Southern Ohio Coal Co. v. Office of Surface Mining Reclamation & Enforcement

831 F. Supp. 1324, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20288, 37 ERC (BNA) 1703, 1993 U.S. Dist. LEXIS 17941, 1993 WL 323877
District Court, S.D. Ohio·Decided August 19, 1993·No. C2-93-751·Published·Cited by 2 cases

Opinion

PRELIMINARY INJUNCTION ORDER

BECKWITH, District Judge.

This matter is currently before the Court for consideration of the motion of the United States Environmental Protection Agency (hereinafter referred to as “USEPA”) to va= cate this Court’s August 4, 1993 Order temporarily restraining USEPA from acting in any manner with regard to the flooding at Plaintiffs Meigs Mine Number 31 (hereinafter referred to as “Meigs 31”) in Meigs County, Ohio. In this Order, the Court also addresses Plaintiffs motion for an order preliminarily enjoining USEPA and the Office of Surface Mining Reclamation and Enforcement, Department of the Interior (hereinafter referred to as “OSM”) from acting to cause a cessation or delay of the evacuation of water from Meigs 31, unless the Ohio agencies approved to enforce the applicable federal and state statutes fail to act as charged by these statutes.

BACKGROUND

Prior to July 11, 1993, Plaintiff ceased mining operations in its Raccoon Mine Number 3 (hereinafter referred to as “Raccoon 3”). Raccoon 3 is adjacent to Meigs 31 and is at a higher underground elevation than Meigs 31. In order to prevent naturally occurring water in Raccoon 3 from flooding into Meigs 31 through the opening that con *1327 nects the two.mines and in order to permit pumping of such naturally occurring water from Meigs 31 into Raccoon 3, Plaintiff constructed a bulkhead between the two mines. That bulkhead was designed to completely seal the. opening between the two mines, except to permit pumping water from Meigs 31 to Raccoon 3. Plaintiff caused the bulkhead to be designed to a strength of ten times the maximum pressure created by the water in Raccoon 3 at the opening between the two mines.

On July 11, 1993, Meigs 31 was inundated with an estimated one billion gallons of water from Raccoon 3. As of August 12, 1993, the cause of the inundation had not been conclusively established and may or may not have been a failure of the bulkhead. Because the water from Raccoon 3 occupied approximately thirty to fifty percent of Meigs 31, Plaintiff immediately began investigating alternatives for evacuating Meigs 31.

Plaintiffs alternatives for evacuating Meigs 31 were limited by three primary factors. The first factor complicating evacuation was that the normal method of evacuating water- from Meigs 31 was through the bulkhead into Raccoon 3. Because the structural integrity of the bulkhead could not be ascertained, Plaintiff could not rely upon the bulkhead or Raccoon 3 as a repository for water evacuation. The second complicating factor was the volume of water occupying Meigs 31. As of July 11, 1993, Plaintiff did not have a method for evacuating more than a few million gallons of water per day from Meigs 31. Accordingly, new methods were required for the evacuation. Finally, the chemical constitution of the water raised environmental concerns related to the evacuation.

The water occupying Meigs 31 contained higher levels of iron, manganese, copper, and zinc as well as a lower PH than normally occurs in the natural waterways in the area around Meigs 31. The level of those elements and the lower PH would, in normal conditions and pursuant to applicable state and federal laws and regulations, make treatment of the water necessary before it could be released into local streams. Because of the volume of the water, however, treatment of all of the water by Plaintiffs existing treatment facilities was not practicable.

Of course, treatment by the existing facilities was possible; however, due to the volume, such a process would have consumed a great deal of time. The mine naturally makes two to two and one-half million gallons of water per day. Therefore, the rate at which the mine naturally makes water would have prevented any genuine progress against the unanticipated volume of the flood. Essentially, the volume of water which plaintiff was equipped to treat was equal to the normally generated amount of mine seepage. Time became an enemy of Plaintiff, because Plaintiffs analysis indicated that unless the water could be evacuated within, at most, a period of two to four months, Meigs 31 could no longer be mined safely. The basis for that conclusion was that the water threatened the structural integrity of the mine. In time, the roof and wall supports within the mine would deteriorate to a point where safety within the mine could not be ensured. Furthermore, methane naturally develops within the mine, and Plaintiffs ability to evacuate methane from Meigs 31 was eliminated by the inundation on July 11, 1993. Until the water could be evacuated, Plaintiff would be unable to evacuate methane from Meigs 31 and it would build to levels that are incompatible with human occupation of the mine. After a certain amount of time, Plaintiff had good cause to believe that it would no longer be able to make the mine safe for workers who would enter the mine.

Plaintiff operates only two mines, Meigs 31 and the adjacent Meigs Mine Number 2 (hereinafter referred to as “Meigs 2”). The viability of Meigs 2 depends to a great extent upon the continued operation of Meigs 31. Accordingly, Plaintiffs entire operation in Meigs County, one of the largest in the United States, was threatened by the water occupying Meigs 31.

After investigating several alternatives with private consultants, plaintiff settled upon an evacuation method that included the drilling of bore holes at various locations and the evacuation of water, without normal treatment precautions, into streams that feed into the Ohio River. Plaintiff determined *1328 that the effects of such an evacuation would include a total or nearly total kill of aquatic life in the relevant streams, a reduction in PH and some increase in sedimentation of iron, zinc, copper, and manganese in these streams and perhaps the Ohio River.

Plaintiff concluded that the proposed evacuation plan would have no permanent effects on the environment, because the only affected life would renew itself within one to two years. Further, Plaintiff concluded, based upon the fact that the water in the relevant waterways prior to the proposed evacuation was not potable and upon Plaintiffs investigation into existing uses of the water in the streams, that human life would not be affected. Plaintiff recognized that some livestock might drink water from the relevant streams and offered to take any necessary precautions, at Plaintiffs expense, to prevent damage to such livestock. Further, Plaintiff offered to provide water to any other person who claimed to use water from the relevant streams for other purposes.

Plaintiff proposed numerous safeguards against permanent ecological damage. Plaintiff proposed to pump water from its treatment facility, after the evacuation of Meigs 31, at a higher than normal rate, in an attempt to force sediment downstream to and through the Ohio River. Plaintiff caused chemical analysis to be performed of the natural rate of sedimentation, comparison of the rate of natural sedimentation versus that resulting from the proposed evacuation, and the possible effects of such sedimentation. Plaintiff concluded that the long-term effects of the evacuation would be minimal.

Free access — add to your briefcase to read the full text and ask questions with AI

Southern Ohio Coal Co. v. Office of Surface Mining Reclamation & Enforcement, 831 F. Supp. 1324, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20288, 37 ERC (BNA) 1703, 1993 U.S. Dist. LEXIS 17941, 1993 WL 323877 (S.D. Ohio 1993).

831 F. Supp. 1324 (Southern Ohio Coal Co. v. Office of Surface Mining Reclamation & Enforcement) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related