MEMORANDUM AND ORDER
ATLAS, District Judge.
Plaintiff Air Liquide America Corporation (“Air Liquide”) has filed a Motion for Partial Summary Judgment on Claim for Contractual Indemnification [Doc. # 17] (“Air Liquide Motion”). In addition, Plaintiff has filed a Motion for Summary Judgment on Breach of Contract a.nd Affirmative Defense Claim [Doc, # 52] (“Air Liquide’s Second Motion”). Defendant Crain Brothers, Inc. (“Crain”).has filed a Cross-Motion for Summary Judgment [Doc. #22] (“Crain Motion”).
Air Liquide claims in its motions that it is entitled to indemnity for amounts it expended in resolving claims brought against it by Enterprise Products Company (“Enterprise”) and Montell USA (“Montell”) as a result of damage to an Enterprise pipeline. Air Liquide maintains that the pipeline damage arose from work performed by Defendant Crain, which Crain vehemently denies.
The Court has considered the motions, the responses and replies, all other matters of record in this case, and the relevant authorities. For the reasons stated herein, summary judgment in favor of Air Liquide is granted in part, and Crain’s motion for summary judgment is denied.
On or before August 29, 1997, Air Liquide is to advise the Court of any remaining issues in this case that are appropriate for summary judgment; Crain may respond on or before September 5, 1997. The parties should be prepared to argue the identified issues at docket call on September 12, 1997.
FACTUAL BACKGROUND
In September 1992, Air Liquide entered into a contract with Crain which provided that Crain would construct two Air Liquide pipelines in the Beaumont Texas, area, from the Gulf States Utility Facility to the North Star Steel Facility (“the Beaumont project”).
See
Construction Contract (Exhibit B to Air Liquide Motion). The constructed Air Liq-uide pipelines crossed four existing pipelines, including an Enterprise pipeline. Air Liq-uide alleges that, during construction of its pipelines in September or October of 1992, Crain damaged the Enterprise pipeline, resulting in a slow failure over a fifteen-month period and eventually a leak on January 19, 1994. Air Liquide further claims that the pipeline was leaking from a “severe dent,” and that the damaged portion of the Enterprise pipeline was directly above an Air Liq-uide line.
Enterprise and its customer, Montell USA, brought claims against Air Liquíde as a result of the leak, which Air Liquide settled in late 1995 for $512,328.66.
See
Settlement Agreements (Exhibits H and I to Air Liquide Motion). Air Liquide in turn sought indemnity from Crain. However, Crain maintains that it is not responsible for the leak in the Enterprise pipeline, and refused to indemnify Air Liquide. Each side has presented expert testimony supporting its position.
The parties disagree as to whether or not the 1992 Construction Contract contained an indemnity clause controlling the damage at issue in this case. The parties also disagree about the effect of a General Hold Harmless Agreement between them, which was executed in 1988.
Each side has lodged multiple objections to the other party’s evidence. Since the Court’s opinion herein cites almost none of the challenged material, all such objections are denied as moot unless specifically noted otherwise. If necessary, such objections may be reurged at a later stage of the litigation.
DISCUSSION
The Construction Contract’s Indemnity Provisions
Section Three of the Construction Contract, entitled General Conditions, contains indemnity provisions.
Under the heading “Injuries and Damages,” the Construction Contract provides as follows:
Without regard to negligence of [sic: or] fault,
[Crain] assumes the entire responsibility and liability for, and agrees to indemnify, protect and hold [Big Three, Air Liquide’s predecessor in interest], its employees and representatives harmless
from and against
all
claims, damages, expense and liabilities of
every kind or character
arising in whole or in part out of acts or failure to act of [Crain], its agents or employees, or out of the performance of the Work by [Crain], its agents and employees, or its subcontractors and their agents and employees....
Construction Contract, at 54, § 3.1504 (emphasis added).
This general agreement to indemnify has broad and inclusive language.
Crain argues that this indemnity provision is facially unenforceable because it fails the conspicuousness requirement. The eonspicu-ousness requirement mandates that an indemnity provision must be presented so that “a reasonable person against whom a clause is to operate ought to have noticed it.”
