L.P. v. Mills
65 F. Supp. 2d 148 (S.D. New York, 1999)
New York SMSA Limited Partnership v. BOARD OF ADJUSTMENT OF THE TOWNSHIP
734 A.2d 826 (New Jersey Superior Court App Division, 1999)
Sprint Spectrum v. Willoth
176 F.3d 630 (Second Circuit, 1999)
Sprint Spectrum, L.P. v. Willoth
176 F.3d 630 (Second Circuit, 1999)
Omnipoint Communications, Inc. v. City of Scranton
36 F. Supp. 2d 222 (M.D. Pennsylvania, 1999)
Primeco Personal Communications, L.P. v. Village of Fox Lake
26 F. Supp. 2d 1052 (N.D. Illinois, 1998)
Sprint Spectrum L.P. v. Town of North Stonington
12 F. Supp. 2d 247 (D. Connecticut, 1998)
Sprint v. Durham
D. New Hampshire, 1998
Omnipoint Communications Enterprises, Inc. v. Town of Amherst
74 F. Supp. 2d 109 (D. New Hampshire, 1998)
Smart Smw of Ny v. Zoning Com'n, Town of Stratford
9 F. Supp. 2d 143 (D. Connecticut, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
996 F. Supp. 253, 1998 U.S. Dist. LEXIS 2143, 1998 WL 84602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sprint-spectrum-lp-v-willoth-nywd-1998.