Spinner-Hay Lumber Co. v. Applebaum

207 S.W. 624, 1918 Tex. App. LEXIS 1247
CourtCourt of Appeals of Texas
DecidedDecember 18, 1918
DocketNo. 7637.
StatusPublished

This text of 207 S.W. 624 (Spinner-Hay Lumber Co. v. Applebaum) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spinner-Hay Lumber Co. v. Applebaum, 207 S.W. 624, 1918 Tex. App. LEXIS 1247 (Tex. Ct. App. 1918).

Opinion

PLEASANTS, C. J.

This suit was brought by appellant against the appellees to recover the sum of $224, with 8 per cent, interest from October 1, 1913. Plaintiffs cause of action is based upon a contract executed by the parties on September 17, 1913, the substance of which is as follows:

It recited that appellant had constructed certain improvements for Applebaum and wife, under a contract which provided for the payment of $2,790, and that differences had arisen between the parties as to whether said houses had been completed in accordance with the contract and plans and specifications, and that the parties, in order to settle the difference thus arising, agreed:

(1)That Applebaum and wife would pay to the appellant the sum of $2,790, as follows : $2,566 to be paid upon the execution of the contract, and which sum was receipted for thereby, “and the remaining sum of $224.00 to be placed with Meyer O. Wagner to be held in escrow until the .first party (appellant) has completed the work herein recited to be done by said first party.”
(2) Appellant agreed to have the water pipes properly placed and tapped with the city main in such manner as to bring water into said houses, and cost and expense therefor to be paid by appellant, and the work to be completed not later than September 22, 1913, and appellant agreed, in the event of the failure to so complete said water connections within the time specified, to pay Applebaum and wife $3 for each day’s delay until the work was done, and for the purpose of further protecting the said Apple-baum and wife the sum of $224 placed in escrow should be held until the completion thereof.
(3) Appellant agreed to repair three windows at an estimated value of $3, and on failure to fix said windows by September 19, 1913, Applebaum and wife were authorized to do that work and receive the sum of $3 therefor.
(4) Appellants agreed to furnish four keys for inside rooms, and upon their failure to furnish said keys by the evening of September 18, 1913, the sum of $4 should be retained to secure payment thereof by Applebaum and wife, who were then authorized to have-keys fitted.
(5) Appellants obligated themselves to have all the tin work on said houses “properly done with proper fall and in proper workmanlike manner,” which work was to be-done by September 24th; said contract with reference to the tin work continuing as follows:
“And failing to do said work by that date, second party is authorized to contract for said work to be done, and all costs and expenses therefor will be paid by first party; that of the amount placed in escrow $71.00 is to protect against claim now outstanding by tinner for payment for his work, and which work has not been accepted by second party, and a controversy has arisen between second party and first party and between tinner and first party as to proper work. It is distinctly understood that the tin work must be properly done with proper fall and in a first-class workmanlike manner. Should first party fail to do and perform and complete said tin work as required by September 24, 1913, second party is authorized to proceed to contract for such work to be done, and the sum held in escrow shall be applied in payment therefor, and should amount not be sufficient, then first party hereby admits liability for any deficiency in amount in escrow to cover payment for all obligations herein undertaken by first party, and' such amount shall be paid as itemized statements from competent workmen show actual' cost.”
(6) The last and. final provision of said-escrow agreement was as follows:
“First party upon execution hereof binds himself to deliver possession of said houses to sec *625 ond party, and such possession and occupancy shall not be a waiver of any legal rights as to the items herein specified, but shall be an acceptance of all other portions thereof, and as to items herein mentioned acceptance thereof is not made by- second party and so expressly understood.'’

Appellants alleged the construction and completion of the houses under the original contract, the difference arising over the acceptance of the work and the execution of the subsequent or escrow agreement, and alleging that appellants had fully complied with said escrow agreement, and that the escrow agent Wagner had refused to pay plaintiffs said sum of $224 deposited with him under the terms of said escrow agreement, and prayed judgment for said sum with interest.

Appellees Applebaum and wife, in their answer, admitted the execution of the contracts pleaded by plaintiffs and admitted that the sum of $224 was placed with Meyer C. Wagner to be held in escrow under the terms of the contract of September 17, 1918. They also admitted that the water pipes provided for in the contract had been connected up as required by said contract, except that plaintiffs had failed to place a cut-off as provided for in the original contract, and that the cost of replacing said cut-off was $5. They denied that plaintiffs had repaired the three windows as required, and alleged that defendants did the work at an expense of $2.60. They admitted that plaintiffs furnished the keys to the houses as alleged in plaintiffs’ petition.

Said defendants, in paragraph 10 of their answer, alleged that plaintiffs had refused to have all the tin work on said houses properly done with proper fall and in a proper, workmanlike manner, and that said defendants had made demand on plaintiffs for the performance of said work, which was refused, and that the reasonable cost of having the tin work on said houses properly done with proper fall and in a proper and workmanlike manner would be the sum of $120, “and which sum these defendants are entitled to receive for the purpose of having said tin work on said houses properly done with proper fall, and in a proper and workmanlike manner, and which sum is the reasonable cost for the performance of said work.”

In paragraph 11 of said answer said defendants admitted that the sum of $71 was placed in escrow to protect against claims outstanding by the tinner for the payment for his work, and that said defendants did not know whether said claim had been paid or not, and, if the same had not been paid, said defendants were entitled to recover the sum of $71 held in escrow in payment of said tinner’s claim.

Paragraph 13 of said defendants’ answer is as follows:

“These defendants further allege under the terms of said contract it was provided that he, the first party (meaning plaintiffs herein), failed to do or perform and complete said tin work as required by September 24, 1913, that these defendants were authorized to proceed to contract for such work to be done, and the sum held in escrow to be applied in payment therefor; that said work was not done, and that these defendants notified Meyer 0. Wagner that they desired to contract to have said work done and receive from the said Meyer O. Wagner such sum as would be required to do and perform such work, and the said Meyer O. Wagner refused to pay said sum unless consent was obtained from the first parties in order to relieve him from any personal liability by virtue of said payment.”

Paragraph 15 of said answer is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Appelbaum v. Spinner-Hay Lumber Co.
186 S.W. 810 (Court of Appeals of Texas, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
207 S.W. 624, 1918 Tex. App. LEXIS 1247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spinner-hay-lumber-co-v-applebaum-texapp-1918.