S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc.

CourtCourt of Appeals of Texas
DecidedMay 23, 2024
Docket09-22-00261-CV
StatusPublished

This text of S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc. (S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc., (Tex. Ct. App. 2024).

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

__________________

NO. 09-22-00261-CV __________________

S&B ENGINEERS & CONSTRUCTORS, LTD. AND ZURICH AMERICAN INSURANCE COMPANY, Appellants

V.

SCALLON CONTROLS, INC., Appellee

__________________________________________________________________

On Appeal from the 172nd District Court Jefferson County, Texas Trial Cause No. E-198,919 __________________________________________________________________

MEMORANDUM OPINION

In this appeal, defendants (and an insurer) who paid to settle a lawsuit are

seeking a recovery from a third-party-defendant for the amounts paid in the

settlement. Appellant S&B Engineers and Constructors, Ltd. (“S&B”) appeals from

an Order on Cross Motions for Summary Judgment. In the order, the trial court

granted summary judgment in favor of Appellee Scallon Controls, Inc. (“Appellee”

or “Scallon”) on all claims asserted against Scallon and denied S&B’s motion for

1 partial summary judgment against Scallon. In four issues on appeal, S&B argues that

the trial court erred. Appellant Zurich American Insurance Company (“Zurich”),

who was an intervenor in the trial court and asserted subrogation rights as Sunoco’s1

insurer, also appeals. As explained herein, we affirm.

Background

Seven individual plaintiffs (“Individual Plaintiffs”) filed a personal injury

lawsuit against Sunoco Logistics Partners Operations GP LLC, Sunoco Logistics

Partners LP (collectively “Sunoco”), and S&B. 2 The Individual Plaintiffs alleged

they were employed by Insulations, Inc. as insulators and insulator helpers, and on

January 5, 2015, they were working at a Sunoco Logistics Terminal. While working,

they heard a loud noise or explosion and saw a thick “chemical cloud” (later

determined to be a fire suppressant chemical called “Purple K”) moving toward

them. As they tried to leave the work area, several of them fell and sustained injuries.

According to the petition, the Fire Suppression System was activated while the S&B

instrument technicians were working in the area, and when they attempted to “put

the system in alarm fail,” it caused the loud noise the Individual Plaintiffs heard and

1 Sunoco is not a party to this appeal. At trial, Sunoco Logistics Partners Operations GP LLC and Sunoco Logistics Partners LP (collectively “Sunoco”) were defendants. 2 We do not name the individual plaintiffs but rather refer to them herein collectively as “the Individual Plaintiffs” because the Individual Plaintiffs settled their claims, and this appeal concerns claims between the defendant S&B, Sunoco’s insurer (intervenor Zurich), and third-party defendant Scallon. 2 the cloud that the Individual Plaintiffs saw. The Individual Plaintiffs alleged that the

Defendants’ (S&B and Sunoco) negligence proximately caused their injuries.3

S&B filed a general denial answer and an Original Third-Party Petition

against Scallon. In the Third-Party Petition S&B alleged that Scallon’s negligence

in performing “PLC Technical Services”4 was a proximate cause of the release of

Purple K and of the Individual Plaintiffs’ injuries. S&B also asserted that if S&B is

found liable for Individual Plaintiffs’ damages, then Scallon, as a third-party

defendant, would be liable to S&B for contribution. According to S&B’s third-party

petition, it entered into a Subcontract Agreement (“Subcontract”) with Scallon that

included a provision that Scallon defend, indemnify, and hold S&B harmless against

any and all losses. S&B asserted a claim for contribution and indemnity under the

Subcontract Agreement and a Purchase Order.

3 Specifically, the Individual Plaintiffs alleged the following acts or omissions of negligence by all the Defendants: failure to provide a safe environment; failure to inspect the worksite to make sure it was safe; failure to remedy the condition on the premises that caused the Individual Plaintiffs’ injuries; failure to warn the Individual Plaintiffs of the sound of an explosion or the release of the cloud; negligent installation of the fire suppression system; negligent check of the fire suppression system in a crowded area with workers present; negligent inspection of the fire suppression system; negligent coordination of work on the fire suppression system and in the Area 250 Pipe Rack; negligent training of employees working on or around the fire suppression system; and negligent purchase and use of the fire suppression system. 4 A purchase order included in the record reflects “PLC” refers to “Programmable Logic Controller.” 3 Sunoco also filed a third-party petition against Scallon. According to Sunoco,

discovery revealed that software and hardware errors had resulted from Scallon’s

negligence, Scallon had subcontracted with S&B to provide services, and Scallon’s

negligence was the proximate cause of the accidental release of fire retardant.

