Spector v. USAA Casualty Insurance Company

District Court, E.D. Louisiana·Decided October 30, 2019·No. 2:18-cv-08806·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

MATTHEW SPECTOR, 18-CV-08806

Plaintiff,

VERSUS JUDGE WENDY B VITTER

USAA CASUALTY INSURANCE MAGISTRATE JUDGE COMPANY, USAA GENERAL INDEMNITY JANIS VAN MEERVELD CO., WALLACE C. DRENNAN, INC., SEWERAGE AND WATER BOARD OF NEW ORLEANS, NEW ORLEANS CITY, UNITED SERVICES AUTOMOBILE ASSOCIATION, INCORRECTLY REFERRED TO AS USAA CASUALTY INSURANCE COMPANY;

Defendants.

ORDER AND REASONS

Before the Court is plaintiff’s Motion for Leave to File a Second Amended Complaint. (Rec. Doc. 93). For the following reasons, the Motion is GRANTED. Background Plaintiff Matthew Spector’s present complaint alleges that street repair work performed by Wallace C. Drennan, Inc. (“Drennan”) on behalf of the Sewerage and Water Board was faulty and failed to provide proper and adequate drainage resulting in flooding to his residence. Trial is set to begin on December 2, 2019, and the deadline to amend pleadings passed on December 18, 2018. Spector asserts that during the depositions of Drennan’s employees in early October 2019, he learned that Drennan had retained C&M Construction Group, Inc. (“C&M”) to perform restoration work, including asphalt and paving around plaintiff’s property. Spector now seeks to name C&M as an additional defendant and to allege that C&M’s faulty street repairs and failure to provide adequate drainage resulted in the flooding of his property. Spector’s motion was set for oral argument on October 30, 2019. Drennan responds that it provided the identity of C&M in its May 24, 2019, discovery responses. Indeed, Interrogatory No. 3 asked Drennan to identify subcontractors who worked on the project. Drennan identified C&M as having performed work on Belfast Street. It also identified

four other companies as having subcontracts related to the underlying construction contract. Drennan adds that at the same time it produced a document titled “Economically Disadvantaged Business Participation Summary Sheet,” which listed C&M and identified “asphalt & concrete” as the scope of work performed by it. Drennan points out that Spector’s theory of liability is improper paving. It argues that Spector should have known in May 2019 that C&M performed the allegedly improper paving. Drennan notes that there are less than 50 days until the jury trial with numerous critical deadlines that will pass before C&M even makes an appearance. It says that over 40 hours of depositions have already been conducted and two separate expert inspections have been performed. It says C&M will be prejudiced if it is forced to go to trial without having

participated in pretrial activities, but the other parties will be prejudiced if all the discovery must be redone. Drennan submits that it was Spector’s responsibility to add C&M when he was notified of its role in May 2019 and that Spector should not be allowed to prejudice the defendants by adding C&M at this late date. In reply, Spector denies that Drennan’s discovery responses gave him notice that C&M was a potentially responsible party. He insists that Drennan’s discovery responses did not give any understanding of the scope of C&M’s work or its role in paving his driveway, paving the surrounding sidewalks, and paving the roadway in front of his house. Spector points out that Drennan identified a number of subcontractors in its May 2019 discovery responses but did not specify that it believed C&M performed all of the work and was specifically responsible for any or all of the alleged damages. He argues that Drennan should have identified C&M in response to other interrogatory responses but did not. For example, Interrogatory No. 13 asked Drennan to identify those entities responsible for responding to, investigating, assessing, monitoring and/or remediating the street or drainage repair failures relating to the incident in question at or near

Spector’s property. Drennan did not identify C&M. Spector also contends that Drennan could have identified C&M in response to his requests for production of documents seeking communications and documents exchanged with subcontractors by producing such documents. Spector insists that he did not learn that Drennan considered C&M to be the only responsible party for the surface work performed on his street until the October 2019 depositions. He says he also did not learn that C&M was the only entity that performed restoration work at this location of the larger construction project until the depositions. He adds that he did not learn until the depositions that C&M is funding the defense of this matter on Drennan’s behalf. Spector also denies that the other parties would be unduly prejudiced. He points out that

all parties have agreed to move the trial date in part because expert depositions have not yet been performed. He says that since C&M has been effectively underwriting this litigation, it is already aware of the discovery that has been conducted and will be given access to all existing discovery materials. He also submits that if Spector or others must be re-deposed, it can be done in a non- duplicative manner. Law and Analysis Under Federal Rule of Civil Procedure 15(a)(2), when the time period for amending a pleading as a matter of course has passed, a party may amend its pleadings by consent of the parties or by leave of court. “The court should freely give leave when justice so requires.” Fed. R. Civ. Proc. 15(a)(2). Thus, the United States Court of Appeals for the Fifth Circuit instructs that the “district court must possess a ‘substantial reason’ to deny a request for leave to amend.” Smith v. EMC Corp., 393 F.3d 590, 595 (5th Cir. 2004). Nonetheless, “that generous standard is tempered by the necessary power of a district court to manage a case.” Yumilicious Franchise, L.L.C. v. Barrie, 819 F.3d 170, 177 (5th Cir. 2016) (quoting Schiller v. Physicians Res. Grp. Inc., 342 F.3d

563, 566 (5th Cir. 2003)). The court may consider numerous factors when deciding whether to grant a motion for leave to amend, including “undue delay, bad faith or dilatory motive on the part of the movant, repeated failures to cure deficiencies by amendments previously allowed, undue prejudice to the opposing party by virtue of allowance of the amendment, and futility of the amendment.” Schiller v. Physicians Res. Grp. Inc., 342 F.3d 563, 566 (5th Cir. 2003). Where the court ordered deadline for amending pleadings has passed, that schedule “may be modified” to allow for additional amendments “only for good cause and with the judge’s consent.” Fed. R. Civ. Proc. 16(b)(4); see S&W Enterprises, L.L.C. v. SouthTrust Bank of Alabama, NA, 315 F.3d 533, 536 (5th Cir. 2003) (“We take this opportunity to make clear that

Rule 16(b) governs amendment of pleadings after a scheduling order deadline has expired.”). When determining whether the movant has shown good cause, the Court considers “(1) the explanation for the failure to [timely move for leave to amend]; (2) the importance of the [amendment]; (3) potential prejudice in allowing the [amendment]; and (4) the availability of a continuance to cure such prejudice.’ ” S&W Enterprises, 315 F.3d at 536 (quoting Reliance Ins. Co. v. Louisiana Land & Expl. Co., 110 F.3d 253, 257 (5th Cir. 1997)) (alterations in original).

Free access — add to your briefcase to read the full text and ask questions with AI