Dresser Industries, Inc. v. Page Petroleum, Inc.,
853 S.W.2d 505, 508 (Tex.1993);
see McGehee v. Certainteed Corporation,
101 F.3d 1078, 1080 (5th Cir.1996).
Crain argues that since the indemnity provision quoted above “was not set out in large type or upper case, or even a heading,” it would not “attract the attention of a reasonable person” and therefore the provision is unenforceable. Crain’s Response to Air Liquide’s Supplemental Motion for Summary Judgment [Doc. # 50] (“Crain’s Response to Supplemental Motion”), at 3.
See Dresser,
853 S.W.2d at 511;
McGehee,
101 F.3d at 1080-81;
U.S. Rentals, Inc. v. Mundy Service Corp.,
901 S.W.2d 789, 792 (Tex.App.—Houston [14th Dist.] 1995, writ denied);
Enserch Corp. v. Parker,
794 S.W.2d 2, 8 (Tex.1990).
However, the requirement of fair notice does not apply when the indemnitee establishes that the indemnitor had actual notice or knowledge of the indemnity agreement.
Dresser,
853 S.W.2d at 508 n. 2. Charles Perry, the Executive Vice President of Crain who executed the Construction Contract on Crain’s behalf, testified in his deposition that he was aware that Section 3.1504 was in the contract before he signed:
Q: Okay. Let me refer you now to Section 3.1504.
A: Okay.
Q: Were you familiar with this provision before you signed the contract?
A: Without reading it — would you like me to read it and let me see what—
Q: Sure. Why don’t you read it and just tell me if you’re — if you were aware that provision was in the contract.
A: Yes, that’s correct.
Q: All right. You were aware that provision was in the contract—
A: Uh-huh.
Q: —prior to signing it—
A: That’s correct.
Q: —is that correct?
A: That’s correct.
Q: And this type of provision is not an unusual provision in these types of contracts; is it?
A: No.
Q: Okay. And what do you as a contractor call this type of provision?
A: Let me see here. It’s basically a hold harmless provision.
Deposition of Charles Perry (Exhibit A to Air Liquide’s Reply to Crain’s Response to Air Liquide’s Motion for Summary Judgment on Breach of Contract and Affirmative Defense Claim [Doc. # 54]) (“Perry Deposition”), at 59-60.
■ Given the testimony by Perry establishing that Crain had actual knowledge of the indemnification provision, the Court holds that the indemnity provision in the Construction Contract is enforceable against Crain.
Moreover, even absent actual knowledge, the Court holds that the provision in question satisfied the conspicuousness requirement under the commercial circumstances existing between the parties. Although the provision was beyond the prime signature page in the contract and its heading and text were not different from the heading and text of other provisions,
the provision was introduced by a heading in all capital letters stating “INJURIES AND DAMAGES.” In addition, the heading was listed clearly in the table of contents for Section Three. The provision was not on the back of a page or in small, hard-to-read type. It was surrounded by related provisions outlining the parties’ liability.
See McGehee,
101 F.3d at 1080-81;
Dresser,
853 S.W.2d at 510-511. A heading such as “INJURIES AND DAMAGES” in the parties’ “General Conditions” section of a commercial contract was designed to draw attention to matters related to damages, such as indemnification.
1988 General Hold Harmless Agreement
In addition, there is a “General Hold Harmless Agreement” executed by the par
ties on April 14, 1988, upon which Air Liq-uide relies for indemnification.
See
General Hold Harmless Agreement (Exhibit A to Air Liquide Motion). For the reasons stated below, the Court holds that this General Hold Harmless Agreement also serves as a basis for Crain’s indemnity obligations to Air Liquide. Therefore, it provides an additional ground supporting summary judgment in favor of Air Liquide on the issue of indemnification.
The agreement provides in part as follows: [Crain] shall reimburse Big Three for, and indemnify Big Three and hold it harmless from and against any and all loss, costs, damage, expense, claims, suits and liability on account of any and all damage to, or loss or destruction of any properlty [sic] (including without limitation, the work covered hereunder and the property of [Crain], any subcontractors arid Big Three) or injury to or death of any person (including, without limitation, employees of [Crain], any subcontractors and Big Three or any other person) arising directly or indirectly out of, or in connection with any work or contract or the making of any deliveries of materials or equipment to Big Three whether caused by a negligent act or omission OF EITHER PARTY HERETO, or their employees or otherwise. IT IS EXPRESSLY UNDERSTOOD BY CONTRACTOR THAT BY THE TERMS OF THIS PARAGRAPH CONTRACTOR IS HEREBY AGREEING TO INDEMNIFY BIG THREE AND HOLD BIG THREE HARMLESS FROM THE CONSEQUENCES OF BIG THREE’S OWN NEGLIGENCE EXCEPT THAT CONTRACTOR ASSUMES NO LIABILITY FOR THE SOLELY NEGLIGENT ACTS OF BIG THREE, ITS AGENTS, SERVANTS OR EMPLOYEES.
