Spartan Drywall v. Post Goldtex, L.P.

CourtSuperior Court of Pennsylvania
DecidedFebruary 5, 2016
Docket1182 EDA 2015
StatusUnpublished

This text of Spartan Drywall v. Post Goldtex, L.P. (Spartan Drywall v. Post Goldtex, L.P.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spartan Drywall v. Post Goldtex, L.P., (Pa. Ct. App. 2016).

Opinion

J-A01003-16

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

SPARTAN DRYWALL BUILDERS, INC., IN THE SUPERIOR COURT OF D/B/A SPARTAN DRYWALL, INC. PENNSYLVANIA

Appellee

v.

POST GOLDTEX, L.P. AND POST GENERAL CONTRACTING

Appellants No. 1182 EDA 2015

Appeal from the Order Entered April 8, 2015 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): June Term, No. 002448

BEFORE: LAZARUS, J., OTT, J., and STEVENS, P.J.E.*

MEMORANDUM BY STEVENS, P.J.E.: FILED FEBRUARY 05, 2016

Appellants Post Goldtex, L.P. (“Post Goldtex”) and Post General

Contracting (“Post Contracting”) appeal from the order of the Honorable

Patricia McInerney of the Court of Common Pleas of Philadelphia County

overruling their preliminary objections to the Mechanic’s Lien Enforcement

Action of Respondent Spartan Drywall Builders, Inc., d/b/a Spartan Drywall,

Inc. (“Spartan”) and dismissing arbitration proceedings. After careful

review, we affirm.

On October 22, 2012, Post Goldtex and Spartan entered a construction

contract (the “Agreement”) for Spartan to install drywall and perform related

construction work at Post Goldtex Apartments located at 315 North 12 th

Street in Philadelphia (the “Property”). The Agreement consists of several

*Former Justice specially assigned to the Superior Court. J-A01003-16

documents that together constitute a “Contract Package” and provides that

Spartan would be compensated under a Timing and Payment Schedule.

On February 7, 2014, Spartan filed a Mechanic’s Lien against the

Property and any interest of its owners, which it alleged were Post Goldtex

and Post Contracting. On May 27, 2014, Post Goldtex filed a praecipe for a

rule to file a complaint upon the mechanic’s lien.

On June 16, 2014, Spartan filed the instant action against Post Goldtex

and Post Contracting. The trial court stayed the action after the parties

agreed to submit their dispute to mediation. Although the parties met with

a jointly-appointed mediator on one occasion, Post Goldtex concluded that a

second mediation session would not resolve the dispute and filed a demand

for arbitration on January 12, 2015.

In response, Spartan filed its First Amended Complaint, again naming

both Post Goldtex and Post Contracting as defendants, as it alleged that both

entities are “reputed owners” of the Property. Spartan sought a judgment in

the amount of $259,681.46 against Post Goldtex and Post Contracting for

their failure to pay Spartan for work, equipment, and materials pursuant to

their obligations in the Agreement.

On March 5, 2015, Post Goldtex and Post Contracting filed preliminary

objections asserting that the Agreement requires the parties to submit their

dispute to arbitration and that Post Contracting was improperly joined to the

mechanic’s lien action. Post Goldtex and Post Contracting also filed a motion

to stay the proceedings in this action and to compel Spartan to submit to

-2- J-A01003-16

arbitration. On April 8, 2015, the trial court entered an order overruling the

preliminary objections and denying the motion to stay the proceedings. This

timely appeal followed. Post Goldtex and Post Contracting complied with the

trial court’s order to file a Concise Statement of Errors Complained of on

Appeal pursuant to Pennsylvania Rule of Appellate Procedure 1925(b).

On appeal, Post Goldtex and Post Contracting claim that the trial court

erred in denying their preliminary objections when they allege that (1) the

Agreement contains an unequivocal agreement to arbitrate and (2) Post

Contracting was improperly joined as a party to this action. While as a

general rule, an order denying preliminary objections is interlocutory and is

not appealable as of right, there is a narrow exception for an order refusing

to compel a case to arbitration, which involves a jurisdictional question that

must be decided by the courts. Pisano v. Extendicare Homes, Inc., 77

A.3d 651, 654 (Pa.Super. 2013).

