Southwest Power Pool, Inc. v. Federal Energy Regulatory Commission

736 F.3d 994, 407 U.S. App. D.C. 247, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2013 WL 6231560, 2013 U.S. App. LEXIS 24009
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 3, 2013
Docket19-5152
StatusPublished
Cited by6 cases

This text of 736 F.3d 994 (Southwest Power Pool, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwest Power Pool, Inc. v. Federal Energy Regulatory Commission, 736 F.3d 994, 407 U.S. App. D.C. 247, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2013 WL 6231560, 2013 U.S. App. LEXIS 24009 (D.C. Cir. 2013).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

“WILLIAMS, Senior Circuit Judge:

This dispute between two regional transmission organizations (“RTOs”) turns on the interpretation of a single contract provision. The Federal Energy Regulatory Commission resolved the conflict against petitioner Southwest Power Pool (“SPP”). Applying both the Administrative Procedure Act and the “Chevron-\Ike analysis” that governs review of such an interpretation, Colorado Interstate Gas Co. v. FERC, 599 F.3d 698, 701 (D.C.Cir.2010), we find that the Commission failed to provide a reasoned explanation for its decision. It leapt to an interpretation of one item of evidence without explaining its implicit rejection of alternative interpretations, and, equally without explanation (o'r at least adequate explanation), it disregarded' evidence that the applicable law required it to consider. See Order on Petition for Declaratory Order, 136 FERC ¶ 61,010 (2011) (“Order”), rehearing denied, Order on Rehearing, 138 FERC ¶ 61,055 (2012) (“Order on Rehearing”). Accordingly, its decision was arbitrary and capricious, and we vacate and remand the orders.

SPP is an RTO adjacent to another RTO, the Midwest Independent Transmission System Operator (“MISO”), recently renamed Midcontinent Independent System Operator, evidently to reflect its continuing expansion to the south. Entergy Arkansas, an operating subsidiary of En-tergy Corporation and at the time of the petition not part of any RTO, abuts both SPP and MISO.

In 2011 Entergy Arkansas made a regulatory filing addressing the possibilities of joining MISO or SPP, and indicating a preference for MISO. Order, 136 FERC ¶ 61,010 at p. 7. That preference rested at least in part on the considerable savings in production costs that joining MISO would yield relative to joining SPP. Entergy Corp., RTO Path for Entergy Operating Companies 4, 9; Joint Appendix (“J.A.”) 225, 230.. To realize those savings, however, MISO must be able to move to Entergy Arkansas electricity generated elsewhere in MISO. Although Entergy Arkansas has transmission connections to both SPP and MISO, its connection to MISO is relatively limited compared to those to SPP and others. MISO would therefore need to *996 rely on these other, non-MISO transmission providers. MISO believes that its Joint Operating Agreement (“JOA”) with SPP gives it the right to rely on SPP’s transmission facilities to do so, even after Entergy Arkansas becomes part of MISO itself, an event that appears imminent— Entergy Arkansas has received multiple regulatory approvals to join MISO. See Press Release, Entergy Corp., APSC Issues Final Conditional Order on Entergy Arkansas’ MISO Integration (Apr. 11, 2013). Section 5.2 of the JOA, the provision invoked by MISO, provides:

Sharing Contract Path Capacity. If the Parties have contract paths to the same entity, the combined contract path capacity will be made available for use by both Parties. This will not create new contract paths for either Party that did not previously exist. SPP will not be able to deal directly with companies wdth which it does not physically or contractually interconnect and the [MISO] will not be able to deal directly with companies with which it does not physically or contractually interconnect.

The parties agree that at the time of FERC’s decision, with Entergy Arkansas distinct from MISO, both RTOs had “contract paths to the same- entity,” to wit Entergy Arkansas. Thus Section 5.2 allowed one RTO to use the other’s transmission network to move electricity to En-tergy Arkansas. That is where agreement ends.

The alternative readings of Section 5.2 are these: MISO understands “contract path to the same entity” to include any physical or contractual interconnection and to apply regardless of whether the “entity” is a part of either RTO. So, even if Enter-gy Arkansas becomes part of MISO, En-tergy Arkansas will (under MISO’s view) be an “entity” to which both RTOs have contract paths. SPP argues that an RTO cannot have a “contract path to’.’ itself or to part of itself. Thus, once Entergy Arkansas joins MISO, Section 5.2 will no longer (under SPP’s view) apply, despite the existence of a “physical or contractual” interconnection between the part of MISO made up of Entergy Arkansas and the other parts of MISO.

After the parties negotiated for some time in vain, MISO petitioned FERC for a declaratory judgment on the interpretation of Section 5.2. FERC adopted MISO’s reading, finding that the term “contract path” was broad enough to encompass any physical or contractual interconnection, and that “entity” could include any operating entity, whether or not it was part of one of the RTOs. Order, 136 FERC ¶ 61,-010 at pp. 61-62; Order on Rehearing, 138 FERC ¶ 61,055 at p. 19. We discuss the details of the Commission’s decision as they become relevant.

Before reaching the merits of SPP’s arguments, we must first address FERC’s assertions that SPP lacks standing and that, in any case, its claims are unripe.

On standing, FERC contends that SPP’s interest in the interpretation of Section 5.2 is too attenuated to create an injury that is “actual or imminent.” Lu-jan v. Defenders of Wildlife, 504 U.S. 555, 560-61, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992). It says that no harm will ensue for SPP unless Entergy Arkansas elects to join MISO and secures the necessary state and federal approval, and MISO then seeks to use Section 5.2 to transmit electricity to Entergy Arkansas. Thus FERC characterizes SPP’s injury as “too speculative.”

We have held that an agency interpretation that defines contractual rights and obligations may itself create enough of an injury to confer standing on a party to that contract. See Dominion Transmis *997 sion, Inc. v. FERC, 533 F.3d 845, 852 (D.C.Cir.2008). We need not explore the scope of that decision, because the Commission’s decision here cast a very present shadow over the three-way maneuvering between SPP, MISO and Entergy Arkansas. The latter’s parent corporation (En-tergy) proclaimed in its 2011 presentation on joinder with MISO that “[rjesolution of the JOA issue in MISO’s favor would increase the potential production cost savings and further tip the benefit ratio in MISO’s favor.” Entergy Corp., RTO Path for Entergy Operating Companies 9; J.A. 230. It is surprising that FERC should think that standing rules require SPP to remain in limbo while its competitor MISO woos Entergy Arkansas with FERC’s assurance of access to SPP’s infrastructure—an assurance that SPP believes is unlawful.

FERC’s ripeness argument fares no better. Ripeness of course typically involves an inquiry into the fitness of the issues for judicial review and the hardship to the parties of withholding that review. Abbott Labs. v. Gardner, 387 U.S. 136, 149, 87 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Childrens Health Defense v. FCC
25 F.4th 1045 (D.C. Circuit, 2022)
Natural Resources Defense Council, Inc. v. Sobeck
244 F. Supp. 3d 66 (District of Columbia, 2017)
Safari Club International v. Jewell
213 F. Supp. 3d 48 (District of Columbia, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
736 F.3d 994, 407 U.S. App. D.C. 247, 43 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 2013 WL 6231560, 2013 U.S. App. LEXIS 24009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwest-power-pool-inc-v-federal-energy-regulatory-commission-cadc-2013.