OPINION
PER CURIAM.
This case involves the application of the “express negligence rule” to an indemnity contract between a contractor and a subcontractor. The contract provided “Subcontractor agrees to ... indemnify Contractor ... against and for all liability ... and damages which Contractor may ... become liable for by reason of any ... injuries ... to ... the workmen of either party ... in any matter arising out of or resulting from Subcontractor’s performance ... hereunder, ... including, but not limited to, any negligent act or omission ... of Contractor....” One of the subcontractor’s workers sued the contractor for negligence, and the contractor filed a third-party claim against the subcontractor. The trial court granted summary judgment for the subcontractor. We hold that the intent expressly stated within the four corners of the contract exculpates the contractor from the consequences of its own negligence that resulted in injury to the subcontractor’s worker. We also hold that, because the worker was injured while performing work for the subcontractor, the claim arises out of the performance of the contract. We further hold that the contractor is entitled to indemnity from the subcontractor. Accordingly, we reverse the summary judgment and remand the cause to the trial court for further proceedings consistent with this opinion.
When, as here, both sides move for summary judgment and the trial court grants one motion and denies the other, the reviewing court reviews the summary judgment evidence presented by both sides and determines all questions presented.
Commissioners Court of Titus County v. Agan,
940 S.W.2d 77, 81 (Tex.1997). If the issue raised is based upon undisputed and unambiguous facts, we may determine the question presented as a matter of law.
Gramercy Ins. Co. v. MRD Invs., Inc.,
47 S.W.3d 721, 724 (Tex.App.-Houston [14th Dist.] 2001, pet. denied). If resolution of the issues rests on disputed facts, however, we reverse and remand for further proceedings.
Coker v. Coker,
650 S.W.2d 391, 394-95 (Tex.1983).
Under the terms of the contract between contractor SpawGlass Construction Corporation and subcontractor E.T. Services, Inc. (“ETS”), ETS agreed to perform structural steel erection for Spaw-Glass Construction Corporation at the Ca-ney Creek High School. Brian Sanders, an ETS employee working as a connector welder, avers that he was rolling up an oxygen hose when he was struck by a three by six foot piece of plywood. The appellee’s motion for summary judgment
alleges that a gust of wind blew the plywood off of the roof during a sudden storm. Sanders sued SpawGlass Construction Corporation and SpawGlass, Inc. (collectively “SpawGlass”)
for negligence, and SpawGlass sought indemnity from ETS. ETS and SpawGlass filed cross-motions for summary judgment. The trial court denied the SpawGlass motion, granted the ETS motion, and severed the third-party claim from the main suit. On appeal, SpawGlass contends the contract clearly and unambiguously requires ETS to indemnify Spawglass for claims of injury to ETS’s workers attributable to Spaw-Glass’s negligence. ETS, on the other hand, contends the indemnity provision is ambiguous and that the indemnity applies only to injuries resulting from ETS’s performance.
The express negligence rule requires that the intent of the party seeking indemnity from the consequences of that party’s own future negligence must be expressed in unambiguous terms within the four corners of the contract.
Ethyl Corp. v. Daniel Constr. Co.,
725 S.W.2d 705, 708 (Tex.1987). The indemnity clause in this case derives from a clause the Supreme Court held was enforceable under the express negligence doctrine.
See Atlantic Richfield Co. v. Petroleum Personnel, Inc.,
768 S.W.2d 724, 726 (Tex.1989).
To distinguish its agreement to indemnify Spaw-Glass from the
Atlantic Richfield
indemnity, ETS relies on the additional language contained within the contract’s responsibility-shifting provision. To the
Atlantic Richfield
language “including, but not limited to, any negligent act or omission” of the indemnified party, the contract in this case added words “or claim involving strict liability or negligence per se of’ Spaw-Glass. The addition of this phrase, the appellee contends, makes the indemnity clause ambiguous. We disagree. The language contained in a contract is accorded its plain grammatical meaning unless to do so would defeat the parties’ intent.
See DeWitt County Elec. Co-op. v. Parks,
1 S.W.3d 96, 101 (Tex.1999). The drafter did not separate “any negligent act or omission or claim involving strict liability” from “or negligence per se of Contractor,” and the subject phrase “any negligent act or omission” makes sense only in conjunction with the prepositional phrase “of Contractor or Owner.” We conclude that the indemnity clause in this contract satisfies the express negligence rule.
The appellee argues that, “regardless of whether the provision meets the express negligence test, indemnity does not apply because the circumstances of the incident did not trigger the indemnity provision.” ETS contends that indemnity may only be triggered if the incident arose out of its performance, not its mere presence on the site. ETS relies on two cases that pre-date
Ethyl
and the adoption of the express negligence test.