Our standard of review is well-established:

We review a trial court's denial of a motion to compel arbitration for an abuse of discretion and to determine whether the trial court's findings are supported by substantial evidence. In doing so, we employ a two-part test to determine whether the trial court should have compelled arbitration. The first determination is whether a valid agreement to arbitrate exists. The second determination is whether the dispute is within the scope of the agreement.

Elwyn v. DeLuca, 48 A.3d 457, 461 (Pa.Super. 2012) (quoting Smay v.

E.R. Stuebner, Inc., 864 A.2d 1266, 1270 (Pa.Super. 2004)).

-3- J-A01003-16

Arbitration is a matter of contract, and parties to a contract cannot be compelled to arbitrate a given issue absent an agreement between them to arbitrate that issue. Even though it is now the policy of the law to favor settlement of disputes by arbitration and to promote the swift and orderly disposition of claims, arbitration agreements are to be strictly construed and such agreements should not be extended by implication.

Elwyn, 48 A.3d at 461 (quoting Cumberland–Perry Area Vocational–

Technical School v. Bogar & Bink, 396 A.2d 433, 434–35 (Pa. Super.

1978)).

As noted above, the parties’ Agreement consists of several documents

that make up the “Contract Package.” The first document, entitled

“Agreement of Critical Business Terms,” was specifically drafted for this

project and designates Post Goldtex as “Owner” and Spartan as

“Contractor.” The Contract Package also includes, inter alia, (1) American

Institute of Architects (AIA) Form A201-1997, General Conditions of the

Contract for Construction (hereinafter “Form A201”) and (2) AIA Form A401-

2007, Standard Form of Agreement between Contractor and Subcontractor

(hereinafter “Form A401”).

Both Forms A201 and A401 contain provisions related to the

enforcement of the Agreement. Form A201 designates Post Goldtex as the

Owner of the Property and Spartan as the Contractor. With respect to

arbitration, Form A201 specifically states:

§ 4.5 MEDIATION

§ 4.5.1. Any Claim arising out of or related to the Contract … shall be subject to mediation as a condition precedent to

-4- J-A01003-16

arbitration or the institution of legal or equitable proceedings by either party. ***

§ 4.6 ARBITRATION

§ 4.6.1. Any Claims arising out of or related to the Contract … shall … be subjected to arbitration. Prior to arbitration, the parties shall endeavor to resolve disputes by mediation in accordance with the provisions of Section 4.5.

AIA Document A201-1997, §§ 4.5, 4.6.1.

In contrast, Form A401 designates Post Contracting as the Contractor

and Spartan as the Subcontractor. Form A401 specifically states:

§ 6.1 MEDIATION

§ 6.1.1. Any Claim arising out of or related to this Subcontract … shall be subject to mediation as a condition precedent to binding dispute resolution ***

§ 6.2 BINDING DISPUTE RESOLUTION

For any claim subject to, but not resolved by mediation pursuant to Section 6.1, the method for binding dispute resolution shall be as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cumberland-Perry Area Vocational-Technical School Authority v. Bogar & Bink
396 A.2d 433 (Superior Court of Pennsylvania, 1978)
Denlinger, Inc. v. Agresta
714 A.2d 1048 (Superior Court of Pennsylvania, 1998)
Barton v. Lowe's Home Centers, Inc.
124 A.3d 349 (Superior Court of Pennsylvania, 2015)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Elwyn v. DeLuca
48 A.3d 457 (Superior Court of Pennsylvania, 2012)
Weiley v. Albert Einstein Medical Center
51 A.3d 202 (Superior Court of Pennsylvania, 2012)
Pisano v. Extendicare Homes, Inc.
77 A.3d 651 (Superior Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Spartan Drywall v. Post Goldtex, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/spartan-drywall-v-post-goldtex-lp-pasuperct-2016.