General Hold Harmless /Agreement, at 1, ¶ 2(b). The agreement further provides that it “will cover all business relations and transactions between the parties
until revoked
by notice in writing to Big Three_”
Id.
at 2, ¶ 5 (emphasis added). Air Liquide argues that this General Hold Harmless Agreement was in effect between the parties and legally obligates Crain to indemnify Air Liquide for the damage to the Enterprise pipeline because it had not been revoked in writing, as required by.its terms. Crain argues that, since the Construction Contract for the Beaumont project did not reference or incorporate the General Hold Harmless Agreement, it effectively invalidated, canceled and/or voided the General Hold Harmless Agreement for purposes of the Beaumont project. Response, at 6; Affidavit of Neil Crain (Exhibit 2 to Crain Motion) (“Crain Affidavit”). Crain’s argument ignores the plain language of the earlier general agreement, which required a revocation before it became ineffective. '
General principles of contract construction apply to indemnity contracts.
See Fireman’s Fund Ins. Co. v. Murchison,
937 F.2d 204, 207 (5th Cir.1991);
Kenneth H. Hughes Interests, Inc. v. Westrup,
879 S.W.2d 229, 232 (Tex.App.—Houston [1st Dist.] 1994, writ denied) (court seeks to reach a “common sense” reading of the indemnity agreement). A court is to “give meaning to each of a contract’s provisions, in light of the circumstances surrounding the contract’s execution, excluding statements of parties as to what they intended.”
Fireman’s Fund,
937 F.2d at 207. When a contract is not ambiguous, “the instrument alone will be deemed to express the intention of the parties, for it is objective, not subjective, intent that controls.”
Watkins v. Petro-Search, Inc.,
689 F.2d 537 (5th Cir.1982) (citing
Sun Oil Co. v. Madeley,
626 S.W.2d 726, 731 (Tex.1981)).
Crain maintains that the Construction Contract is “a lengthy document detailing every aspect of the business relationship
formed between1 Air Liquide and Crain for the purpose of constructing and installing the two pipelines at the Beaumont site,” and therefore that it, rather than the General •Hold Harmless Agreement, governs the parties’ relations. Crain Affidavit, at l.
Although Crain is correct that the Construction Contract does not mention or explicitly incorporate the General Hold Harmless Agreement,
this does not preclude application of the general agreement. Nothing in the “Scope of Contract Documents” provision, set out in full in the margin, indicates that the documents identified represent the exclusive agreement between the parties, although such a clause could easily have been inserted. Moreover, the fact that the documents listed “for the contract for the work herein described,” Construction Contract, § 1.0302, does not revoke a
General
Hold Harmless Agreement which appears to contemplate being in force throughout the parties’ more specific contracts. Indeed, the General Hold Harmless Agreement states as follows:
For and in consideration of Ten and no/ lOÓths Dollars ($10.00) and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged,
and in further consideration of the performance of any work or contract for, and in the making any deliveries of materials or equipment to BIG THREE INDUSTRIES, INC.,
its divisions or subsidiaries, hereafter referred to as “Big Three,” [Crain] shall perform the same as an independent contractor in a prudent manner and shall undertake responsibility for the condition of the premises and the taking of all proper precautions pertinent to such performance.
General Hold Harmless Agreement, at 1, ¶ 1 (all emphasis added).
See id.
at 1, ¶20)) (Crain agrees to hold Air Liquide harmless for damage “arising directly or indirectly out
of, or in connection with any work
or contract
or the making of any deliveries of materials or equipment to Big Three”) (emphasis added). The fact that the general agreement specifically states that it is in effect until revoked in writing further evidences the parties’ intent that it apply over the course of various specific contracts.
Crain argues that a specific contract occurring after a prior agreement can overrule the prior agreement, directing the Court’s attention to
National Convenience Stores, Inc. v. Martinez,
784 S.W.2d 468, 471 (TexApp.—Texarkana 1989, writ denied), and Keith A.
Nelson Co. v. R.L. Jones, Inc.,
604 S.W.2d 351 (Tex.Civ.App.—San Antonio 1980, writ ref d n.r.e.). These cases state that “a later contract is incorporated with or correlated to an old agreement when that is the intention of the parties expressed in the later agreement.”
