Appelbaum v. Spinner-Hay Lumber Co.

186 S.W. 810, 1916 Tex. App. LEXIS 676
CourtCourt of Appeals of Texas
DecidedMay 25, 1916
DocketNo. 599.
StatusPublished
Cited by2 cases

This text of 186 S.W. 810 (Appelbaum v. Spinner-Hay Lumber Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appelbaum v. Spinner-Hay Lumber Co., 186 S.W. 810, 1916 Tex. App. LEXIS 676 (Tex. Ct. App. 1916).

Opinion

HIGGINS, J.

Appelbaum and wife entered into an agreement with the Spinner-Hay *811 Lumber Company, whereby the latter agreed to construct and complete six cottages according to certain plans and specifications, in consideration whereof the Appelbaums agreed to pay the sum of $2,790. The houses having been built, a controversy arose between the parties as to whether or not the houses had been constructed and completed in accordance with the terms of the contract. Thereupon the parties entered into a written contract whereby the Appelbaums agreed to pay and did pay to appellee $2,566 and the balance of the contract price, namely, $224, was placed in the hands of Meyer 0. Wagner, to be held in escrow until appellee had done certain work upon the buildings. This contract reads:

“This agreement made this 17th day of September, 1913, by and between E. Spinner and S. E. Hay, composing the firm of Spinner-Hay Lumber Company, acting through E. Spinner hereafter styled first party, and J. Appelbaum and wife, Ida Appelbaum, hereafter styled party of the second part, witnesseth:
“The first party has constructed certain im-rovements for second party .on lots 1, 2, and , block 1, William Burnett addition north side of Buffalo bayou under a contract providing for payment of sum of $2,790 for completion under terms of contract, plans and specifications, and differences have arisen between the parties as to completion thereof in full compliance, and the parties are desirous of adjusting and settling the differences and for that purpose do agree as follows:
“That the second party will pay to the first party the sum of $2,790 as follows: $2,566 to be paid to first party this day and receipt of which sum is hereby acknowledged, and the remaining sum of $224 to be placed with Meyer O. Wagner to be held in escrow until the first party has completed the work herein recited to be done by said first party.
“First party is to have the water pipes properly placed and tapped with city main using new pipe and to connect with sidewalk at proper places on which houses are not situated, and cutoff to be placed, pipe to be one inch pipe and be so connected as to bring water to houses making clear connection so that houses have water as contemplated and understood by original contract and as herein provided to be done; that all costs and expenses for pipe, labor, material and connections to be paid by first party and work to be started at once and fully completed not later than Monday, September 22, at 6 o’clock p. m., 1913, and failure to so complete laying of pipes and all work relating to same and furnishing of water by that date, said first party binds and obligates himself to pay secbnd party the sum of $3 for each day’s delay from that time until properly done and connected and water furnished, and for the purpose of further protecting said second party the sum of $224 retained and placed in escrow shall be held until completion thereof.
“The amount actually held for water is $150, but said sum shall be held with the $224 until all of the remaining work understood herein is finished and completed in a proper manner.
“The first party will fix and repair three windows and the estimated value thereof $3 and, failing to fix said windows by September 19th, second party shall be authorized to do said work and withhold the sum of $3 therefor.
“First party is to furnish four keys for inside rooms, and, failing to furnish said keys by evening of September 18th, the sum of $4 shall be retained to secure payment therefor by second party who is then authorized to have keys fitted.
First party obligates-himself to have all of the tinwork on said houses properly done with proper fall and in proper workmanlike manner and which work is to be done by Wednesday, September 24, 1913, and failing to do said work by that date, second party is authorized to contract for said work to be done and all costs and expenses therefore will be paid by first arty; that of the amount placed in escrow 71 is to protect against claim now outstanding by tinner for payment for his work and which work has not been accepted by second party and a controversy has arisen between second party- and first party and between tinner and first party as to proper work. It is distinctly understood that the tinwork must be properly done with proper fall and in a first-class workmanlike manner. Should first party fail to do and perform and complete said tinwork as required by September 24, 1913, second party is authorized to proceed to contract for such work to be done and the sum held in escrow shall be applied in payment therefor, and should amount not be sufficient then first party hereby admits liability for any deficiency in amount in escrow to cover payment for all obligations herein undertaken by first party, and such amount shall be paid as itemized statements from competent workmen show actual cost.
“First party, upon execution hereof, binds himself to deliver possession of said houses to second party, and such possession and occupancy shall not be a waiver of any legal rights as to the items herein specified, but shall be an acceptance of all other portions thereof, and as to items herein mentioned, acceptance thereof is not made by second party and so expressly understood.”

This suit was- filed by appellee against the Appelbaums and Wagner to recover said $224, alleging that it had complied with its obligations under the contract just quoted.

In their answer, the Appelbaums admitted that appellee had placed the water pipes as it had agreed to do, but averred that it had failed to place the cut-off as provided in the contract, and that the cost of placing the same was $5. They denied that plaintiff had fixed and repaired the windows as required, and averred that they had done so at a cost of $2.60. They admitted that keys had been supplied as the contract required. They denied that the tinwork on the houses had been done with proper fall and in a proper and workmanlike manner, and that it would cost $120 to do so, which amount they were entitled to receive from the escrow fund with which to have said tinwork properly done. They also averred that the Texas Tinners’ Supply Company had a claim for $71 and lien for tinwork on the houses, and that defendants were entitled to this amount out of the escrow fund to protect against said claim and lien.

By supplemental petition, appellee denied the allegations of the answer, and with reference to the claim that the tinwork had not been properly done it pleaded specially:

“That the tinwork and labor for said houses was properly done in accordance with said contract of settlement declared on by tile plaintiffs herein, and that the defendants, by failing to have any work, claimed to be defective or insufficient or omitted by the plaintiffs, contracted for, and an itemized statement from competent workmen showing the actual cost for doing said work, as required by said contract, are not en *812 titled to have or receive or further hold the money so placed in escrow under the contract pleaded by the plaintiffs.”

E. Spinner testified, for plaintiff:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilbur v. Tourangeau
71 A.2d 565 (Supreme Court of Vermont, 1950)
Spinner-Hay Lumber Co. v. Applebaum
207 S.W. 624 (Court of Appeals of Texas, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
186 S.W. 810, 1916 Tex. App. LEXIS 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appelbaum-v-spinner-hay-lumber-co-texapp-1916.