Southwestern Bell Telephone, L.P. v. Missouri Public Service Commission

530 F.3d 676, 45 Communications Reg. (P&F) 540, 2008 U.S. App. LEXIS 13062, 2008 WL 2468718
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 20, 2008
Docket06-3701, 06-3726, 06-3727
StatusPublished
Cited by30 cases

This text of 530 F.3d 676 (Southwestern Bell Telephone, L.P. v. Missouri Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone, L.P. v. Missouri Public Service Commission, 530 F.3d 676, 45 Communications Reg. (P&F) 540, 2008 U.S. App. LEXIS 13062, 2008 WL 2468718 (8th Cir. 2008).

Opinion

BYE, Circuit Judge.

Southwestern Bell Telephone, L.P., d/b/a SBC Missouri (SBC), attempted to negotiate interconnection agreements with several competitors (Competing Local Exchange Carriers (CLEC)) as required by the Telecommunications Act of 1996, Pub.L. No. 104-104, 110 Stat. 56 (codified as amended in scattered sections of 47 U.S.C.). When those negotiations failed, the dispute was submitted to arbitration as provided for under the Act and the resulting arbitrator’s decision was adopted by the Missouri Public Service Commission (MPSC). SBC petitioned the district *680 court 2 for review, arguing the MPSC exceeded its authority by ordering SBC to allow CLECs broader access to its facilities network than mandated by the Act. SBC also argued the MPSC erred in ordering it to provide CLECs access to entrance facilities at cost. The district court found the MPSC exceeded its authority when it decided issues relating to which network facilities SBC was required to make available to CLECs. The district court affirmed the MPSC’s decision setting the rate SBC could charge CLECs for entrance facilities needed for interconnection. On appeal, the MPSC and various CLECs argue the district court erred in concluding the MPSC exceeded its authority. In its cross-appeal, SBC argues the district court erred in setting the rate it could charge for access to entrance facilities. We affirm.

I

For years, local telephone service was provided by companies holding monopolies which were subject to regulation by local governments. In passing the Telecommunications Act of 1996, Congress chose to encourage competition among telephone service providers and to impose greater federal regulation. The Act requires existing telephone companies, which previously held monopolies (Incumbent Local Exchange Carriers (ILEC)), to make their local facilities or networks available to newcomers — CLECs—for a fee, if the CLEC’s ability to provide service was “impaired” without access. This appeal focuses on two sections of the Act which implemented these requirements — 47 U.S.C. §§ 251 and 271.

Under § 251, all ILECs are required to negotiate interconnection agreements with impaired CLECs and to lease certain of their network facilities at cost-based rates known as “total element long-run incremental cost” (TELRIC). If an agreement cannot be negotiated, the Act requires unresolved § 251 disputes be submitted to arbitration. Section 251 compliance, including the arbitration process, is subject to oversight by state public service commissions.

Prior to 2005, the Federal Communications Commission (FCC) took the position ILECs were required under § 251 to make all basic elements of their local networks (Unbundled Network Elements-Platform (UNE or UNE-Platform)) available to CLECs at TELRIC rates. Courts reviewing the FCC’s orders, however, disagreed when the practice caused the competition pendulum to swing too far in favor of CLECs. See, e.g., AT & T Corp. v. Iowa Utils. Bd., 525 U.S. 366, 390, 119 S.Ct. 721, 142 L.Ed.2d 835 (1999) (“[I]f Congress had wanted to give blanket access to incumbents’ networks on a basis as unrestricted as the scheme the Commission has come up with.... It would simply have said ... whatever requested element can be provided must be provided.”); U.S. Telecom Ass’n v. FCC, 290 F.3d 415, 424 (D.C.Cir.2002) (“If parties who have not shared the risks are able to come in as equal partners on the successes, and avoid payment for the losers, the incentive to invest plainly declines.”); Verizon New England, Inc. v. Maine Pub. Utils. Comm’n, 509 F.3d 1, 9 (1st Cir.2007) (“[MJaking a monopolist share ... ‘essential facilities’ can promote competition; but it can also retard investment, handicap competition detrimentally, and discourage alternative means of achieving the same result that could conceivably en *681 hance competition.... ”). In 2005, the FCC issued its Triennial Review Remand Order (TRRO), which no longer required ILECs to make all elements of their local networks available under § 251 at TEL-RIC rates. See Order on Remand, In the Matter of Unbundled Access to Network Elements, Review of the Section 251 Unbundling Obligations of Incumbent Local Exchange Carriers, 20 F.C.C.R. 2533 (2005).

