South Point Retail Partners, LLC v. North American Properties Atlanta, Ltd.

696 S.E.2d 136, 304 Ga. App. 419, 2010 Fulton County D. Rep. 1913, 2010 Ga. App. LEXIS 542
CourtCourt of Appeals of Georgia
DecidedJune 11, 2010
DocketA10A1350
StatusPublished
Cited by20 cases

This text of 696 S.E.2d 136 (South Point Retail Partners, LLC v. North American Properties Atlanta, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Point Retail Partners, LLC v. North American Properties Atlanta, Ltd., 696 S.E.2d 136, 304 Ga. App. 419, 2010 Fulton County D. Rep. 1913, 2010 Ga. App. LEXIS 542 (Ga. Ct. App. 2010).

Opinion

Ellington, Judge.

This dispute arises from an agreement between South Point Retail Partners, LLC, and North American Properties Atlanta, Ltd. (“NAP”). NAP filed a claim with the American Arbitration Association, alleging that South Point breached the agreement by failing to make certain payments when due. South Point then filed this action in the Superior Court of Fulton County, seeking a judgment declaring that the arbitration clause in the parties’ agreement does not encompass NAP’s claim and seeking to enjoin the arbitration pending adjudication of South Point’s declaratory judgment action. The *420 trial court denied South Point’s motion for an injunction and granted NAP’s motion to dismiss South Point’s declaratory judgment action for failure to state a claim upon which relief can be granted. South Point appeals, contending that the trial court misconstrued the arbitration clause in the parties’ agreement and, consequently, erred in granting NAP’s motion to dismiss. For the reasons explained below, we reverse.

“We review de novo the trial court’s grant of a motion to dismiss. A motion to dismiss may be granted only where a plaintiff would not be entitled to relief under any set of facts that could be proven in support of the plaintiffs claim.” (Citations and punctuation omitted.) Johnson v. Bd. of Commrs. &c., 302 Ga. App. 266 (690 SE2d 912) (2010).

For the purpose of evaluating NAP’s motion to dismiss, we assume that South Point can prove the following facts as averred in its complaint. See Johnson v. Bd. of Commrs. &c., 302 Ga. App. at 266. In 2005, investors organized South Point to develop a shopping center in McDonough. South Point and NAP entered a “pre-development” agreement under which NAP provided certain services to South Point, including applying for rezoning and negotiating with certain anchor retailers.

In September 2006, the parties entered into a new agreement under which South Point retained NAP to provide consulting and marketing services to South Point in connection with the shopping center. In Paragraph 1, the parties specified the hourly rate for NAP’s consulting services and the commission that South Point would pay NAP for procuring a buyer or lessee for any outparcel.

In the consulting and marketing agreement, South Point and NAP also expressly terminated the pre-development agreement. In Paragraph 3, the parties agreed that South Point would “reimburse [NAP] the NAP Pre-Development Costs as defined in the Pre-Development Agreement.” NAP acknowledged that it had already received “$442,240.00 or thirty percent of the NAP Pre-Development costs.” South Point agreed to pay NAP “$1,031,089.00, or the remaining seventy percent of the NAP Pre-Development Costs” in installments, “if, as and when” South Point received installment payments from the anchor retailers.

Paragraph 5 (a) of the consulting and marketing agreement set out the conditions and process for early termination of the agreement. Paragraph 5 (b) provided as follows:

In the event of early termination of this Agreement as provided for herein, NAP shall be entitled to a pro-rata portion of Sales and Leasing Fees for space leased or committed to ... as of such termination. In the event the *421 parties involved are unable to agree on the total compensation owed to NAI] the matter shall be submitted to binding arbitration in accordance with the rules of the American Arbitration Association[.] ... If this Agreement is terminated by Owner prior to the repayment outlined in Paragraph 3 above (except for cause) then Owner shall deliver payment of all funds due to NAP under Paragraph 3 notwithstanding the early termination to NAR within 10 days of delivery of the notice of early termination.

In the claim NAP filed with the American Arbitration Association, NAP alleged that South Point breached Paragraph 3 of the consulting and marketing agreement by paying only $106,441.35 of the total it owed NAP for its pre-development costs and failing to pay the remaining $924,647.65 due. The trial court determined that the parties had agreed “to arbitrate all disputes between them as to the ‘total compensation’ owed to [NAP], and that the claims raised in [NAP’s] Demand for Arbitration clearly fall within that arbitration clause.” Based on that construction of the agreement, the trial court denied South Point’s motion for an interlocutory injunction and dismissed South Point’s complaint with prejudice for failure to state a claim upon which relief can be granted.

