Southern Constructors Group, Inc. v. Dynalectric Co.

CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 22, 1993
Docket93-3252
StatusPublished

This text of Southern Constructors Group, Inc. v. Dynalectric Co. (Southern Constructors Group, Inc. v. Dynalectric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Constructors Group, Inc. v. Dynalectric Co., (5th Cir. 1993).

Opinion

United States Court of Appeals,

Fifth Circuit.

No. 93-3252

Summary Calendar.

SOUTHERN CONSTRUCTORS GROUP, INC., Plaintiff-Appellant,

v.

DYNALECTRIC COMPANY, Defendant-Third Party Plaintiff-Appellee,

Allen R. BOUDREAUX, Third Party Defendant-Appellant.

Sept. 27, 1993.

Appeal from the United States District Court for the Eastern District of Louisiana.

Before: JOLLY, WIENER, and EMILIO M. GARZA, Circuit Judges.

WIENER, Circuit Judge:

This case illustrates the preclusive consequences flowing from failure to provide proper notice

of a possible theory of recovery. Plaintiff-Appellant Southern Constructors Group, Inc. ("Southern")

sued Defendant-Appellee Dynalectric Company under various claims that were all predicated on the

existence of a contract. The case was eventually submitted to arbitration. After receiving notice that

the arbitration panel had failed to find a contract, Southern attempted to switch to a quasi-contract

theory of recovery grounded in quantum meruit. The district court held that Southern had waived

these claims by failing to include them within any of its original or amended complaints or even in the

pretrial order. Southern appeals this conclusion. Southern also appeals the district court's refusal to

grant it leave to amend its complaint to add the quasi-contract claim. Concluding that the district

court properly found waiver and did not abuse its discretion in refusing to allow amendment of the

complaint to include the waived claims, we affirm.

I

FACTS AND PROCEEDINGS

This case arises out of events following the bankruptcy of MMR Holding Company, Inc. ("MMR"), a large national electrical and mechanical contractor. MMR's bankruptcy led to default

on all of its bonded work, which in turn placed responsibility for completion of this work on MMR's

surety, Aetna Casualty and Surety Company ("Aetna"). Allen R. Boudreaux, a former vice-president

of MMR and owner and president of Southern, contacted Dynalectric about acquiring the contracts

for completing all of MMR's electrical work from Aetna. What transpired next is the subject matter

of the present suit. Boudreaux claims that his expertise and connections led to the awarding of

approximately $120 million of completion contracts to Dynalectric, and that Southern and Dynalectric

entered into an agreement to split the profits of these contracts 807 to Dynalectric and 207 to

Southern. Disputing that version of the facts, Dynalectric claims that it broke off negotiations with

Southern before a contract was formed because it had learned that several of Boudreaux's

representations were inaccurate and that Southern was merely a shell company without any track

record or employees.

Southern brought suit against Dynalectric in August of 1990. In the second amended

complaint, the operat ive one for this litigation, Southern alleged that Dynalectric breached its

contractual and fiduciary duties, and engaged in unfair trade practices and fraud. Southern's claims

included the standard prayer that it be awarded "any other just and equitable relief this Court may

deem appropriate." All of the claims were apparently predicated on proof of the existence of a

contract between Southern and Dynalectric.1 When extensive discovery was complete it became clear

that the existence of the contract turned on the enforceability of a draft agreement containing an

arbitration provision. Thus Southern faced the prospect of submitting to two separate

proceedings—a jury trial to determine the existence of a contract; and then, only if a contract were

found, an arbitration proceeding to determine whether damages were due under that contract.

Instead of incurring the costs and delays of both a trial and an arbitration proceeding,

1 Although Southern contends that its complaint implicitly includes additional claims of quasi-contract, it has not disputed Dynalectric's assertion that the breach of contract, breach of fiduciary duty, unfair trade practices, and fraud claims presuppose the existence of a contract. Moreover, Southern's actions in conditioning the arbitration of those claims on whether a contract existed indicates that Southern believed those claims were valid only if there were a contract. Southern and Dynalectric agreed to submit all issues in this dispute to arbitration.2 The agreement

to arbitrate provided, inter alia, that an earlier pretrial order confected by Southern and Dynalectric

would control the arbitration "to the extent practicable," and that the first stage of the arbitration

would consider only whether a contract existed. If no contract were found the arbitration would be

over and either party could seek to confirm or appeal the decision of the arbitration panel. Only if

a contract were found to exist would the arbitration proceed to the second stage, determining whether

and to whom damages were owed under the various contractual claims.

The arbitration panel conducted four days of formal hearings at which the parties presented

numerous witnesses, depositions, and exhibits. In its initial decision the majority of the arbitration

panel found that no contract existed between Southern and Dynalectric. Only after it learned of this

decision did Southern raise the issue of its entitlement to recover under a quasi-contract theory.

Southern raised that issue by filing a Motion to Reconsider with the arbitration panel. The majority

of the panel concluded that this motion raised issues beyond the scope of the panel's authority and

accordingly refused to reconsider the decision.3 Dynalectric filed a Motion to Confirm the Arbitration

Award, which was granted by the district court.

Southern filed a timely motion with the district court to reconsider its decision confirming the

arbitration award. In its motion Southern contended that the district court should hear the

quasi-contract issues because the arbitration panel refused to resolve those claims. The district court

reviewed the amended co mplaint and pretrial order, but concluded that Southern had waived the

quasi-contract claims by failing to raise them in a timely manner. The district court subsequently

entered judgment for Dynalectric confirming the arbitration award.

After entry of judgement Southern filed a timely motion pursuant to FED.R.CIV.P. 59(e) to

vacate the judgment and to grant leave to Southern t o file a third amended complaint under

2 Dynalectric filed a counterclaim against Southern and a third party complaint against Southern's owner, Boudreaux. Dynalectric has not appealed the judgment by the district court dismissing those complaints with prejudice. 3 Southern does not directly challenge on appeal the arbitrators' conclusion that the quantum meruit and quasi-contract claims were beyond the scope of the agreement to arbitrate. FED.R.CIV.P. 15. The third amended complaint would have added Boudreaux as a party plaintiff and

would have included quasi-contractual claims. The district court denied this motion concluding that:

1) it was correct in finding that Southern had waived the quasi-contract claims by failing to raise them

until after it lost its case at arbitration; and 2) granting the motion would be unfairly prejudicial to

Dynalectric in subjecting it to renewed litigation when Dynalectric had a reasonable and justifiable

expectation that the arbitration had conclusively resolved its dispute with Southern. Southern timely

appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shearson/American Express Inc. v. McMahon
482 U.S. 220 (Supreme Court, 1987)
Dotschay v. National Mutual Insurance Company
246 F.2d 221 (Fifth Circuit, 1957)
Smith v. Hudson
519 So. 2d 783 (Louisiana Court of Appeal, 1987)
Fullerton v. Scarecrow Club, Inc.
440 So. 2d 945 (Louisiana Court of Appeal, 1983)
Little v. Liquid Air Corp.
952 F.2d 841 (Fifth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Southern Constructors Group, Inc. v. Dynalectric Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-constructors-group-inc-v-dynalectric-co-ca5-1993.