South Mississippi Electric Power Ass'n v. Mississippi Public Service Commission

211 So. 2d 827, 1968 Miss. LEXIS 1280
CourtMississippi Supreme Court
DecidedJune 10, 1968
DocketNo. 45065
StatusPublished
Cited by1 cases

This text of 211 So. 2d 827 (South Mississippi Electric Power Ass'n v. Mississippi Public Service Commission) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Mississippi Electric Power Ass'n v. Mississippi Public Service Commission, 211 So. 2d 827, 1968 Miss. LEXIS 1280 (Mich. 1968).

Opinion

INZER, Justice:

This is an appeal by South Mississippi Electric Power Association and four of its member associations from a decree of the Chancery Court of the First Judicial District of Hinds County, wherein that court affirmed in part, reversed in part and remanded an order of the Mississippi Public Service Commission which had granted to appellant, South Mississippi Electric Power Association, an amended certificate to construct enlarged facilities for supplying four of its member associations with wholesale electricity.

This is the third appearance of this case before this Court. Its history and the description of the parties involved are set out in Mississippi Power Company v. South Mississippi Electric Power Association, 254 Miss. 754, 183 So. 163 (1966), wherein we affirmed an order of the Mississippi Public Service Commission granting to appellant a certificate of public convenience and necessity to build facilities to generate and supply wholesale electricity to four of its member associations. This certificate was granted on March 7, 1963, as a result of an application filed with the commission on March 31, 1960. Appellees appealed from that order of the commission and obtained a “stay order” which prevented appellant from beginning .the construction authorized by the certificate. On July 20, 1965, while the former appeal was pending, appellant filed with the commission a petition to amend its certificate. It asked to enlarge the capacity of its system to properly meet the increased supply demands of the members it was authorized to serve. After this application was filed, appellees filed a plea in bar in this Court setting up that the application was an admission that the facilities proposed and authorized for construction were inadequate and thus rendered the appeal moot. We overruled the plea in bar.

The petition to amend alleged that the delay incident to appeals necessitated enlarging the system. It was alleged that inasmuch as the delay had been suffered there were changes that could be made in the generating facilities for the purpose of efficiency and economy. It asked that its certificate be amended to authorize it to install three fifty megawatt units in its generating station at Moselle and one fourteen megawatt unit at Benndale on the periphery of the system, rather than the three twenty-two megawatt units originally proposed. It also requested that the transmission system that it was authorized to build be altered so as to enable it to construct about 800 miles of 60KV transmission lines instead of the 392.6 miles originally proposed. The petition alleged that this increase in mileage was mostly due to the closing of loops in the lines as originally proposed. It was also requested that additional delivery points be established in order that it might properly supply electricity to the member associations it had heretofore been authorized to serve.

[829]*829Appellees protested the granting of the amended certificate and contended among other things that the facilities and generating plant described in the petition to amend was not a modification of the facilities and plant authorized by the order of March 7, 1963, but instead was a new and different plant and that it was in effect an original application and an abandonment of the certificate granted. As a consequence thereof appellees argue that appellant was required by the Public Utility Act of 1956 to prove, as it did in the original petition, that public convenience and necessity require construction of any facilities by appellant. Singing River, Dixie, Southern Pine and Pearl River Valley electric power associations filed a petition to intervene and they were allowed to do so. They joined in the request that the amended application be granted. The commission confined the issue to be tried on the amended application to the question of whether public convenience and necessity required the construction of the enlarged system rather than the system originally authorized. It rejected the evidence offered by appellees designed to show that public convenience and necessity did not require the construction of any facilities by the appellant. It also refused to allow appellees to cross examine appellant’s witnesses on this issue. The commission held that the testimony offered was immaterial to the issue before it at that time. Appellees were allowed to proffer the evidence rejected and it is in the record before us. The hearing was extended over a period of several weeks and resulted in a rather lengthy record, which we have carefully reviewed.

On January 4,1967, the commission entered an order sustaining the petition and granted an amended certificate authorizing appellant to construct the enlarged system. The order of the commission deals with all the questions involved in this appeal but due to its length we will only set out herein such portions as we deem appropriate.

The commission found from the evidence that:

31. From all of the evidence, the Commission is of the opinion and finds that the granting of an order herein amending the certificate of public convenience and necessity heretofore granted to Petitioner by the Order of March 7, 1963, in manner and form as sought by the Petition to Amend would materially benefit the Petitioner, the four corporate members of Petitioner to be supplied with power at wholesale by Petitioner and that segment of the public served by said corporate members of Petitioner; this would be particularly true in that Petitioner would thereby be enabled to build its system up to the capacity presently required in a more orderly way with a substantially smaller capital investment and would obtain a more efficient operation than would be the case if it approached the problem by building the system as originally certificated and making additions thereto.
32. On the whole record therein, the Commission is of the opinion and finds that the Petitioner has sustained its Petition to Amend its certificate of public convenience and necessity heretofore granted on March 7, 1963, by the evidence and that the public convenience and necessity require and will require that the Commission issue an order herein amending said certificate of public convenience and necessity in manner and form as sought and prayed for in the Petition to amend, as amended.

Appellees appealed to the Chancery Court of the First Judicial District of Hinds County. The chancellor, after reviewing the record, wrote a memorandum opinion wherein he concurred with the commission in its finding that the order as affirmed in Mississippi Power Company, supra, was res judicata in this cause. He also concurred with the commission in its finding that the delay of the appellant in constructing the authorized generating plant and transmission lines was through no fault of appellant, [830]*830but was solely caused by appellee’s appeal. The chancellor then stated:

It is my opinion that the issue for trial before the Commission on this second petition was whether public necessity and convenience required the increased facilities or any part thereof, due to increased needs and demands, if any, and increased or decreased supply, if any, occurring since the order on the original petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swartz v. Unemployment Appeals Commission
714 So. 2d 508 (District Court of Appeal of Florida, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
211 So. 2d 827, 1968 Miss. LEXIS 1280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-mississippi-electric-power-assn-v-mississippi-public-service-miss-1968.