Southern Industrial Contractors LLC v. O'Brien and Gere Inc of North America

District Court, D. South Carolina·Decided April 1, 2021·No. 2:19-cv-01691·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF SOUTH CAROLINA CHARLESTON DIVISION

Southern Industrial Contractors, LLC, ) Civil Action No. 2:19-cv-1691-RMG ) ) Plaintiff, ) ) ORDER AND OPINION v. ) ) O’Brien and Gere of North America ) and Western Surety Company, ) ) ) Defendants. ) ___________________________________ ) Before the Court is Defendants O’Brien and Gere of North American and Western Surety Company’s (collectively “Defendants”) motion to strike the expert report and exclude the expert testimony of Dr. Ashraf Elsayed. (Dkt. No. 74). For the reasons set forth below, the Court denies Defendants’ motion. I. Background This action arises out of the expansion and renovation of the J.W Aluminum, Inc. aluminum processing facility located in Goose Creek, South Carolina (the “Project”). Defendant O’Brien Gere of North America (“OBG”) served as the engineering, procurement, and construction contractor for the Project. In August 2018, OBG allegedly hired Plaintiff Southern Industrial Contractors, LLC (“SIC”) as its subcontractor to perform concrete foundation work on the Project. (Dkt. No. 74-1 at 2). According to Defendants, in September 2018, SIC “contracted with OBG to perform additional scopes of work, including the excavation and shoring required to construct the deep foundation for a new Rolling Mill building.” (Id.) In performing this work, SIC allegedly “engaged Dr. Ashraf Elsayed of Geotechnology, Inc., a geotechnical engineer, to provide a design for a shoring system that would allow SIC to brace the surrounding soil as it excavated the foundation pit.” (Id.) Dr. Elsayed provided SIC with a report (the “Report”)—dated October 18, 2018—which, according to Defendants, “provided geotechnical information and subsurface conditions and a design for the bracing system, including necessary materials and a construction sequence.” (Id. at 2-3). Defendants allege OBG “opted not to move forward with SIC and Dr. Elsayed’s proposed design because OBG determined that the originally-conceived exterior bracing

system would have less interference with the design and construction of the concrete that would be poured in the foundation pit to form the foundations.” (Id. at 3). Defendants thus “allege[] in this action that SIC’s provision of Dr. Elsayed’s design behind schedule and with interior rather than exterior bracing contributed to Project delays that caused OBG to incur unanticipated costs.” (Id. at 2-3). On June 12, 2019, Plaintiff initiated this lawsuit against Defendants for non-payment of work done on the Project. (Dkt. Nos. 1 & 10). Defendants, in pertinent part, filed a counterclaim seeking damages for alleged SIC-caused delays and inefficiencies. (Dkt. No. 50 at 24-25). Under the Second Amended Scheduling Order, Plaintiff’s expert disclosures were due on

or by October 10, 2020 and Defendants’ expert disclosures were due on or by October 28, 2020. (Dkt. No. 43). On October 9, 2020, Plaintiff disclosed its respective expert. On October 28, 2020, Defendants disclosed their respective experts. On November 27, 2020, Plaintiff disclosed Dr. Elsayed as an additional expert and attached a copy of the Report. (Dkt. No. 74-3). On January 19, 2021, Defendants moved to exclude the testimony of Dr. Elsayed. (Dkt. No. 74). Defendants argue that Dr. Elsayed’s expert disclosure does not comply with Fed. R. Civ. P. 26(a)(2)(B) or is, in the alternative, untimely. Plaintiff opposes Defendants’ motion. (Dkt. No. 81). Defendants have filed a reply. (Dkt. No. 87). Defendants’ motion is fully briefed and ripe for disposition. II. Legal Standard Rule 37 of the Federal Rules of Civil Procedure provides that “[i]f a party fails to provide information or identify a witness as required by Rule 26(a) or (e), the party is not allowed to use that information or witness to supply evidence on a motion, at a hearing, or at a trial, unless the failure was substantially justified or is harmless.” Fed. R. Civ. P. 37(c)(1). Local Civil Rule

16.02(D)(2) provides that witnesses identified in the last twenty-eight days of the discovery period are presumed to be untimely identified, absent a showing of good cause. “[T]he basic purpose of Rule 37(c)(1) [is] preventing surprise and prejudice to the opposing party.” S. States Rack & Fixture, Inc. v. Sherwin-Williams Co., 318 F.3d 592, 596 (4th Cir. 2003). Thus, the district court has broad discretion to determine whether a nondisclosure of evidence is substantially justified or harmless. Id. at 597. “[I]n exercising its broad discretion to determine whether a nondisclosure of evidence is substantially justified or harmless for purposes of a Rule 37(c)(1) exclusion analysis, a district court should be guided by the following factors: (1) the surprise to the party against whom the evidence would be offered; (2) the ability of that party to cure the surprise; (3) the extent to which allowing the evidence would disrupt the trial; (4) the

importance of the evidence; and (5) the nondisclosing party’s explanation for its failure to disclose the evidence.” Id. III. Discussion Defendants first move to strike Dr. Elsayed and his testimony on the basis that Plaintiff’s respective disclosure does not conform to the requirements of Rule 26(a)(2)(B). Rule 26(a)(2) provides for two different types of disclosure of expert opinions. Rule 26(a)(2)(B) requires experts who are “retained or specially employed to provide expert testimony in the case or ... whose duties as the party’s employee regularly involve giving expert testimony” to disclose an extensive expert report. Rule 26(a)(2)(C) requires experts who are not so retained or employed to provide a more summary disclosure of the witness’s expected testimony. Rule 26(a)(2)(C) was added to Rule 26 in 2010. The committee notes explain: Rule 26(a)(2)(C) is added to mandate summary disclosures of the opinions to be offered by expert witnesses who are not required to provide reports under Rule 26(a)(2)(B) and of the facts supporting those opinions. This disclosure is considerably less extensive than the report required by Rule 26(a)(2)(B). Courts must take care against requiring undue detail, keeping in mind that these witnesses have not been specially retained and may not be as responsive to counsel as those who have.

This amendment resolves a tension that has sometimes prompted courts to require reports under Rule 26(a)(2)(B) even from witnesses exempted from the report requirement. An (a)(2)(B) report is required only from an expert described in (a)(2)(B).

A witness who is not required to provide a report under Rule 26(a)(2)(B) may both testify as a fact witness and also provide expert testimony under Evidence Rule 702, 703, or 705.

Free access — add to your briefcase to read the full text and ask questions with AI

Southern Industrial Contractors LLC v. O'Brien and Gere Inc of North America, (D.S.C. 2021).

Southern Industrial Contractors LLC v. O'Brien and Gere Inc of North America (Southern Industrial Contractors LLC v. O'Brien and Gere Inc of North America) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related