See Sun Oil Co. v. Renshaw Well Serv., Inc.,
571 S.W.2d 64 (Tex.Civ.App.-Tyler 1978, writ ref'd n.r.e.), and
Westinghouse Elec. Corp. v. Childs-Bellows,
352 S.W.2d 806 (Tex.Civ.App.-Fort Worth 1961, writ ref'd). The contracts in those cases included some language similar to that found in the
ETS/SpawGlass contract, but lacked the express inclusion of negligent acts or omissions
of
SpawGlass found within the indemnity undertaken by ETS.
In this case, the worker was allegedly injured in the performance of ETS’s work under the SpawGlass contract. The contract expressly provided that ETS would indemnify SpawGlass against liability for SpawGlass’s negligent act that injured ETS’s worker. Although the appellee contends that the injury arose from Spaw-Glass’s performance completely unrelated to the work ETS and its worker were hired to perform, the contractor, the subcontractor, and the worker were all engaged in the construction of a high school auditorium.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
PER CURIAM.
This case involves the application of the “express negligence rule” to an indemnity contract between a contractor and a subcontractor. The contract provided “Subcontractor agrees to ... indemnify Contractor ... against and for all liability ... and damages which Contractor may ... become liable for by reason of any ... injuries ... to ... the workmen of either party ... in any matter arising out of or resulting from Subcontractor’s performance ... hereunder, ... including, but not limited to, any negligent act or omission ... of Contractor....” One of the subcontractor’s workers sued the contractor for negligence, and the contractor filed a third-party claim against the subcontractor. The trial court granted summary judgment for the subcontractor. We hold that the intent expressly stated within the four corners of the contract exculpates the contractor from the consequences of its own negligence that resulted in injury to the subcontractor’s worker. We also hold that, because the worker was injured while performing work for the subcontractor, the claim arises out of the performance of the contract. We further hold that the contractor is entitled to indemnity from the subcontractor. Accordingly, we reverse the summary judgment and remand the cause to the trial court for further proceedings consistent with this opinion.
When, as here, both sides move for summary judgment and the trial court grants one motion and denies the other, the reviewing court reviews the summary judgment evidence presented by both sides and determines all questions presented.
Commissioners Court of Titus County v. Agan,
940 S.W.2d 77, 81 (Tex.1997). If the issue raised is based upon undisputed and unambiguous facts, we may determine the question presented as a matter of law.
Gramercy Ins. Co. v. MRD Invs., Inc.,
47 S.W.3d 721, 724 (Tex.App.-Houston [14th Dist.] 2001, pet. denied). If resolution of the issues rests on disputed facts, however, we reverse and remand for further proceedings.
Coker v. Coker,
650 S.W.2d 391, 394-95 (Tex.1983).
Under the terms of the contract between contractor SpawGlass Construction Corporation and subcontractor E.T. Services, Inc. (“ETS”), ETS agreed to perform structural steel erection for Spaw-Glass Construction Corporation at the Ca-ney Creek High School. Brian Sanders, an ETS employee working as a connector welder, avers that he was rolling up an oxygen hose when he was struck by a three by six foot piece of plywood. The appellee’s motion for summary judgment
alleges that a gust of wind blew the plywood off of the roof during a sudden storm. Sanders sued SpawGlass Construction Corporation and SpawGlass, Inc. (collectively “SpawGlass”)
for negligence, and SpawGlass sought indemnity from ETS. ETS and SpawGlass filed cross-motions for summary judgment. The trial court denied the SpawGlass motion, granted the ETS motion, and severed the third-party claim from the main suit. On appeal, SpawGlass contends the contract clearly and unambiguously requires ETS to indemnify Spawglass for claims of injury to ETS’s workers attributable to Spaw-Glass’s negligence. ETS, on the other hand, contends the indemnity provision is ambiguous and that the indemnity applies only to injuries resulting from ETS’s performance.
The express negligence rule requires that the intent of the party seeking indemnity from the consequences of that party’s own future negligence must be expressed in unambiguous terms within the four corners of the contract.
Ethyl Corp. v. Daniel Constr. Co.,
725 S.W.2d 705, 708 (Tex.1987). The indemnity clause in this case derives from a clause the Supreme Court held was enforceable under the express negligence doctrine.
See Atlantic Richfield Co. v. Petroleum Personnel, Inc.,
768 S.W.2d 724, 726 (Tex.1989).
To distinguish its agreement to indemnify Spaw-Glass from the
Atlantic Richfield
indemnity, ETS relies on the additional language contained within the contract’s responsibility-shifting provision. To the
Atlantic Richfield
language “including, but not limited to, any negligent act or omission” of the indemnified party, the contract in this case added words “or claim involving strict liability or negligence per se of’ Spaw-Glass. The addition of this phrase, the appellee contends, makes the indemnity clause ambiguous. We disagree. The language contained in a contract is accorded its plain grammatical meaning unless to do so would defeat the parties’ intent.
