Southern Management Corp. v. Kevin Willes Construction Co.

856 A.2d 626, 382 Md. 524, 2004 Md. LEXIS 498
CourtCourt of Appeals of Maryland
DecidedAugust 20, 2004
Docket89, Sept. Term, 2003
StatusPublished
Cited by7 cases

This text of 856 A.2d 626 (Southern Management Corp. v. Kevin Willes Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Management Corp. v. Kevin Willes Construction Co., 856 A.2d 626, 382 Md. 524, 2004 Md. LEXIS 498 (Md. 2004).

Opinion

*528 CATHELL, J.

This case raises numerous issues pertaining to the correct application of the modern law of mechanic’s liens in Maryland. The case arises out of a “Complaint to Establish and Enforce Mechanic’s Lien” (“Initial Complaint”), filed on April 20, 2000, by the Kevin Willes Construction Company (“Willes Construction”), respondent in the present appeal, as against Baltimore Condo 2-8, LLC (“Baltimore Condo”), one of two owners of separate real property interests in the building against which the lien was claimed, Southern Management Corporation (“SMC”), alleged property manager for Baltimore Condo in respect to the building, and James M. Jost and Company, Inc. (“Jost”), construction manager for the building renovation and under contract with SMC, collectively, the petitioners in the present proceeding. On May 15, 2001, more than a year after filing the Initial Complaint, a year during which service of process against the petitioners was not effectuated, and after receiving a “Notification of Contemplated Dismissal” from the Circuit Court for Baltimore City pursuant to Maryland Rule 2-507, 1 Willes Construction filed an “Amended Complaint to Establish and Enforce Mechanic’s Lien and Breach of Contract” (“Amended Complaint”). No additional defendants were named in the Amended Complaint. The Amended Com *529 plaint added a breach of contract count. On August 6, 2001, Baltimore Condo, Jost and SMC filed a motion to dismiss Willes Construction’s Amended Complaint. During a hearing before the circuit court on August 15, 2001, petitioners’ motion to dismiss was denied. Immediately following the denial, the circuit court proceeded with a show-cause hearing, requiring the petitioners to “show cause” as to why a lien should not be established against the building in question. On December 19, 2001, the circuit court entered a “Final Order Establishing Mechanic’s Lien and Directing Sale of Property” (“Final Order”).

Petitioners thereafter appealed the decision of the circuit court to the Court of Special Appeals of Maryland. On August 15, 2003, in an unreported opinion, the intermediate appellate court modified the order of the circuit court, changing it from a “final order” to an “interlocutory order.” While this holding favored petitioners, other determinations were made by the intermediate appellate court in favor of Willes Construction. Petitioners then filed a Petition for Writ of Certiorari with this Court and Willes Construction filed a cross-petition. On December 11, 2003, we granted both the petition and the cross-petition. Southern Management v. Willes Construction, 378 Md. 613, 837 A.2d 925 (2003). The parties presented the following questions for our review:

Petitioners ask:

“I. Did the Court of Special Appeals commit reversible error by holding that where work is performed throughout an eight (8) unit condominium building, including the common areas, and is not allocated among the units or the common elements, the notice provisions prefatory to filing a mechanic’s lien against the entire condominium regime (Real Property Article § 9-104(d)) are satisfied by providing notice to either the property manager of the condominium entity of record or to one but not all of the unit owners holding title to individual units within the condominium?
*530 “II. Did the Court of Special Appeals commit reversible error by sustaining the Circuit Court’s entry of a Final Order for Mechanic’s Lien without allocating the lien among the common elements and the condominium units of the condominium regime or in failing to identify which units were subject to having had work performed on them as required by the ‘Horizontal Property Act,’ Real Property Article Section 11-118 of the Maryland Code?
“III. Did the Court of Special Appeals commit reversible error in sustaining the Circuit Court’s denial of Petitioner’s Motion to Dismiss where there was substantial evidence that Respondent’s Complaint to Establish and Enforce a Mechanic’s Lien was filed more than 180 days from the day Respondent’s contract was terminated and all of its work benefitting the project ended? If no such error was committed by the Court of Special Appeals in determining the Circuit Court’s denial of this argument was not clearly erroneous, did the Court of Special Appeals commit reversible error by not requiring the issue of what was the time barred date for determining whether Respondent’s Complaint to establish a mechanic’s lien was filed within 180 days be remanded to the Circuit Court for a full evidential hearing?
“IV. Did the Court of Special Appeals commit reversible error in overruling Respondent’s Motion to Dismiss and in entering a Mechanic’s Lien when the lien was not clearly established within one (1) year from the filing of the initial complaint as required by Real Property Article 9-109? 2
*531 “V. Did the Court of Special Appeals commit reversible error by sustaining the Circuit Court’s entry of a Final Order of Mechanic’s Lien when for monetary consideration Respondent prepared, executed and delivered, in writing, a Release of Liens for all work and services performed and materials furnished, where Respondent specifically waived any right to make the claim it has asserted in the Circuit Court and where the Respondent waived its right to establish the mechanic’s lien?”
Willes Construction asks:
“Did the Court of Special Appeals commit reversible error in modifying the Final Order of Mechanic’s Lien to [an] Interlocutory Order and remanding the case to the Trial Court for further proceedings consistent with that opinion?” [Alteration added.] 3

We hold that a condominium regime lawfully existed at the building that is the subject of this case at the relevant times in question and, as such, notice was required to be given to all condominium unit owners under § 9-104 of the Real Property Article and all such owners had to be parties to the case before a mechanic’s lien could be established as against the entire building and that the circuit court further erred in entering an order establishing a mechanic’s lien where the lien was not allocated among the individual unit owners according to their percentage interests in the common elements as is required under § 11-118 of the Real Property Article. We need not decide the remaining issues.

*532 I. Facts

A. Relevant pre-claim facts

In August, 1999, Jost, construction manager for SMC, entered into an agreement with Willes Construction whereby Willes Construction was to provide demolition and abatement work for renovation of a building located at 118 N. Howard Street in Baltimore City (“Lexington Towers”). The building consisted of eight condominium units with general and limited common areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Walker and Walker
248 A.3d 981 (Court of Appeals of Maryland, 2021)
Rigby v. Allstate Indemnity Co.
123 A.3d 592 (Court of Special Appeals of Maryland, 2015)
Rounds v. Maryland National Capital Park & Planning Commission
75 A.3d 987 (Court of Special Appeals of Maryland, 2013)
Ace American Insurance v. Williams
15 A.3d 761 (Court of Appeals of Maryland, 2011)
Williams v. Work
995 A.2d 744 (Court of Special Appeals of Maryland, 2010)
Elderkin v. Carroll
941 A.2d 1127 (Court of Appeals of Maryland, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
856 A.2d 626, 382 Md. 524, 2004 Md. LEXIS 498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-management-corp-v-kevin-willes-construction-co-md-2004.