Southern Pac. Co. v. McCready

47 F.2d 673, 1931 U.S. App. LEXIS 3532
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 9, 1931
DocketNo. 6297
StatusPublished
Cited by7 cases

This text of 47 F.2d 673 (Southern Pac. Co. v. McCready) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Pac. Co. v. McCready, 47 F.2d 673, 1931 U.S. App. LEXIS 3532 (9th Cir. 1931).

Opinion

RUDKIN, Circuit Judge.

This ease was before this court on a former appeal, where a full statement of the facts as then presented will be found. McCready v. Southern Pac. Co., 26 F.(2d) 569, 570. After reciting the facts on the former appeal, Judge Dietrich stated the questions for decision as follows:

“The questions for consideration therefore are whether the facts as above recited make a prima facie case of actionable negligence, and, if so, whether they disclose such contributory negligence as in law bars recovery.”

The first question was answer-ed in the affirmative, the second in the negative, and the judgment of involuntary nonsuit was accordingly reversed and the case remanded for a new trial. Upon a retrial a verdict was returned for the plaintiff, and from the judgment on the verdict this appeal was prosecuted.

Before taking up the assignments of error, it might be well to consider wherein the present record differs from the record on the former appeal, if at all. The appellant contends that it differs in two respects: First, because the construction contract between the appellant and the independent contractor was in evidence on the last trial and not on the former; and, second, because the defense of assumption of risk, withdrawn on the for[674]*674mer trial, was interposed and relied on at the last trial.>

The first difference suggested does not in fact exist: When the construction contract was offered in evidence by -the appellee, the appellant interposed an objection, and as a result of that objection the offer was expressly limited to the provision of the contract fixing the time for the commencement of the work and the time for its completion. True, the entire contract is found in the record .on the present appeal, but it was not read to the jury, nor was it taken to the jury room. The contention that the entire contract was in evidence is therefore without merit; and whether the court below erred in referring to other provisions of the contract not in evidence, in its charge to the jury, will be considered later, as will also the question of assumption of risk.

A witness called by the appellee testified that he represented the appellant while the building in question was under construction and that it was his duty to see that the contractor lived up to specifications and to orders. He further'testified that, shortly before the appellee was injured, the construction foreman in charge of the work for the contractor notified him that they were about to take down certain scaffolding and that the proximity of the live wires rendered the work dangerous. For this reason, he was requested to deaden the wires or cut off the electric current, but refused to do so. A general objection was interposed to this testimony on the ground that it was incompetent^ irrelevant, and immaterial, hearsay, and no foundation laid. It is now urged that it does not appear that the employee who was thus notified had authority to deaden the wires or cut off the current. We do not think that the general objection thus interposed was sufficient for any purpose. The stock form of objection, incompetent, irrelevant, and immaterial, is too general to raise any question for review in an appellate court unless the testimony is so palpably immaterial that any form of objection is sufficient to challenge the attention of the trial court. Sparf and Hansen v. United States, 156 U. S. 51, 57, 15 S. Ct. 273, 39 L. Ed. 343; Sparks v. Territory of Oklahoma (C. C. A.) 146 F. 371, 374. In any event, whether the agent upon whom the request was made had authority to deaden the wires or cut off the current, or not, his relation to his employer and to the work in hand was such that notice to him was notice to the employer. Confronted with the same testimony on the former appeal, we said:

“Desiring to remove the scaffolding, the contractor’s foreman notified representatives of the defendant and sought to have the current temporarily cut off, but his requests were refused; and finally, selecting plaintiff and others of the more experienced workmen, he assigned to them the task of taking down the scaffolding, at the same time giving them appropriate warnings that they should exercise care to avoid injury from the wires.”

From that conclusion we see no adequate reason to depart.

There is some contention over the admission of testimony bearing upon the right of the appellant to use or extend the live wires into the uncompleted portion of the building where the appellee and his associates were at work, and over the charge of the court relating to that question, or right. On the former appeal we said:

“But here we do not have the case of a mere invitee in the ordinary sense. As we understand, it is not disputed that, being by virtue of his employment in privity with the contractor, plaintiff’s right to be and to work in and about the unfinished unit was of equal dignity to that of his employer, and that the duty of the defendant to refrain from subjecting him to unnecessary peril was as great at least as was its duty in that respect toward the contractor. * * *
“While the defendant was under no affirmative duty to keep the premises safe for the workmen, it was under the duty to refrain from actively creating a danger.”

We still adhere to the views there expressed, and, regardless of the abstract right of the appellant to use or occupy the uncompleted portion of the building, we are convinced that there was neither excuse nor justification for extending this deadly agency into the uncompleted portion of the building where men were necessarily employed in the work of dismantling the scaffolding. For these reasons, there was no error in the admission or exclusion of testimony, or in the charge of the court, even if the charge was based on provisions of the contract not in evidence, as claimed.

This brings us to the perplexing question of assumption of risk when applied to the particular facts before the court. As already stated, this defense was withdrawn or abandoned'on the former trial, because counsel for appellant was then of opinion that such a defense was not available inasmuch as the-relation of master and servant did not exist between the appellant and the appellee. After [675]*675the ease was remanded, an amended answer was filed combining, in a single paragraph, the defenses of contributory negligence and assumption of risk, and upon the trial the court was requested to instruct the jury that, under a given state of facts, the appellee would be guilty of contributory negligence, and, by another instruction, that under tho same identical state of facts he would assume the risk. But the confusion of counsel in this respect is at least excusable, in view of tho many conflicting decisions upon tho question.

The general principle underlying the doctrine of assumption of risk, as stated by Chief Justice Shaw in Farwell v. Boston & Worcester Ry., 4 Metc. (Mass.) 49, 38 Am. Dec. 339, has very generally been accepted:

“The general rule, resulting from considerations as well of justice as of policy, is, that he who engages in tho employment of another for the performance of specified duties and services, for compensation, takes upon himself the natural and ordinary risks and perils incident to the performance of such services, and in legal presumption, the compensation is adjusted accordingly.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. El Dorado Bowl, Inc.
409 P.2d 57 (Court of Appeals of Arizona, 1965)
Eastern Shore Public Service Co. v. Corbett
177 A.2d 701 (Court of Appeals of Maryland, 1962)
Swift & Co. v. Schuster
192 F.2d 615 (Tenth Circuit, 1952)
Amacker v. Skelly Oil Co.
132 F.2d 431 (Fifth Circuit, 1942)
United Production Corp. v. Chesser
95 F.2d 521 (Fifth Circuit, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
47 F.2d 673, 1931 U.S. App. LEXIS 3532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-pac-co-v-mccready-ca9-1931.