See National Convenience Stores,
784 S.W.2d at 470 (“Lease Cancellation” expressly stated that the prior agreement, a lease, was to be terminated);
Nelson,
604 S.W.2d at 353-54 (subcontract had different parties than prime contract, made no reference to prime contract, and did not incorporate prime contract’s general conditions; therefore, general conditions of prime contract allowing for additional compensation were not incorporated into subcontract). Crain’s cases, however, do not compel a holding in Crain’s favor in this ease, in which the General Hold Harmless Agreement states that it will govern, while explicitly referencing that there nevertheless may be other contracts. Texas courts have recognized that several documents should be read together when they pertain to the same transaction, even if the documents were executed at different times and even if they do not expressly refer to one another.
Richland Plantation Co. v. Justiss-Mears Oil,
671 F.2d 154, 156 (5th Cir.1982);
Massey v. Galvan,
822 S.W.2d 309, 315 (Tex.App.—Houston [14th Dist.] 1992, writ denied);
Milam Development Corp. v. 7*7*0*1 Wurzbach Tower Council,
789 S.W.2d 942, 945 (Tex.App.San Antonio 1990, writ denied). Moreover, of course, an agreement should be read so as not to render any provision meaningless.
Richland,
671 F.2d at 156.
Thus, the Court rejects Crain’s various arguments and holds that the two valid agreements, whether read together or separately, clearly mandate that Crain indemnify Air Liquide for damage caused by Crain’s work. As noted previously, Crain has directed the Court to no language in the Construction Contract which excludes or revokes other agreements. To the extent that Crain argues that the Construction Contract is ambiguous as to whether or not it revokes the General Hold Harmless Agreement, the Court is unpersuaded. Crain has directed the Court to no language even suggesting such revocation. The non-exclusive “Scope of Contract Documents” provision does not accomplish revocation. In addition, even if the Construction Contract were ambiguous and subject to more than one reasonable interpretation, the General Hold Harmless Agreement certainly is not, and Crain has not argued that it is. The agreement states clearly that it is effective until revoked in writing and Crain does not argue it was explicitly revoked.
Moreover, there is no conflict between the two documents since, whether they are read together or separately, the result is to indemnify Air Liquide for damage resulting from Crain’s work.
See Cothron Aviation, Inc. v. Avco Corp.,
843 S.W.2d 260, 263 (Tex.App.—Ft. Worth 1992, writ denied) (“[a] binding agreement may be collected from various writings between parties so long as such different writings do not conflict in respect to the terms, parties, and the like”). Air Liquide is indemnified both by the General Hold Harmless Agreement and by an independent provision in the Construction Contract.
This Court is required to ascertain “the meaning that would be attached to the wording ‘by a reasonably intelligent person acquainted with all operative usages and knowing all the circumstances prior to a
contemporaneous with the making of the integration, other than oral statements by the parties of what they intended.’ ”
Watkins,
689 F.2d at 538 (quoting
Sun Oil,
626 S.W.2d at 731). In this case, there is no basis to hold that a reasonably intelligent person acquainted with the circumstances prior to the Construction Contract would not consider the General Hold Harmless Agreement to be applicable. Thus, the . Court concludes as a matter of law that a reasonable person would have understood the General Hold Harmless Agreement was agreement in effect unless and until revoked in writing.
Watkins,
689 F.2d at 540-41.
Finally, to the extent Crain argues that it misunderstood the meaning of the agreement’s language, the Court notes that Crain has not even alleged conditions that would warrant setting aside the contract on the grounds of unilateral mistake.
See Interfirst Bank of Abilene, N.A. v. Lull Mfg.,
778 F.2d 228, 232 (5th Cir.1985).
The general rule in Texas, and in other jurisdictions, is that a unilateral mistake is insufficient to warrant setting the contract asidé unless the mistake is induced by acts • of the other party.... An exception to the general rule precluding relief for a unilateral mistake exists when: 1) the mistake is of so great a consequence as to make enforcement of the contract unconscionable; 2) the mistake relates to a material feature of the contract; and 3) the mistake is made regardless of the exercise of ordinary care.
In light of all of the surrounding circumstances, the Court therefore holds that the Construction Contract was not ambiguous and did not revoke the General Hold Harmless Agreement.
