South Central Tennessee Railroad Authority v. Harakas

44 S.W.3d 912, 2000 Tenn. App. LEXIS 520, 2000 WL 1121532
CourtCourt of Appeals of Tennessee
DecidedAugust 9, 2000
DocketM1999-00567-COA -R3-CV
StatusPublished
Cited by12 cases

This text of 44 S.W.3d 912 (South Central Tennessee Railroad Authority v. Harakas) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Central Tennessee Railroad Authority v. Harakas, 44 S.W.3d 912, 2000 Tenn. App. LEXIS 520, 2000 WL 1121532 (Tenn. Ct. App. 2000).

Opinion

OPINION

COTTRELL, J.,

delivered the opinion of the court, in which

KOCH, and CAIN, JJ., joined.

Plaintiffs, the owner and lessee of property on which a railroad track was located, obtained a temporary injunction prohibiting Defendants, owners of adjacent property, from building a house on what Plaintiffs alleged was their right-of-way. After Defendants presented evidence that Plaintiffs possessed only an easement as needed for railroad operations, rather than a right-of-way, the court dissolved the temporary injunction and denied a permanent injunction. Defendants then filed a motion to assess damages and enforce liability of surety on injunction bond pursuant to TenmR.Civ.P. 65.05, seeking recovery for the losses resulting from the issuance of the temporary injunction. Defendants appeal the trial court’s denial of their motion. We reverse.

The appellants, the Harakases, 1 seek review of the trial court’s denial of their post-trial motion, made pursuant to Tenn. R.Civ.P. 65.05, to assess damages and collect upon an injunction bond which had *914 been posted by the appellees, South Central Tennessee Railroad Authority (the “Authority”) and South Central Tennessee Railroad Company (the “Company” and, collectively, “the Railroads”). In the underlying action, the Harakases were enjoined, upon the Railroads’ motion, from continuing construction on a house they had begun budding sixty feet from the center of a railroad track owned by the Authority and leased to the Company. The Harakases assert that they incurred damages from the four and a half month delay in construction and were wrongfully enjoined from an act they had a right to perform. Although neither party has appealed the judgment in the underlying action, the facts of that dispute must be examined in considering the issues raised in this appeal.

In November of 1997, the Harakases were building a house on real property they owned. The property adjoined land owned by the Railroads around their railroad track. On November 10, the Railroads filed a complaint in which they claimed to own a right-of-way, extending one hundred (100) feet from the centerline of the track. They alleged that the Hara-kases’ construction, being only sixty (60) feet from the centerline, encroached on their right-of-way. They further alleged that the Harakases’ “violation of Plaintiffs’ property rights is willful, intentional, and gross, they being fully informed of the facts concerning the property and the rights of the parties therein.”

Based upon this complaint, the Railroads obtained a temporary restraining order (“TRO”) prohibiting the Harakases from further construction on the house or other encroachment on the right-of-way the Railroads claimed. The court required the Railroads to post a $5,000 injunction bond. That bond, with handwritten corrections by the surety, counsel for the Railroads, read in pertinent part:

The condition of this obligation is that the principal(s) will prosecute the temporary restraining order with effect, or in case of failure, pay all costs that may be adjudged against the defendant(s), and all such damages as may be sustained by the defendant(s) caused by the wrongful suing out of the temporary restraining order.

A hearing on the application for temporary injunction was held on November 25. The trial court made preliminary findings that (1) the Authority was “the owner, in fee, of a strip of land running ninety (90) feet in width from the centerline of the railroad track and lying between said cen-terline and the land acquired by Defendant in Deed Book 55, at page 433, ROHCT;” and (2) the Railroads were entitled to the temporary injunction restraining the Hara-kases from building any permanent structure encroaching upon “said strip of land.” The bond remained in effect.

The Harakases moved to dissolve the temporary injunction on January 9, 1998. Their motion was supported by an affidavit of Karen Dutton, a title examiner. After tracing the title history of the real property on which the house was being built, the title examiner attested that no right-of-way had been conveyed to the Railroads by the Harakases’ predecessors in title. The deed originally relied upon by the Railroads was determined by the examiner not to be applicable to the property in dispute. The trial court denied this motion, but noted that the matter should be set for trial as soon as possible.

At the March 18 trial, the parties stipulated to the relevant facts, and argument was had on the law. The parties stipulated that the railroad track had been in its present location since before 1900. They further stipulated that there was no *915 record that a right-of-way on the property where the house was being constructed had been conveyed by deed to any of the Railroads’ predecessors in interest or to the Railroads. In addition, the parties stipulated that there was no record of any lawsuit by the Authority or its predecessors in interest seeking to condemn such right-of-way or any lawsuit by the Hara-kases’ predecessors in interest seeking compensation for the taking of a right-of-way.

Faced with this inability to prove ownership of the right-of-way as originally asserted, at trial the Railroads took the position that the right-of-way originated in the Charter of the Nashville and Tuscaloosa Railroad Company dated June 6, 1877. 2 That Charter authorized the railroad “to appropriate as an easement the right-of-way not exceeding two hundred feet, one hundred feet on each side of the center line of said road,” to be exercised by filing a lawsuit. No such lawsuit was ever filed, however.

The Harakases acknowledged that the Railroads had a prescriptive easement based upon their long use of the track, but argued that such easement would extend only approximately ten (10) feet on either side of the center line of the track, which they claimed was the only amount of land obviously used for the operation of the train.

The trial court determined that, regardless of the size of any easement right-of-way which the Railroads might hold under their Charter, the Harakases, as owners in fee of the property on which the house was being constructed, were entitled to use their property in any way that did not interfere with the use of the property for railroad purposes. 3 Based upon this holding and its finding that “the house in issue is located so that it does not interfere with the current operation of the railroad,” the court held that the Harakases could “build a house on their property even if it is on the easement of the Plaintiffs, so long as the house does not interfere with the present or future operations of the railroad.” The court dissolved the temporary injunction, denied the Railroads’ request for a permanent injunction, and ordered the parties to brief the issue of the size of the easement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larry E. Parrish, P. C. v. Nancy J. Strong
Court of Appeals of Tennessee, 2018
In Re: Estate of Edward Stephen McRedmond
Court of Appeals of Tennessee, 2014
Gentry v. McCain
329 S.W.3d 786 (Court of Appeals of Tennessee, 2010)
Denver Area Meat Cutters & Employers Pension Plan v. Clayton
209 S.W.3d 584 (Court of Appeals of Tennessee, 2006)
Murfreesboro Medical Clinic, P.A. v. David Udom
Court of Appeals of Tennessee, 2004
McCall v. National Health Corp.
100 S.W.3d 209 (Tennessee Supreme Court, 2003)
Paul Rector v. Elizabeth Halliburton
Court of Appeals of Tennessee, 2003
Basil Marceaux v. Governor Don Sundquist
107 S.W.3d 527 (Court of Appeals of Tennessee, 2002)
Wright Medical Technology, Inc. v. Grisoni
135 S.W.3d 561 (Court of Appeals of Tennessee, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
44 S.W.3d 912, 2000 Tenn. App. LEXIS 520, 2000 WL 1121532, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-central-tennessee-railroad-authority-v-harakas-tennctapp-2000.