Air Liquide America Corp. v. Crain Bros., Inc.

11 F. Supp. 2d 709, 1997 U.S. Dist. LEXIS 22687, 1997 WL 910750
CourtDistrict Court, S.D. Texas
DecidedAugust 22, 1997
DocketCivil Action H-96-0443
StatusPublished
Cited by3 cases

This text of 11 F. Supp. 2d 709 (Air Liquide America Corp. v. Crain Bros., Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air Liquide America Corp. v. Crain Bros., Inc., 11 F. Supp. 2d 709, 1997 U.S. Dist. LEXIS 22687, 1997 WL 910750 (S.D. Tex. 1997).

Opinion

MEMORANDUM AND ORDER

ATLAS, District Judge.

Plaintiff Air Liquide America Corporation (“Air Liquide”) has filed a Motion for Partial Summary Judgment on Claim for Contractual Indemnification [Doc. # 17] (“Air Liquide Motion”). In addition, Plaintiff has filed a Motion for Summary Judgment on Breach of Contract a.nd Affirmative Defense Claim [Doc, # 52] (“Air Liquide’s Second Motion”). Defendant Crain Brothers, Inc. (“Crain”).has filed a Cross-Motion for Summary Judgment [Doc. #22] (“Crain Motion”).

Air Liquide claims in its motions that it is entitled to indemnity for amounts it expended in resolving claims brought against it by Enterprise Products Company (“Enterprise”) and Montell USA (“Montell”) as a result of damage to an Enterprise pipeline. Air Liquide maintains that the pipeline damage arose from work performed by Defendant Crain, which Crain vehemently denies.

The Court has considered the motions, the responses and replies, all other matters of record in this case, and the relevant authorities. For the reasons stated herein, summary judgment in favor of Air Liquide is granted in part, and Crain’s motion for summary judgment is denied.

On or before August 29, 1997, Air Liquide is to advise the Court of any remaining issues in this case that are appropriate for summary judgment; Crain may respond on or before September 5, 1997. The parties should be prepared to argue the identified issues at docket call on September 12, 1997.

FACTUAL BACKGROUND

In September 1992, Air Liquide entered into a contract with Crain which provided that Crain would construct two Air Liquide pipelines in the Beaumont Texas, area, from the Gulf States Utility Facility to the North Star Steel Facility (“the Beaumont project”). See Construction Contract (Exhibit B to Air Liquide Motion). The constructed Air Liq-uide pipelines crossed four existing pipelines, including an Enterprise pipeline. Air Liq-uide alleges that, during construction of its pipelines in September or October of 1992, Crain damaged the Enterprise pipeline, resulting in a slow failure over a fifteen-month period and eventually a leak on January 19, 1994. Air Liquide further claims that the pipeline was leaking from a “severe dent,” and that the damaged portion of the Enterprise pipeline was directly above an Air Liq-uide line.

Enterprise and its customer, Montell USA, brought claims against Air Liquíde as a result of the leak, which Air Liquide settled in late 1995 for $512,328.66. See Settlement Agreements (Exhibits H and I to Air Liquide Motion). Air Liquide in turn sought indemnity from Crain. However, Crain maintains that it is not responsible for the leak in the Enterprise pipeline, and refused to indemnify Air Liquide. Each side has presented expert testimony supporting its position.

The parties disagree as to whether or not the 1992 Construction Contract contained an indemnity clause controlling the damage at issue in this case. The parties also disagree about the effect of a General Hold Harmless Agreement between them, which was executed in 1988.

Each side has lodged multiple objections to the other party’s evidence. Since the Court’s opinion herein cites almost none of the challenged material, all such objections are denied as moot unless specifically noted otherwise. If necessary, such objections may be reurged at a later stage of the litigation.

*711 DISCUSSION

The Construction Contract’s Indemnity Provisions

Section Three of the Construction Contract, entitled General Conditions, contains indemnity provisions. 1 Under the heading “Injuries and Damages,” the Construction Contract provides as follows:

Without regard to negligence of [sic: or] fault, [Crain] assumes the entire responsibility and liability for, and agrees to indemnify, protect and hold [Big Three, Air Liquide’s predecessor in interest], its employees and representatives harmless from and against all claims, damages, expense and liabilities of every kind or character arising in whole or in part out of acts or failure to act of [Crain], its agents or employees, or out of the performance of the Work by [Crain], its agents and employees, or its subcontractors and their agents and employees....

Construction Contract, at 54, § 3.1504 (emphasis added). 2 This general agreement to indemnify has broad and inclusive language.

Crain argues that this indemnity provision is facially unenforceable because it fails the conspicuousness requirement. The eonspicu-ousness requirement mandates that an indemnity provision must be presented so that “a reasonable person against whom a clause is to operate ought to have noticed it.” Dresser Industries, Inc. v. Page Petroleum, Inc., 853 S.W.2d 505, 508 (Tex.1993); see McGehee v. Certainteed Corporation, 101 F.3d 1078, 1080 (5th Cir.1996). 3 Crain argues that since the indemnity provision quoted above “was not set out in large type or upper case, or even a heading,” it would not “attract the attention of a reasonable person” and therefore the provision is unenforceable. Crain’s Response to Air Liquide’s Supplemental Motion for Summary Judgment [Doc. # 50] (“Crain’s Response to Supplemental Motion”), at 3. See Dresser, 853 S.W.2d at 511; McGehee, 101 F.3d at 1080-81; U.S. Rentals, Inc. v. Mundy Service Corp., 901 S.W.2d 789, 792 (Tex.App.—Houston [14th Dist.] 1995, writ denied); Enserch Corp. v. Parker, 794 S.W.2d 2, 8 (Tex.1990).

However, the requirement of fair notice does not apply when the indemnitee establishes that the indemnitor had actual notice or knowledge of the indemnity agreement. Dresser, 853 S.W.2d at 508 n. 2. Charles Perry, the Executive Vice President of Crain who executed the Construction Contract on Crain’s behalf, testified in his deposition that he was aware that Section 3.1504 was in the contract before he signed:

Q: Okay. Let me refer you now to Section 3.1504.
A: Okay.
Q: Were you familiar with this provision before you signed the contract?
A: Without reading it — would you like me to read it and let me see what—
Q: Sure. Why don’t you read it and just tell me if you’re — if you were aware that provision was in the contract.
A: Yes, that’s correct.
Q: All right. You were aware that provision was in the contract—
*712 A: Uh-huh.
Q: —prior to signing it—
A: That’s correct.
Q: —is that correct?
A: That’s correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 F. Supp. 2d 709, 1997 U.S. Dist. LEXIS 22687, 1997 WL 910750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-liquide-america-corp-v-crain-bros-inc-txsd-1997.