Southfund Partners III v. Sears, Roebuck and Co.

57 F. Supp. 2d 1369, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20044, 49 ERC (BNA) 1052, 1999 U.S. Dist. LEXIS 16620, 1999 WL 557684
District Court, N.D. Georgia·Decided July 30, 1999·No. 1:97-cv-01058·Published·Cited by 11 cases

Opinion

MEMORANDUM OPINION & ORDER

STORY, District Judge.

Plaintiff Southfund Partners III [“Southfund”] brought this action against Defendant Sears, Roebuck and Company [“Sears”] to recover costs associated with the cleanup of property formerly owned by Sears under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C. §§ 9601 et seq. [“CERCLA”] and the Georgia Hazardous Site Response Act, O.C.G.A. § 12-8-90 et seq. [“HSRA”]. Before the Court are Defendant’s Motion for Summary Judgment [13-1] and Defendant’s Motion to Withdraw or Amend Admissions [20-1], As an initial matter, the Court grants Defendant’s Motion to Withdraw or Amend Admissions. After reviewing the entire record and considering all arguments of the parties, this Court enters the following Order.

*1372 I. Factual Background

A. Discovering the Contamination.

Sears purchased a two-story brick building at the corner of Ponce De Leon Avenue and Glen Iris Drive in Atlanta, Georgia from a large local laundry and dry cleaning company in 1966. (Ricketts Dep. at Ex. 1.) The building served as the main plant for the laundry company, but Sears converted the building into a carpentry shop and used it as such until Sears sold the property to Southfund in November of 1988. (Ricketts Dep. at Ex. No. 1; Rick-etts Aff. at ¶ 3.) By December of 1988, Southfund discovered and arranged for the removal of three underground storage tanks- — two 500 gallon solvent tanks on the north side of the building and one approximately 20,000 gallon fuel tank on the south side. 1 (Holton Dep. at Ex. No. 7, Hellinger Aff. at ¶¶ 4-6 & Ex. B.) In 1991 — over two years after Southfund removed the tanks — the United States Postal Service considered purchasing the property from Southfund, but declined after conducting an investigation that revealed substantial contamination in two plumes located on the property. (Smithgall Dep. at Ex. No. 2, Smithgall Aff. at ¶ 6.)

Gregory Holton, Southfund’s. expert who also oversaw most of the cleanup effort, opined that the discharge of dry-cleaning solvents from the solvent tanks caused the contamination found in Plume A; Holton traced the contamination in Plume B to the fuel tank. (Smithgall Aff. at ¶ 6; Holton Dep. at 86-89, 91, Ex. No. 14.) Using a mathematical model, Holton concluded the contamination found in Plume A resulted from dry cleaning fluids and solvents being introduced into the soil between the years 1978 and 1984, during the time Sears owned the property. (Holton Dep. at 15, 82-35.) As Holton described it, the solvent materials escaped from the two solvent tanks as rainwater filled the tanks and displaced them, causing the materials to contaminate the soil and move into the groundwater. (Holton Dep. at 45.) This conclusion is supported by testimony of Joe Hellinger, the person Southfund paid to remove the solvent tanks. He testified that, at the time of their removal, the solvent tanks had no cap or cover on them and were filled with rainwater that had “evidently over the years forced out whatever material had been kept in the tanks into the surrounding area.” (Hellinger Aff. at ¶ 5.)

In the summer of 1994, the Georgia Department of Natural Resources [“DNR”] examined the site, concluded a reportable quantity of hazardous substances had been released, and placed the property on its Hazardous Site Inventory [“HSI”]. (Smithgall Dep. at Ex. No. 42.) Numerous factors are considered to determine whether a release constitutes a reportable quantity, including the extent to which the contaminated portion of the property is accessible. In a July 14, 1994 letter to DNR, Southfund’s legal counsel pointed out that the contaminated portion of the property was enclosed in a fence — a mitigating factor not reflected in DNR’s initial analysis — and explained this fact should lower DNR’s assessment of the release from a reportable to a non-reportable quantity. (Smithgall Dep. at Ex. No. 42.) Southfund also stated in the letter that “additional factors” aside from the limited access could “cause the site’s ... score to be lowered even further.” (Smithgall Dep. at Ex. No. 42.) DNR responded on August 5, 1994, agreeing that “a release exceeding a reportable quantity has not occurred at this site[,]” and removing the property from the HSI. (Smithgall Dep. at Ex. No. 42.)

B. Southfund’s Initiation of Cleanup Efforts.

One year after DNR removed the property from its HSI, Southfund employed *1373 Industrial Compliance [“IC”] to begin remedial action in the fall of 1995. (Smith-gall Aff. at ¶ 6.) Southfund decided to clean the site for two reasons: (1) doing so would enhance the marketability of the property: (2) the possibility DNR could add the property to the HSI once again if access to the contaminated area became unrestricted. (Smithgall Dep. at 149.) The remedial action taken by Southfund consisted of three components. First, IC installed a series of extraction wells used to pump contaminated groundwater from the property into the city sewer system. (Holton Dep. at 74.) Second, IC drilled sparging wells and injected air into the plume to increase the rate of decay of hazardous materials in the soil. (Holton Dep. at 74-75.) Third, IC used a vacuum extraction system to remove air from areas near the sparging wells. (Holton Dep. at 75.)

C. Sears’s Knowledge of the Solvent Tanks and Fuel Tanks During its Ownership of the Property.

Mr. James Ricketts, Sears’s superintendent over the building in question during the entire time Sears owned it, testified that neither he nor anyone else associated with Sears knew of “any contamination on any part of the property occurring during or before the period of Sears’ ownership.” (Ricketts Aff. at ¶ 4.) In addition, no one at Sears knew during Sears’s ownership of the property the underground solvent tanks and fuel tank 2 were even located on the property. (Ricketts Aff. at ¶ 4.) But a May 3, 1950 plat Sears possessed indicates the existence of three solvent tanks — two 500 gallon tanks and one 1000 gallon tank — and two fuel tanks — one a 3900 gallon tank and the other a 18,000 gallon tank — in the same location where South-fund found and removed the two 500 gallon solvent tanks and the approximately 20,000 gallon fuel tank.

D. The “As Is” Provision in the Sales Contract.

John Smithgall, an experienced real estate investor, purchased the property on behalf of Southfund for investment purposes. Smithgall knew from the outset of negotiations with Sears that the subject building was referred to as the “laundry building,” but explained in his deposition that he simply believed at the time that clothes had only been laundered on site; he did not realize that a dry-cleaning business, complete with all the harsh chemicals associated therewith, had operated out of the building. (Smithgall Dep. at 37-38.) Southfund agreed to purchase the property “as is,” the sales contract stating as follows:

The Property and the improvements thereon, including, but not limited to, the T.V.

Free access — add to your briefcase to read the full text and ask questions with AI

Southfund Partners III v. Sears, Roebuck and Co., 57 F. Supp. 2d 1369, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20044, 49 ERC (BNA) 1052, 1999 U.S. Dist. LEXIS 16620, 1999 WL 557684 (N.D. Ga. 1999).

57 F. Supp. 2d 1369 (Southfund Partners III v. Sears, Roebuck and Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related