The TRRO also concluded CLECs were no longer impaired with respect to “entrance facilities” and ILECs were not required to provide such facilities as UNEs at TELRIC rates. An entrance facility is a connection between a switch maintained by an ILEC and a switch maintained by a CLEC. It is a means of transferring traffic from one carrier’s network to another’s, and facilitates an ILEC’s obligation under the Act to interchange traffic among networks. CLECs also use entrance facilities to route customer traffic between a CLEC’s customer and the CLEC’s switch — a practice known as “backhauling.” When used to transfer traffic from one network to another, entrance facilities are used for interconnection purposes. When used for backhauling, they are not used for interconnection. The TRRO found CLECs did not need entrance facilities for backhauling CLEC to CLEC traffic. Conversely, the TRRO reiterated that ILECs are required to provide entrance facilities at TELRIC rates under § 251(c)(2) if necessary for interconnection purposes.

In addition to § 251, which applies to all ILECs, § 271 imposes additional requirements on ILECs previously part of the Bell network (Bell Operating Companies (BOC)). Under § 271, BOCs wishing to enter the long-distance market must demonstrate they have, in addition to complying with § 251, made additional network facilities listed in a “competitive checklist” available to CLECs. Unlike § 251, the language of § 271 expressly states § 271 compliance is determined by the FCC.

Prior to 2005, § 271 compliance was not a contentious issue because the FCC’s interpretation of § 251 required ILECs to provide § 271 network facilities as part of the § 251 agreements. It did not matter whether states had authority to force ILECs to comply with § 271, because they could order the same level of compliance by enforcing § 251. After the FCC issued its 2005 TRRO reducing the number of network facilities ILECs were required to make available, states and CLECs began exploring whether ILECs could be required to provide the same network facilities, i.e., the UNE-Platform, by enforcing the competitive checklist requirements of § 271. That brings us to the primary issue in this case — the authority of states to enforce § 271.

After the Act was passed, SBC negotiated § 251 agreements with various CLECs and complied with the additional requirements of § 271. As SBC and the CLECs were in the process of renegotiating their § 251 agreements, the FCC issued its 2005 TRRO reducing the number of network facilities ILECs were required to make available.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charter Advanced Services (MN), LLC v. Lange
259 F. Supp. 3d 980 (D. Minnesota, 2017)
Qwest Corp. v. Minnesota Public Utilities Commission
684 F.3d 721 (Eighth Circuit, 2012)
Talk America, Inc. v. Michigan Bell Telephone Co.
131 S. Ct. 2254 (Supreme Court, 2011)
Qwest Corporation v. Arizona
Ninth Circuit, 2009
Qwest Corp. v. Arizona Corp. Commission
567 F.3d 1109 (Ninth Circuit, 2009)
Alton Armstrong v. State
Court of Appeals of Texas, 2009
Firstcom, Inc. v. Qwest Corp.
555 F.3d 669 (Eighth Circuit, 2009)
Southwestern Bell Telephone Co. v. Combs
270 S.W.3d 249 (Court of Appeals of Texas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
530 F.3d 676, 45 Communications Reg. (P&F) 540, 2008 U.S. App. LEXIS 13062, 2008 WL 2468718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-lp-v-missouri-public-service-commission-ca8-2008.