Southern Indiana Gas & Electric Co. v. Indiana Statewide Rural Electric Cooperative, Inc.

232 N.E.2d 899, 142 Ind. App. 32, 1968 Ind. App. LEXIS 535
CourtIndiana Court of Appeals
DecidedJanuary 9, 1968
DocketNo. 20,372
StatusPublished
Cited by5 cases

This text of 232 N.E.2d 899 (Southern Indiana Gas & Electric Co. v. Indiana Statewide Rural Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Indiana Gas & Electric Co. v. Indiana Statewide Rural Electric Cooperative, Inc., 232 N.E.2d 899, 142 Ind. App. 32, 1968 Ind. App. LEXIS 535 (Ind. Ct. App. 1968).

Opinions

Bierly, J.

— This is an action in equity, whereby appellant, plaintiff below, sought to' enjoin appellee:

“. . . from either constructing or operating an electric utility generating plant of transmission facilities'; from producing, furnishing, transmitting or selling electricity in any part of the area or to any of the customers, served by the plaintiff; from using or crossing county roads or other county property for the installation of its facilities; and from otherwise engaging as a public utility in the production, transmission, sale or furnishing of electric power, all unless and until authorized to do so by proper order of the Public Service Commission of Indiana, and in the case of using county property, unless and until properly authorized so to do by the respective counties.”1

It appears from the record that appellee proposed to construct an electric utility generating plant and transmission facilities in order to render service to the Southern Indiana Rural Electric Cooperative, Inc., (hereinafter referred to as Southern REMC) and to the Dubois Rural Electric Coopera[34]*34tive, Inc., (hereinafter referred to as Dubois REMC), both of which are presently receiving service rendered by appellant.

The trial court found against the appellant on its complaint and entered judgment accordingly.

On appeal, appellant assigns as error the trial court’s action in overruling its motion for a new trial, which motion specified that the trial court’s decision was contrary to law.

At this point it would prove helpful for a better understanding of the issues, if we briefly outline the facts surrounding this action, as well as the nature of the parties’ operations.

Appellant was initially organized in 1912 under the name “Public Utilities Company,” and in 1921 its name was changed to its present form. As of mid-1964, it asserts that its total investment in electric utility plants was $78,072,891.00. As of the time of the filing of the complaint, its cost of operation of electric facilities then being used to supply utility service to Southern REMC and Dubois REMC was $270,280.52. This property consists of lines, meters, transformers, substations and miscellaneous other property and equipment.

In addition to the above two REMCs, appellant renders service to residential, commercial, industrial, municipal and wholesale municipal customers in the counties of Posey, Vanderburgh, Gibson, Warrick, Spencer, Pike, Dubois and Perry. As of May 31, 1964, appellant was serving approximatey 74,377 customers directly, and 17,500 customers indirectly. The indirect customers consist of those served by the wholesale municipal and REMC customers. Appellant has served Southern REMC continuously since 1941, and Dubois REMC since 1954. The revenue received by appellant from the above two REMCs for electric utility service during 1963 amounted to $261,360.00. The revenue per year had grown in the past and the parties agreed that further growth at an increasing rate would be experienced in the future.

The Southern REMC was incorporated in 1939 under the REMC Act, (Burns’ Anno. Stat. §§ 55-4401 to 55-4426, 1951 [35]*35Replacement and 1967 Cum. Supp.), to distribute electricity in certain rural areas in Spencer and Posey Counties and areas to the east thereof. It does not generate its own electricity or operate the large, high voltage, transmission lines. Instead, it purchases all of its electricity from appellant and then distributes the current to the ultimate consumer.

The Dubois REMC was also incorporated in 1939, and it, like the Southern REMC, does not generate or transmit its own electricity, but purchases some from the appellant as well as some from other utilities, and distributes it to its customers.

The appellee has admitted, in its answer to appellant’s complaint, that it:

“[Pjroposes to, and will unless prevented by this court, construct an electric generating plant and transmission facilities and engage as a public utility in rendering to Southern REMC and Dubois REMC, as well as others, the electric utility services which is presently being, and for many years has been, rendered by the plaintiff.”

The possibility of generation of electric energy by the REMCs had been under consideration and discussion for a number of years. The motivating factor was the REMCs’ desire to obtain electricity at the lowest possible rate, and under the present set-up the public service commission approved these rates between appellant and appellee.

As a result, the appellee, along with several member REMCs, organized the Hoosier Cooperative Energy, Inc., as a not-for-profit corporation in 1949, and as a vehicle for generating electrical energy.

Several studies were made concerning the feasibility of a generating program. None of these studies advanced beyond the planning stage until June of 1961, when the REA approved a loan to Hoosier Cooperative Energy, Inc., for a generation and transmission project.

Hoosier Cooperative Energy, Inc., planned to receive Public Service Commission authorization of this proposed genera[36]*36tion and transmission, and then construct a generating plant near Petersburg, Indiana, for the transmission of electricity to some sixteen [16] local REMCs.

On December 18, 1961, Hoosier Cooperative Energy, Inc., filed with the Public Service Commission its petition for a certificate of convenience and necessity to construct, maintain and operate a generating station and transmission system.

Several utilities, including appellant, intervened and opposed the project as being unnecessary, uneconomical, and not in the public interest. Thereafter, arrangements were made to transfer the REA loan from Hoosier Cooperative Energy, Inc., to the appellee. On April 25, 1962, Hoosier Cooperative Energy, Inc., dismissed its petition before the commission.

On May 14, 1962, the traditional ground breaking ceremony was held near Petersburg, Indiana. Appellant then filed this action on June 1, 1962.

For purposes of this appeal there appears three issues for our determination. The first would be whether or not the appellee has the authority to proceed with its generation and transmission plans, and if this is found to be in the affirmative, where does it derive this authority, from the statute or from the Public Service Commission? The second issue concerns itself with non-user. That is, even assuming appellee had the authority to proceed with its plan, has it lost this authority by reason of lapse through non-user ? The third and final issue is the question of whether appellant is a proper party to bring an action asserting such loss of revenues and capital invested to extend services to REMCs.

We are of the opinion that a literal interpretation of the statute creating the REMCs leaves little room for doubt as to whether the power to generate is present.

Under § 55-4411, it is provided that:

“A corporation created under the provisions of this act shall have power to do any and all acts or things necessary [37]*37or convenient for carrying out the purpose for which it was formed, including, but not limited to:
“(d) To acquire, own, operate, maintain and improve a system or systems.”

Under § 55-4403, the word “system” is defined as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
232 N.E.2d 899, 142 Ind. App. 32, 1968 Ind. App. LEXIS 535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-indiana-gas-electric-co-v-indiana-statewide-rural-electric-indctapp-1968.