1. South Point contends that the trial court erred in determining as a matter of law that the arbitration clause applies to NAP’s claim and, therefore, erred in granting NAP’s motion to dismiss.

Under Georgia law,

arbitration is a matter of contract[,] and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit. Therefore, the question of arbitra-bility, i.e., whether an agreement creates a duty for the parties to arbitrate the particular grievance, is undeniably an issue for judicial determination.

(Citation and punctuation omitted.) Yates v. CACV of Colorado, 303 Ga. App. 425, 430 (1) (693 SE2d 629) (2010). The construction of an arbitration clause in a contract is subject to the ordinary rules of contract construction. Tillman Park v. Dabbs-Williams Gen. Contractors, 298 Ga. App. 27, 29 (679 SE2d 67) (2009). “The cardinal rule of contract construction is to ascertain the intention of the parties. Contract construction is a three-step process. Initially, the construction of the contract is a question of law for the court.” (Punctuation and footnote omitted.) Id. First, the court determines whether the contract is ambiguous. Id.; Azzouz v. Prime Pediatrics, 296 Ga. App. 602, 604 (1) (a) (675 SE2d 314) (2009). A contract is *422 ambiguous when the language used may be fairly understood in more ways than one. Azzouz v. Prime Pediatrics, 296 Ga. App. at 604 (1) (a); Western Pacific Mut. Ins. Co. v. Davies, 267 Ga. App. 675, 680 (1) (601 SE2d 363) (2004). If the language of a contract is plain, unambiguous, and capable of only one reasonable interpretation, no construction is required or even permissible, and the trial court enforces the contract according to its literal meaning. Tillman Park v. Dabbs-Williams Gen. Contractors, 298 Ga. App. at 29; Quality Foods v. Smithberg, 288 Ga. App. 47, 51 (1) (653 SE2d 486) (2007).

Second, if the trial court determines that the contract is ambiguous,

the trial court then applies the applicable rules of contract construction in OCGA § 13-2-2. ... In construing a contract, courts must give words their usual and common meaning. And the entirety of the agreement should be looked to in arriving at the construction of any part. The contract is to be considered as a whole, and each provision is to be given effect and interpreted so as to harmonize with the others.

(Punctuation and footnote omitted.) Quality Foods v. Smithberg, 288 Ga. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles R. Brooks v. Vinci C. Brooks
Court of Appeals of Georgia, 2023
EMORY HEALTHCARE, INC. v. ILLE VAN ENGELEN
Court of Appeals of Georgia, 2022
James Darren Summerville v. Innovative Images, LLC
826 S.E.2d 391 (Court of Appeals of Georgia, 2019)
Kelly Capital Investments, LLC v. Hamilton State Bank
779 S.E.2d 757 (Court of Appeals of Georgia, 2015)
Aaa Restoration Company, Inc. v. Peek
775 S.E.2d 627 (Court of Appeals of Georgia, 2015)
Sandra S. Marshall v. Sheila K. Deverger
Court of Appeals of Georgia, 2014
Marshall v. McIntosh County
759 S.E.2d 269 (Court of Appeals of Georgia, 2014)
Bing Chi Lam v. Allstate Indemnity Company
Court of Appeals of Georgia, 2014
Lam v. Allstate Indemnity Co.
755 S.E.2d 544 (Court of Appeals of Georgia, 2014)
Dennis v. City of Atlanta
751 S.E.2d 469 (Court of Appeals of Georgia, 2013)
Dudney v. State
745 S.E.2d 713 (Court of Appeals of Georgia, 2013)
Scsj Enterprises, Inc. v. Hansen & Hansen
Court of Appeals of Georgia, 2012
Center for a Sustainable Coast, Inc. v. Ga Dnr
Court of Appeals of Georgia, 2012
SCSJ Enterprises, Inc. v. Hansen & Hansen Enterprises, Inc.
734 S.E.2d 214 (Court of Appeals of Georgia, 2012)
Scott v. Scott
716 S.E.2d 809 (Court of Appeals of Georgia, 2011)
City of Atlanta v. BENATOR
714 S.E.2d 109 (Court of Appeals of Georgia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
696 S.E.2d 136, 304 Ga. App. 419, 2010 Fulton County D. Rep. 1913, 2010 Ga. App. LEXIS 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-point-retail-partners-llc-v-north-american-properties-atlanta-ltd-gactapp-2010.