South Carolina State Highway Department v. The Tank Steamer Fort Fetterman

177 F. Supp. 76, 1959 U.S. Dist. LEXIS 2615
CourtDistrict Court, D. South Carolina
DecidedSeptember 26, 1959
DocketNo. 1073
StatusPublished
Cited by2 cases

This text of 177 F. Supp. 76 (South Carolina State Highway Department v. The Tank Steamer Fort Fetterman) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Carolina State Highway Department v. The Tank Steamer Fort Fetterman, 177 F. Supp. 76, 1959 U.S. Dist. LEXIS 2615 (D.S.C. 1959).

Opinion

WYCHE, District Judge.

On June 8, 1959, the Court of Appeals remanded this case to the District Court for further proceedings (4 Cir., 268 F.2d 27, 1959 A.M.C. 1342). The scope of the remand was limited to consideration of the following questions: 1. With respect to the gear rack used to elevate the bascule span, was its protrusion approximately 18 inches beyond the face of its concrete pier housing, but some 3% feet shoreward of the channel face of the protective fender line, a violation of the permit issued by the War Department for the construction of the Ashley River Bridge? 2. Was it reasonably possible that the failure to raise the bascule leaves more than approximately 71° could have caused or contributed to the collision and damage resulting from the ship’s impact against the bridge structure? 3. Was it reasonably possible that any other statutory violation on the part of the libellant could have caused or contributed to the destruction of the bascule?

Opinion.

In my findings on the first trial of this case I described the location, basic construction and mechanical operation of this bridge and its appurtenances.1

I have considered all proffered testimony and exhibits that were offered both at the prior trial and at this trial.

There are three statutes that cover the procedure followed by the War Department in authorizing bridges over navigable streams.2 While these vary somewhat among themselves, the War Department, which is the agency charged with the administration of these laws, follows substantially the identical practice in administering them.

There is now an official pamphlet describing the procedure to be followed by any agency desiring to erect an obstruction to navigable waters; a portion of this pamphlet is devoted specifically to bridges. At the time the permit for the Ashley River Bridge was sought, the then-existing pamphlet did not contain a section specifically applicable to bridges, but rather made reference to detailed instructions on the bridge application form itself. Such a form was used in connection with the Ashley River Bridge application and a copy of the same, from the Office of the Chief of Engineers, Washington, is in evidence. It is clear that the “plans” accompanying the application are not of the detailed type required for con[78]*78struction bids, and have no similarity to the meticulous detail of the so-called “shop drawings” or working plans used to fabricate and erect the bridge itself. The testimony of Robert J. Kennedy, Chief, Miscellaneous Civil Branch, Civil Works, Office of Chief of Engineers, U. S. Army Engineers, Washington, shows that in the many years throughout which he has handled all such applications, the only “plans” presented to the War Department were sketches of the sort accompanying the Ashley River Bridge application. It would be most extravagant to expend the builder’s funds for costly detailed construction plans and drawings before the builder is virtually assured of the approval of its application by the War Department.

As a general rule, it is only after a permit application has been approved that detailed contract drawings for the structure are prepared and these form the basis for bidding on the construction contract. Those to whom is delegated the work of preparing the contract drawings are required to make certain that those drawings faithfully implement the conditions of the permit, and afford its prescribed navigational clearance. After the job has been awarded, the successful bidder is required to prepare detailed shop drawings. On these drawings the location and size of each hole, spacing, plate and angle are set forth in precise measurements, in order that the work can be fabricated in the manner contemplated by the contract plans and the structure erected on its chosen site. ' Here again the shop drawings must obey all conditions of the permit and provide its prescribed navigational clearance.

War Department regulations, then as well as now, merely required that the “plans” accompanying the permit application show only those structural details which are needed to illustrate the effect of the proposed structure on navigation. The Ashley River Bridge application form specifically stated to the applicant that “the omission of all other details is generally desirable”. The most important feature of any permissible navigational obstruction is the clearance of the opening through the same; this opening constitutes the navigational fairway. The Ashley River Bridge application form provided that the sketch plan submitted therewith must show, among other things, “the outside structure lines separating the area left for navigation from the area occupied by the bridge * * The current regulations require particularly that the clearances of the navigational opening be outlined in red on the permit application, a procedure which had been followed in this application.

The processing of every application starts at the District Engineer’s level, where it is not unusual for the applicant and the District Engineer personnel to have informal talks to acquaint the applicant generally with what will be approved by the District Engineer. After the application is filed, notices of the same are sent by the District Engineer to all interested parties, and in some cases public hearings are held. A record is made of the proceedings by the District Engineer and it is sent to the Division Engineer and to the Chief of Engineers in Washington, with the recommendations of the District and Division Engineers. In Washington, it is reviewed by trained civilian personnel and if approved by them is processed routinely for the signature of the Secretary of War or his deputy. At this stage the approved permit is issued.

The work of the Army Engineers does not end there. It is their duty to see that the conditions of the permit are observed in the construction and maintenance of the bridge. Liaison of the most cooperative nature is maintained between the Army Engineers and those who build structures over navigable waters. Periodic inspections are made in order to avoid costly mistakes and to insure that the conditions of the permit are observed. During these inspections resort can be had to the detailed working plans on the job site. Thus all those who are charged with the determination of whether the structure is built in accordance with the [79]*79conditions of the permit have full opportunity to determine if the plans as drawn faithfully implement the conditions of the permit.

This general course of action was evidently followed in the case of the Ashley River Bridge. At the time of its construction the project was one of the most important highway bridges on the Atlantic Coast, and had been much publicized both at the local and regional levels.

During the greater part of this time the Army Engineers’ office in Charleston, was under the command of Colonel Jadwin, who filled the billets of both District and Division Engineer, and who was later Chief of the Army Engineers in Washington.

As early as 1922, conferences on the subject of the bridge had occurred between State officials and Army Engineer officials in Charleston. On May 17, 1922, a public hearing was held at the District Engineer’s office in Charleston. As a result of this hearing some rearrangement of the proposed structure was effected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
177 F. Supp. 76, 1959 U.S. Dist. LEXIS 2615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-carolina-state-highway-department-v-the-tank-steamer-fort-fetterman-scd-1959.