See DeWitt County Elec. Co-op. v. Parks,
1 S.W.3d 96, 101 (Tex.1999). The drafter did not separate “any negligent act or omission or claim involving strict liability” from “or negligence per se of Contractor,” and the subject phrase “any negligent act or omission” makes sense only in conjunction with the prepositional phrase “of Contractor or Owner.” We conclude that the indemnity clause in this contract satisfies the express negligence rule.
The appellee argues that, “regardless of whether the provision meets the express negligence test, indemnity does not apply because the circumstances of the incident did not trigger the indemnity provision.” ETS contends that indemnity may only be triggered if the incident arose out of its performance, not its mere presence on the site. ETS relies on two cases that pre-date
Ethyl
and the adoption of the express negligence test.
See Sun Oil Co. v. Renshaw Well Serv., Inc.,
571 S.W.2d 64 (Tex.Civ.App.-Tyler 1978, writ ref'd n.r.e.), and
Westinghouse Elec. Corp. v. Childs-Bellows,
352 S.W.2d 806 (Tex.Civ.App.-Fort Worth 1961, writ ref'd). The contracts in those cases included some language similar to that found in the
ETS/SpawGlass contract, but lacked the express inclusion of negligent acts or omissions
of
SpawGlass found within the indemnity undertaken by ETS.
In this case, the worker was allegedly injured in the performance of ETS’s work under the SpawGlass contract. The contract expressly provided that ETS would indemnify SpawGlass against liability for SpawGlass’s negligent act that injured ETS’s worker. Although the appellee contends that the injury arose from Spaw-Glass’s performance completely unrelated to the work ETS and its worker were hired to perform, the contractor, the subcontractor, and the worker were all engaged in the construction of a high school auditorium.
In its motion for summary judgment, ETS contended that Sanders’s injury did not arise out of ETS’s performance of its contractual duty to erect steel because Sanders “was standing under cover when a storm began.” The factual basis for this allegation is not established by the summary judgment record, which includes discovery responses in which Sanders maintains that he was rolling up oxygen hose when struck by the sheet of plywood. Therefore, the trial court could not have granted summary judgment for ETS on that ground.
The contract between the parties expressly stated that ETS would indemnify SpawGlass from the consequences Spaw-Glass’s own negligence that resulted in injury to ETS’s worker. The claim assert
ed by Brian Sanders arises out of the performance of ETS’s contract with Spaw-Glass. Therefore, the trial court erred in dismissing the . appellants’ third-party claim against the appellee. We reverse the summary judgment and remand the cause to the trial court for further proceedings consistent with this opinion.
REVERSED AND REMANDED.
APPENDIX
CONTRACTOR [PPI] agrees to hold harmless and unconditionally indemnify COMPANY [ARCO]
against and for all liability, cost, expenses, claims and damages
which [ARCO] may at any time suffer or sustain or become liable for by reason of any accidents, damages or injuries either to the persons or property or both, of [PPI], or of the workmen of either party, or of any other parties, or to the property of [ARCO],
in any matter arising from the work performed hereunder,
including but not limited to any negligent act or omission of [ARCO], its officers, agents or employees .... (emphasis added)
Indemnity for Personal Injury and Property Damage INDEMNITY. To the fullest extent permitted by law,
Subcontractor agrees to defend, hold harmless and unconditionally indemnify Contractor and Owner, their officers, directors, shareholders, employees, agents, Contractor’s surety and all parties whom Contractor is required to indemnify pursuant to the terms of the Contract Documents,
against and for all liability, costs, expenses, claims, liens, citations, penalties, fines, attorney’s fees, losses, and damages
which Contractor may at any time suffer or sustain or become liable for by reason of any accidents, damages or injuries either to the persons or property or both of Subcontractor, or the workmen of either party, or of any other parties, or to the property of Contractor,
in any matter arising out of or resulting from Subcontractor’s performance or failure to perform hereunder, or failure or defects of materials or goods supplied by or on behalf of Subcontractor,
including, but not limited to, any negligent act or omission or claim involving strict liability or negligence per se of Contractor or Owner, their officers, directors, shareholders, employees, agents, Contractor’s surety and all parties whom Contractor is required to indemnify pursuant to the terms of the Contract Documents.
The coverage of any insurance policy required herein or actually carried by Subcontractor shall not limit the extent of Subcontractor’s liability under the foregoing indemnity.