South Dallas Water Authority v. Guarantee Co. of North America, USA

767 F. Supp. 2d 1284, 2011 WL 586083
CourtDistrict Court, S.D. Alabama
DecidedFebruary 9, 2011
DocketCivil Action 10-0604-CG-C
StatusPublished
Cited by9 cases

This text of 767 F. Supp. 2d 1284 (South Dallas Water Authority v. Guarantee Co. of North America, USA) is published on Counsel Stack Legal Research, covering District Court, S.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Dallas Water Authority v. Guarantee Co. of North America, USA, 767 F. Supp. 2d 1284, 2011 WL 586083 (S.D. Ala. 2011).

Opinion

ORDER

CALLIE V.S. GRANADE, District Judge.

After due and proper consideration of all portions of this file deemed relevant to the issues raised, and there having been no objections filed, the recommendation of the Magistrate Judge made under 28 U.S.C. § 636(b)(i )(B) and dated January 25, 2011 is ADOPTED as the opinion of this Court. Therefore, plaintiffs motion to remand (Doc. 4) is hereby GRANTED and this action is REMANDED to the Circuit Court of Dallas County, Alabama. It is further ORDERED that plaintiffs motion to tax costs and expenses (Doc. 6) is DENIED.

REPORT AND RECOMMENDATION

WILLIAM E. CASSADY, United States Magistrate Judge.

This cause is before the Magistrate Judge for issuance of a report and recommendation, pursuant to 28 U.S.C. § 636(b), on the notice of removal (Doc. 1), plaintiffs *1287 motion to remand (Doc. 4; see also Doc. 5) and motion to tax costs and expenses (Doc. 6), the response in opposition filed by defendant The Guarantee Company of North America USA (Doc. 14), 1 and plaintiffs reply (Doc. 21). Upon consideration of the foregoing pleadings, the Magistrate Judge recommends that the Court GRANT plaintiffs motion to remand and remand this action to the Circuit Court of Dallas County, Alabama.

FINDINGS OF FACT

1. Sometime in 2008, plaintiff awarded to W.D. Wainwright & Sons, Inc. (‘Wainwright”) a construction contract under which Wainwright “was obligated to install a water main and connecting water lines along various county roads to connect to the waste-water treatment plant being constructed by ... Cardinal Contracting, Inc.” (Doc. 1, Exhibit A, COMPLAINT, at ¶ 8) 2 As required by the construction contract and bid request, Wainwright obtained and submitted to plaintiff a performance bond which obligated it (Wainwright) and its third-party surety, The Guarantee Company, to fulfill the construction contract “and pay any damages, costs, expenses, including attorneys’ fees, and other sums due the Authority under the construction contract or arising from a breach thereof should Wainwright fail to timely perform the contract.” (Id. at ¶ 9)

2. Because Wainwright did not complete its work by the April 16, 2009 deadline, the South Dallas Water Authority’s (“South Dallas”) board of directors held a meeting with the officers of Wainwright on April 24, 2009 to discuss the corporation’s breach of the construction contract. (Id. at ¶ 13) At the meeting, Wainwright requested an opportunity to complete the contract and by letter dated May 6, 2009, plaintiff notified Wainwright and The Guarantee Company that although it was granting Wainwright’s request to complete the contract, it “reserved its right to enforce the contract’s liquidated damages provision, bg which liquidated damages would accumulate from the date of the breach until the contract was completed.” (Id. (emphasis supplied))

The Board of the South Dallas Water Authority recently met to act upon the recommendations of the United States Department of Agriculture regarding Wainwright’s failure to complete the Water Main Improvements Construction Contract by the contractual deadline of April 16, 2009. The Board has taken the following actions, of which you and Wainwright are hereby notified:
1. In reliance upon Wainwright’s commitment and representations made to the Authority during the April 24, 2009 conference, Wainwright is to fully complete, carry-out and satisfy its duties and responsibilities under the Contract as soon as possible and without any further delay.
2. The Authority will enforce the Liquidates Damages provision contained in § 4.03 of the Contract, which imposes Liquidated Damages of $500 for each day after the time specified for the Contract’s completion, i.e., April 16, 2009, until the Contract is completed.
3. The Authority will make no further Progress Payments to Wainwright.
4. Once Wainwright has completed, carried-out and fully satisfied its duties and responsibilities under the Contract, the Authority will make Final Payment *1288 to the order of Wainwright and Wainwright’s guarantor, The Guarantee Company, to be mailed directly to The Guarantee Company. If Wainwright claims all or a portion of the funds comprising the Final Payment, Wainwright should seek satisfaction from The Guarantee Company.

(Doc. 1, Exhibit F (May 6, 2009 letter) 3 )

3. Upon subsequently being informed by Wainwright that it could not complete the contract until September 2, 2009, the Water Authority notified Wainwright and The Guarantee Company by letter dated August 17, 2009 that no additional delays would be acceptable and demanded completion of the work not later than September 2, 2009. (Doc. 1, Exhibit A, COMPLAINT, at ¶ 15) Wainwright not only did not complete its work by September 2, 2009 but, in addition, informed the Water Authority, on September 17, 2009, that it needed another month to complete the work. (Id. at ¶ 16) The next day, September 18, 2009, the Water Authority informed Wainwright by letter that it was terminated. (Id. at ¶ 17)

As I previously advised, the South Dallas Water Authority is extremely dissatisfied with W.D. Wainwright & Sons’ performance of the Water Main Improvements Construction Contract. South Dallas’s dissatisfaction has been expressed in numerous letters either addressed directly to you or to The Guarantee Company of North America or its attorney, Graves Stiff, with which you were copied....
Wainwright previously represented that it would complete its work by September 2, 2009. As you recall, the contract required Wainwright to complete its work by April 16, 2009. By my letter to you dated August 7, 2009, Wainwright was placed on notice that no further delays were acceptable or would be tolerated. It has been brought to my attention that substantial work remains to be completed and that Wainwright now claims it will take an additional month to complete the work.... This is totally - unacceptable. Accordingly, Wainwright is hereby notified that it is terminated, effective today, by the South Dallas Water Authority for breach of contract.
South Dallas Water Authority has reserved, continues to reserve, and will exercise its contractual and legal rights with respect to the Water Main Improvements Construction] Contract including, but not limited to, obtaining indemnity from Wainwright and its surety, The Guarantee Company of North America, for all costs and expenses the Authority has previously incurred or will incur for Wainwright’s breach of contract.

(Doc. 1, Exhibit G (September 18, 2009 Letter) 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franco v. Franco (In re Franco)
574 B.R. 730 (D. New Mexico, 2017)
In re Kuzniewski
508 B.R. 678 (N.D. Illinois, 2014)
Alley Cassetty Companies, Inc. v. Wren
502 B.R. 609 (N.D. Georgia, 2013)
In re Lamb
465 B.R. 714 (S.D. Georgia, 2012)
Toskich v. J.H. Investment Services, Inc.
806 F. Supp. 2d 1224 (M.D. Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
767 F. Supp. 2d 1284, 2011 WL 586083, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-dallas-water-authority-v-guarantee-co-of-north-america-usa-alsd-2011.