Southwestern Bell Telephone Co. v. Meader Construction Co.

574 S.W.2d 839, 1978 Tex. App. LEXIS 3964
CourtCourt of Appeals of Texas
DecidedNovember 22, 1978
Docket6724
StatusPublished
Cited by11 cases

This text of 574 S.W.2d 839 (Southwestern Bell Telephone Co. v. Meader Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone Co. v. Meader Construction Co., 574 S.W.2d 839, 1978 Tex. App. LEXIS 3964 (Tex. Ct. App. 1978).

Opinion

OPINION

WARD, Justice.

A road builder known as Meader Construction Company sued Southwestern Bell Telephone Company for damages caused from its having made false and fraudulent representations to the Plaintiff as to dates it would remove its telephone poles and other facilities from right-of-ways contracted to be constructed by the Plaintiff. Trial was to a jury which returned a verdict sustaining the Plaintiff’s contentions. Judgment was then entered for Meader against Southwestern Bell for $56,934.00 actual damages and $230,000.00 exemplary damages. The Defendant appeals asserting error in the Court’s Charge, as well as numerous insufficiency of evidence points. We reverse and remand as to that part of the judgment which we have described.

Meader Construction Company was the successful bidder on two road improvements undertaken by the City of San Antonio known as the Babcock Road Project and the Walters-Moore Street Project. The first was the Babcock Road Project and it was advertised for bidding in November, 1973. As was its custom, the City invited contractors interested in bidding the Project to a pre-bid conference on November 20, 1973. The conference was attended by the Plaintiff’s President, Ike Meader, and other interested contractors, as well as representatives of the various utilities whose facilities would be affected by the construction. Pri- or to such a conference, the interested contractors would have previously received a set of bid documents, and would have probably made an on site investigation and preliminary cost analysis of the Project. At the conference, various problems were discussed and explained, and dates that the various utilities would relocate their obstructing facilities were settled. Ike Mead-er testified that at that meeting the Defendant’s engineer told him that the telephone poles in the Project area would be removed by January 1, 1974. He testified that this statement was relied upon by him in making his work plans, his cost analysis of the Project, and his bid to the City, which was finally accepted. Construction then started on the Babcock Road Project on January 14, 1974. According to Mead-er’s version, when he started excavation, the telephone poles were in his way and the poles thereafter seriously interfered with the performance of his contract with the City. When he complained to the Telephone Company, he stated that all he got was a runaround and a switch from one person to another. As a result, he had to work the entire area with the poles right in the middle of it, and the net result was that his costs were increased by $30,434.00.

As to the Walters-Moore Street Project, the pre-bid conference was held on December 3,1974. Mr. Meader again attended the meeting, though no Southwestern Bell representative was present. The Plaintiff’s bid was then accepted, and on January 24, 1975, a preconstruction meeting was held which Mr. Meader and the representatives of the various utilities, including the Defendant, attended. Due to the nature of the Project, Mr. Meader explained that he proposed to work the job in phases, taking the phases in numerical sequence as required by the City. At that conference, the Southwestern Bell representative told those in attendance that Bell’s conflicts would be cleared prior to construction, and a letter was read explaining that Bell’s conflicts for the entire length of the Walters-Moore Street Project would be cleared by approximately March 31, 1975. It developed that Bell Telephone did not remove its conflicts in time and there were some sixty-eight telephone poles in the way on the Walters-Moore Street Project. In some areas it resulted in Meader not being able to work around the poles as he had done on the *842 Babcock Road Project because they were too numerous and were located in the middle of the proposed street. Instead of working the job in phases as planned, he was forced to skip phase and as a result lost time in moving back and forth from one phase to another. Since the orderly sequence was disrupted, Mr. Meader estimated that his actual costs on the Walters-Moore Street Project were increased by approximately $26,500.00.

The Plaintiff’s theory that the Telephone Company had made false and fraudulent representations to it which resulted in increased construction costs for the Company was submitted to the jury separately as to each Project. On the Babcock Road Project, the jury determined by its answers to the issues submitted that (1) the Defendant, its agents, servants, and employees knowingly represented and made statements to the Plaintiff prior to the Plaintiff’s bid that all telephone installations and obstructions in conflict would be removed prior to the beginning of the construction; (2) that the representations and statements were material in nature and were made to the Plaintiff with the intention that the Plaintiff should act upon them; (3) that the Plaintiff believed and relied upon the representations and statements, and that but for them it would not have made the bid that it did to the City of San Antonio; (4) that the representations and statements of the Defendant, its agents, servants, and employees were false; and (5) that as a result of the representations and statements, the Plaintiff was damaged. The five special issues, numbered 7 through 11 inclusive, were in regard to the Walters-Moore Street Project and were worded in a similar form to the first five issues, and were all answered in favor of the Plaintiff’s position.

The trial Court’s Special Issue No. 4 was as follows:

“Do you find from a preponderance of the evidence that the representations and statements, if any, of the defendant, Southwestern Bell Telephone Company, its agents, servants and employees, were false?”
Special Issue No. 10 was identical in form, but because of its sequence related to the Walters-Moore Street Project. The Defendant objected to Special Issue No. 4 for the reason that:
“* * * same fails to inquire as to whether or not the representations and statements made by defendant Southwestern Bell were known to be false at the time that they were made; therefore constitutes an evidentiary issue and not an ultimate issue in the case.”

Defendant objected to Special Issue No. 10 for the reason that:

“* * * same fails to inquire as to whether or not the representations and statements were known to be false at the time that they were made and whether or not they were made with intent to deceive Meader Construction Company, and therefore is an evidentiary issue only and not an ultimate issue.”

The trial Court overruled these two objections, and the overruling of the two objections is the subject of the first two points of error presented by the Defendant.

Before proceeding further, we again note that the Plaintiff’s cause of action is based on alleged false and fraudulent representations as to future events. Normally, a failure to discharge a promise regarding the doing of an act in the future is not fraud, otherwise every breach of a contract would amount to fraud. However, since the state of mind of a person making a representation is a fact, it is susceptible of being misrepresented and thus can become the basis of a suit for fraudulent representation. Where a promise regarding future action is made with the intent that it will not be performed and is made to deceive a person, then it is actionable as a fraudulent representation. Stanfield v. O’Boyle,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
574 S.W.2d 839, 1978 Tex. App. LEXIS 3964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-co-v-meader-construction-co-texapp-1978.