See Hanssen,
904 F.2d at 269.
Cause of Damage to Enterprise Pipeline
The parties vigorously dispute whether or not the claims of Enterprise and Mon-tell in fact arose in connection with Cram’s work on the Air Liquide pipeline.
The Court holds, on the basis of the current record, that there is a genuine question of material fact on the issue of causation.
Enterprise and Montell investigated the damage to the Enterprise pipeline and concluded that Crain was responsible for the damage.
See
Demand Letter from Enterprise to Air Liquide, dated February 1, 1994 (Exhibit E to Air Liquide Motion).
Enterprise’s letter states that its excavation of the leaking pipe revealed that the Enterprise line was “severely damaged” and leaking at both top and bottom, and that the leak was located directly over a Big Three pipeline installed in October 1992.
See id.
Crain argues that the leak “is scientifically and as a matter or engineering principles not Crain’s fault.” Crain Motion, at 3. In particular, Crain points to the conclusion of its expert that the failure of the Enterprise pipeline was the result of a single occurrence which happened at or about the time of the failure and therefore was unrelated to Crain’s work fifteen months earlier. Paul J. Kovach, an expert in the field of metallurgy and failure analysis of pipelines, discusses the data and report of Law Engineering and Environmental Services:
This electron microscopy conclusively establishes, in my opinion, that the failure of what is known as the Enterprise pipeline was the result of a single occurrence which transpired at or about the time the pipeline failed, i.e., in January, 1994. In my opinion, therefore, the pipeline failure in question could not have been related in any way to work performed by Crain Brothers, Inc., approximately 15 months earlier, i.e., in and around October, 1992. As a matter of fact, Law Engineering reached this same type of conclusion in its report where the report states that “It is certain, however, that the crack development did not happen by stages over a two year period. This was a single event.” .... I know Les Harrington who is one of the engineers who prepared the Law Engineering report ..., and he has explained to me that the above mentioned language in the Law Engineering report means that Law Engineering’s opinion was that
a single occurrence happening at'or about the time of the 'pipeline failure precipitated that failure.
Affidavit of Paul J. Kovach (Exhibit 1 to Response). (“Kovach Affidavit”), at 2, ¶¶ 3^4 (emphasis added) (quoting Law Engineering Report (Exhibit B to Kovach Affidavit), at 5).
Kovach also states that he visually inspected the fractured surfaces and that his inspection confirmed the results of the elec-tronmicroscopy.
Id.
at 3, ¶ 5.
Air Liquide has presented evidence from the investigation of the leak showing that the Enterprise line was severely damaged from top to bottom, that the line was leaking from a severe crimp or dented area, and that the crimped area was directly above the spot where the Air Liquide line crossed the Enterprise line.
See
Affidavit of Charles R. Morin, P.E. (Exhibit A to Air Liquide’s Reply to Defendant’s Response to Plaintiffs Motion for Summary Judgment and Response to Defendant’s Motion for Summary Judgment [Doe. #29] (“Plaintiffs Reply”)) (“Morin Affidavit”);
Photographs of Damaged Line (Exhibit D to Air Liquide Motion).
Air Liquide also has presented evidence from the owner of the property that no other rights-of-way or easements were granted from the time Air Liquide secured its easement until February 1994.
See
Air Liq-uide’s Supplemental Motion, at 5; Affidavit of Robert Dunham (Exhibit J to Air Liquide Motion) (there is no record of any right-of-way or easement granted across the Beaumont property from the time of the Big Three easement until February 1994, and if such an easement had been granted it would be reflected in the records).
Charles R. Morin, P.E., an engineer and metallurgist, has provided an affidavit which concludes as follows:
[T]his pipeline failure exhibits the characteristics of a failure caused by contractor damage during the construction of the Air Liquide lines. This conclusion is supported by, among other factors: the location of the damage; the type of damage to the pipe; the history of the pipeline; the
operation of the pipeline; and the evidence of strain-age embrittlement.
Morin Affidavit, at 2. He further explains that “strain-age embrittlement” is a “well-known phenomenon in the metallurgical field.”
Id.
Strain-age embrittlement is a process by which a piece of metal that is damaged becomes increasingly brittle over time ... leaving it increasingly susceptible to failure. It is the initial damage to the metal, however, which precipitates the later failure.