Sunoco sought contribution and indemnity from Scallon.

In its Answer, Scallon asserted a general denial and the following affirmative

defenses: the injuries were caused by the acts or omissions of others for whom

Scallon was not responsible; the injuries resulted from new and independent

intervening or superseding causes; the injuries resulted from Third-Party Plaintiff’s

own negligence. We include a chart below to demonstrate the relationship of the

parties.

4 Over the course of the underlying lawsuit, S&B amended its petition against

Scallon, and S&B’s Ninth Amended Original Petition was S&B’s live pleading

when the trial court rendered its Final Judgment. In the Ninth Amended Original

Petition, S&B asserted claims against Scallon pursuant to its Subcontract, as well as

the Terms and Conditions of the Purchase Order. S&B asserted a claim for breach

of contract, alleging that Scallon (1) changed the work from what was instructed

without obtaining prior written approval by S&B, and (2) Scallon failed to indemnify

S&B as required by the Purchase Order and Subcontract. S&B also asserted a claim

against Scallon for breach of express warranty under both the Purchase Order and

Subcontract, alleging that Scallon’s work had defects and did not conform to S&B’s

specifications. Specifically, S&B alleged that it directed Scallon that both the inputs

and outputs of the Fire Suppression System should be configured as “non-fail-safe”

but that Scallon configured the inputs as “fail-safe.” S&B also asserted claims for

breaching the implied warranty of fitness for a particular purpose and the warranty

of merchantability under the UCC. 5 S&B sought damages of $2,350,000 that it paid

in settling with the Individual Plaintiffs plus $2,000,000 paid by insurers on its

behalf, Zurich American Insurance Company (“Zurich”) and American Guarantee

and Liability Insurance Company.

5 Citing Tex. Bus. & Com. Code Ann. §§ 2.314, 2.315. 5 Scallon filed a Counterclaim against S&B, alleging that S&B failed to meet

its obligations under the Sunoco Contract, and S&B’s errors and omissions were the

proximate cause of the equipment failure, the release of Purple K, and the Individual

Plaintiffs’ injuries, and sought a recovery of Scallon’s attorney’s fees and expenses

in the lawsuit. Scallon also demanded that S&B defend and indemnify Scallon

pursuant to the parties’ Subcontract. The Counterclaim also stated a claim for breach

of contract, alleging that S&B breached its obligations under the Subcontract to

defend and indemnify Scallon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Fisk Electric Co. v. Constructors & Associates, Inc.
888 S.W.2d 813 (Texas Supreme Court, 1994)
Randall's Food Markets, Inc. v. Johnson
891 S.W.2d 640 (Texas Supreme Court, 1995)
Faulk Management Services v. Lufkin Industries, Inc.
905 S.W.2d 476 (Court of Appeals of Texas, 1995)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Palmer v. Espey Huston & Associates, Inc.
84 S.W.3d 345 (Court of Appeals of Texas, 2002)
Gilbane Building Co. v. Keystone Structural Concrete, Ltd.
263 S.W.3d 291 (Court of Appeals of Texas, 2007)
Ramirez v. State
263 S.W.3d 40 (Court of Appeals of Texas, 2006)
Man GHH Logistics GmbH v. Emscor, Inc.
858 S.W.2d 41 (Court of Appeals of Texas, 1993)
Guillot v. Hix
838 S.W.2d 230 (Texas Supreme Court, 1992)
Stine v. Stewart
80 S.W.3d 586 (Texas Supreme Court, 2002)
Great American Products v. Permabond International
94 S.W.3d 675 (Court of Appeals of Texas, 2003)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Air Liquide America Corp. v. Crain Bros., Inc.
11 F. Supp. 2d 709 (S.D. Texas, 1997)
Ethyl Corp. v. Daniel Construction Co.
725 S.W.2d 705 (Texas Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
S&B Engineers & Constructors, Ltd. and Zurich American Insurance Company v. Scallon Controls, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sb-engineers-constructors-ltd-and-zurich-american-insurance-company-v-texapp-2024.