South Yuba River Citizens League v. National Marine Fisheries Service

804 F. Supp. 2d 1045, 2011 U.S. Dist. LEXIS 81594, 2011 WL 3163296
CourtDistrict Court, E.D. California
DecidedJuly 26, 2011
DocketCIV. S-06-2845 LKK/JFM
StatusPublished
Cited by8 cases

This text of 804 F. Supp. 2d 1045 (South Yuba River Citizens League v. National Marine Fisheries Service) is published on Counsel Stack Legal Research, covering District Court, E.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Yuba River Citizens League v. National Marine Fisheries Service, 804 F. Supp. 2d 1045, 2011 U.S. Dist. LEXIS 81594, 2011 WL 3163296 (E.D. Cal. 2011).

Opinion

ORDER

LAWRENCE K. KARLTON, Senior District Judge.

This order addresses whether any interim measures are appropriate during the remand period where the federal defendants were found to have violated the Endangered Species Act (“ESA”). In an order issued on July 8, 2010, 723 F.Supp.2d *1049 1247 (E.D.Cal.2010), (the “July Order”) this court held that the National Marine Fishery Service acted arbitrarily and capriciously in issuing a 2007 Biological Opinion (“BiOp”) that concluded that operations associated with the Englebright and Daguerre dams on the Yuba River posed no jeopardy to the survival of spring-run Chinook salmon (“chinook”), Central Valley Steelhead (“steelhead”), and green sturgeon, all of which are on the threatened species list. In an order issued on April 29, 2011, 2011 WL 1636235 this court remanded the matter back to the National Marine Fishery Service (“NMFS”) to prepare a new BiOp consistent with the court’s July Order. The April order requires the NMFS to complete the BiOp by December 12, 2011. See ECF No. 378.

Plaintiffs seek injunctive relief in the form of nine interim measures to protect the species until a new BiOp is prepared by the agency. Defendants argue that the only appropriate remedy is to remand the matter to the NMFS. For the reasons stated below, the plaintiffs’ motion is GRANTED in part and DENIED in part.

I. Procedural Background

This court’s July Order addressed claims by plaintiff that the National Marine Fishery Service acted arbitrarily and capriciously in adopting the BiOp, in violation of Section 7 of the Endangered Species Act. This court held that the BiOp was arbitrary and capricious because it concluded that the operation of the dams would pose “no jeopardy” to the threatened fish, when that conclusion was not supported by the record. Upon a finding that a project poses no jeopardy to the survival or recovery of a threatened species, an agency may operate the project pursuant to an Incidental Take Statement (“ITS”). The ITS specifies (1) what incidental “takings” of individual species will result from the project, (2) the mitigation measures that are necessary to minimize the takings, and (3) the terms and conditions that must be complied with to implement those mitigation measures. The court held that the NMFS had not sufficiently supported its no-jeopardy conclusion, “but not that a jeopardy conclusion was inescapable.” July 8 Order 16:18. In particular, the court found the following defects in the BiOp:

(1) The BiOp did not conclude that the populations of the three listed fish are stable, yet it concluded that the project’s unmitigated effects would not jeopardize the species. Any conclusion about the effects of the project must take the current status of the population into account. Without a finding that the three listed fish populations are stable, the BiOp cannot rationally conclude that the unmitigated effects of the project would not jeopardize the species. July Order, 723 F.Supp.2d at 1258.

(2) The BiOp concludes that the project will continue to impose stressors on listed species without explaining why these stressors will not jeopardize the species. Those stressors are: migration barriers caused by Daguerre Point Dam and Englebright Dam; irregular flow regimes and temperature, leading to pre-spawning mortality and reduced reproductive success; interference with gravel accumulation and compromised spawning habitat below Englebright Dam; and entrainment and impingement. 1 Because the BiOp failed “to discuss (through some method) the magnitude of the stressors’ impact, the populations’ ability to tolerate this impact, *1050 and the reason why any decline will not reduce the overall likelihood of survival or recovery,” it could not properly determine that the stressors will not cause a decline in reproduction, population, distribution, or diversity — the factors necessary for the species to survive. July Order, 723 F.Supp.2d at 1267.

(3) The BiOp omits any analysis of the possibility of a period of increased entrainment due to the cumulative effect of the challenged project and the Wheatland project. Additionally, the BiOp did not support its conclusion that the Corps’ operations, when considered in the context of the Wheatland project, will not jeopardize the green sturgeon population.

(4) The BiOp does not discuss other stressors that might jeopardize the listed species. Those stressors are: hatcheries, the San Francisco Bay Delta, the species’ overall depressed conditions, global warming, and poaching. Even if the agency determined these factors to be unimportant, it must provide a reasoned explanation for that conclusion.

(5) With respect to critical habitat for the listed species, the BiOp does not support its conclusion that the restoration measures described in the BiOp will provide benefits whose magnitude outweighs the project’s impacts.

The court ordered additional briefing on the issue of whether the Corps violated the terms and conditions of the ITS, and whether the plaintiffs would be entitled to preliminary relief if such a violation had occurred. On November 16, 2010, 2010 WL 4746187 after supplemental briefing on the issue the court dismissed as prudentially moot plaintiffs’ claim that the Corps had violated the ITS, and denied plaintiffs’ motions for a preliminary injunction. On November 23, 2010, this court entered an order approving a stipulation by the parties. In that stipulation, the parties agreed, inter alia, that the BiOp and ITS should not be vacated during remand. Thus, the project is currently operating pursuant to the 2007 BiOp and the ITS.

In April 2011, the court remanded the matter back to the NMFS to complete a new BiOp consistent with the July Order by December 12, 2011.

II. Analysis

Plaintiffs propose an injunction requiring the defendants to comply with nine measures, which plaintiffs argue are necessary to prevent the project from jeopardizing the survival or recovery of the listed species while a new BiOp is prepared. Plaintiffs’ proposed interim measures are:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
804 F. Supp. 2d 1045, 2011 U.S. Dist. LEXIS 81594, 2011 WL 3163296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-yuba-river-citizens-league-v-national-marine-fisheries-service-caed-2011.