The evidence of strain age embrittlement is important in at least three respects. First, strain-age embrittlement follows severe damage to the metal, such as would be caused by contractor damage, such as a bump by machinery or a crease caused by outside force. Second, strain-age embrit-tlement explains the delay between the time of the damage and the time of the leak. Third, strain-age embrittlement results in the brittle, cleavage-type fracture surfaces noted by everyone who has examined this pipe specimen.
Id.
In response to the Kovach Affidavit, Morin states that Kovach’s statement that the failure could not have been the result of Crain’s work fifteen months earlier is “inconsistent with a sound, well-founded methodology based on good grounds.”
Id.
Morin’s report concludes that the damage to the Enterprise pipeline was due to a “large blunt force directed at the side of the pipe by a powerful, strong and hard object, such as the side of an excavator bucket,” and that the initial damage was inflicted by Crain. Report of Engineering Systems Inc. (Exhibit B to Morin Affidavit) (“Morin Report”), at 6.
The only reasonable conclusion that can be drawn from the location and nature of the dent and crease is that the damage was done by [Crain] during the laying of the dual 6-inch lines where they passed immediately under the specific leak area_ Even though the physical damage to the line was immediate, because of the nature of the cracking observed and progressive brittleness that should be expected by natural strain aging, the probability of leakage would continue to increase with time after the damage is inflicted. Because natural strain aging requires some appreciable time to develop, brittle failure a year (or more) after the initial damage is introduced is not at all surprising.... The writer has personal experience with delayed brittle failures of this sort in pipeline and other applications as well.
Id.
at 4-5.
Both Air Liquide and Crain argue that summary judgment is appropriate in their favor on this issue because the other side has presented insufficient evidence to create a genuine question of material fact. Both sides also challenge the other’s expert testimony under
Daubert v. Merrell Dow Pharmaceuticals,
509 U.S. 579, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993).
The Court holds, on the record presented, that the differing opinions of the parties’. experts creates a fact question. However, the Court has not reached the
Daubert
issues the parties intend to present. Therefore, summary judgment on the issue of causation is denied at this time. The parties are instructed to file all
Daubert
motions by September 3, 1997, and to file all responses on or before September 15, 1997. In addition, the parties are to confer and inform the Court whether they seek a hearing on the
Daubert
issues and, if so, (1) the amount of time necessary for the hearing, and (2) whether live testimony will be presented.
Right of Contribution
Crain argues that Air Liquide may not seek contribution, directing the Court to Texas case law holding that “when a co-defendant settles with a plaintiff, the settlement extinguishes the settling defendant’s right of contribution from an alleged nonset-tling joint tortfeasor.”
See Insurance Co. of N. Am. v. Security Ins. Co.,
790 S.W.2d 407, 410 (Tex.App.—Houston [1st Dist.] 1990, no writ); Crain’s Reply to Air Liquide’s Reply to Defendant’s Response to Plaintiffs Motion for Partial Summary Judgment ... [Doc. # 37], at 1-2. However, Air Liquide states that it is not relying upon common law indemnification. The Construction Contract itself provides that Air Liquide may settle claims brought against it and then in turn
seek reimbursement from Crain,
see
Construction Contract, § 1.1505, and Crain has presented no argument or authority suggesting that the common law doctrine on which it relies invalidates this provision of the contract.
Statute of Limitations and Tort Issues
The arguments raised by the parties concerning statute of limitations for various alleged torts, the applicability of strict liability in trespass, and other tort issues appear moot in light of the above holdings.
However, if the parties disagree, they may so advise the Court at the upcoming docket call setting.
CONCLUSION
For the foregoing reasons, it is hereby
ORDERED that Air Liquide’s Motion for Partial Summary Judgment on Claim for Contractual Indemnification [Doc. # 17] is GRANTED IN PART. Summary judgment is granted in favor of Air Liquide on the issue of contractual indemnification, and denied on the issue of causation. It is further
ORDERED that Cram’s Cross-Motion for Summary Judgment [Doc. # 22] is DENIED. It is further
ORDERED that on or before August 29, 1997, Air Liquide is to advise the Court of any remaining issues in this case that are appropriate for summary judgment. Crain may respond on or before September 5, 1997. The parties should be prepared to argue the identified issues at docket call on September 12,1997. It is further
ORDERED that the parties are instructed to file all
Daubert
motions by September 3, 1997, and to file all responses on or before September 15, 1997. The parties are to confer and inform the Court whether they seek a hearing on the
Daubert
issues and, if so, (1) the amount of time necessary for the hearing, and (2) whether live testimony will be presented.