South Carolina Electric & Gas Co. v. Utilities Construction Co.

135 S.E.2d 613, 244 S.C. 79, 1964 S.C. LEXIS 62
Supreme Court of South Carolina·Decided March 26, 1964·No. 18188·Published·Cited by 28 cases

Opinions

Bussey, Justice.

In this action the plaintiff-respondent seeks to recover by way of indemnity, the sum of $39,000.00, interest and costs from the defendant-appellant. The controversy arose out of the following facts:

The Town of Holly Hill passed an ordinance which granted the plaintiff the electric franchise for that copimunity. The portions of this ordinance pertinent to this controversy read as follows:

“Section 3. The poles, towers, conduits, cables, conductors, transforming stations, fittings, appliances and appurtenances shall be so, constructed as not to unreasonably interfere with the proper use of the streets, avenues, alleys, ways, bridges and public places in said Town of Holly Hill and shall be maintained in a reasonably good condition and repair.
“Section 4. Whenever the Grantee shall cause any opening or alteration to be made in any of the streets, avenues, alleys, ways, bridges, or public places of said Town of Holly Hill for the purpose of installing, maintaining, operating or repairing any poles, towers, conduits, cables and other appliances, the work shall be. completed within a reasonable time and the Grantee shall upon completion of such work restore such portion of the streets, avenues, alleys, ways, [83] bridges or other public places to as good condition as it was before the opening or alterations so made.
“Section 5. The Grantee shall hold said Town of Holly Hill harmless from any and all liability o,r damages resulting from the negligence of the Grantee in the construction, maintenance or operation of said poles, towers, conduits, wires, cables and other appliances.”

Subsequently, on November 9, 1953, the plaintiff and the defendant entered into a written contract under which the defendant agreed to perform certain work assigned to it by the plaintiff, consisting of the construction and maintenance of transmission and distribution lines. This contract was prepared by plaintiff, or its counsel, and provided, inter alia, that the defendant would work as an independent contractor and not as an agent or employee of the plaintiff; that all work performed by the defendant would be done in a good, proper and workmanlike manner; and contained the following indemnity clause:

“(e) The Contractor hereby agrees to indemnify and to hold the Company harmless from any and all claims for damages to persons and/or property arising out of or in any way connected with the performance of any work covered by this contract.”

In February 1955, while the aforesaid contract was in force between the parties, and pursuant thereto, plaintiff gave the defendant a wo,rk order which required defendant to remove an old pole and install a new fifty foot pole, and put two cross arms on it and a gang switch — install light fixtures and some wire attachments — and patch the sidewalk. The pole in question was located near the curb on Main Street in the Town of Holly Hill. The wo,rk was completed and accepted by the plaintiff in February 1955. The defendant, unknown to "the plaintiff, improperly performed the work of repairing the sidewalk, in a manner which will be later herein more fully described. As a consequence thereof, a depression gradually developed in the patched area of the side[84] walk as a result of the defective workmanship and, on June 20, 1959, a Mrs. Brant, a resident of Holly Hill, stepped into the depression, fell and was severely injured. The depression had existed for some time prior to the date of Mrs. Brant’s injury.

Thereafter, Mrs. Brant brought suit against the plaintiff and the defendant for the damages caused by the injuries sustained. The plaintiff then made demand upon the defendant to take over the defense of the case op. the ground that it was entitled to be indemnified by the defendant, both by reason of the express indemnity provision of the contract and a contract of indemnity implied by law. The defendant denied that it was liable either to the plaintiff or Mrs. Brant and consequently refused to do so,. The parties, however, did enter into a stipulation under which, without prejudice to either, the plaintiff could settle Mrs. Brant’s case for $36,-000.00, and institute such action under its indemnity agreement, or otherwise, as it might be advised to recover from the defendant. The plaintiff then settled with Mrs. Brant for the sum of $36,000.00 and in this action seeks to, recover that amount plus interest and the sum of $3,000.00 in attorneys fees. No issue as to the reasonableness of either the settlement figure or the amount of attorneys fees is here involved, nor is it contended that said amounts would no,t bear interest if the defendant be liable at all.

The plaintiff sought to recover under both the express indemnity agreement and on the theory of an indemnity agreement implied by law. The defendant by answer denied that it was liable under either theory.

The case was referred by consent to the Honorable Harry M. Lightsey, Master in Equity for Richland County, who, after taking testimony, filed his report therein and recommended that plaintiff have judgment under both theories against the defendant in the full amount demanded. The circuit judge, upon hearing exceptions of the defendant to the master’s report, confirmed and adopted the factual findings [85] of the master and held that the plaintiff was entitled to indemnification by the defendant by reason of the express contract of indemnity and ordered judgment fo,r the full amount prayed for. The cirfcuit judge did not pass on exceptions to the master’s report with respect to the finding that the defendant was also liable to the plaintiff under a contract of indemnity implied by law. On appeal, defendant contends that the circuit judge erred in holding plaintiff entitled to recover under the express contract of. indemnity, but raises no question as to the amount of the recovery, if plaintiff be entitled to recover. The plaintiff urges as an additional sustaining ground that it is also entitled to recover by reason of a contract of indemnity implied by law.

The facts and circumstances surrounding the repair of the sidewalk by the defendant, as found by the master, confirmed by the circuit judge, and not excepted to, were as follows:

The defendant had to make an opening in the concrete sidewalk which was four to five inches thick, immediately adjacent to the old pole; dig a hoje and insert a new pole. It then had to remove the old pole, fill in the hole from which it was taken and repair the sidewalk. The defendant filled the area of the sidewalk necessary to be repaired with soil to within one and a quarter to one and three-quarters inches of the sidewalk surface. It then filled in the remaining void with a mprtar patch which consisted of one part cement and seven parts topsoil taken from an adjacent alley.

Free access — add to your briefcase to read the full text and ask questions with AI

South Carolina Electric & Gas Co. v. Utilities Construction Co., 135 S.E.2d 613, 244 S.C. 79, 1964 S.C. LEXIS 62 (S.C. 1964).

135 S.E.2d 613 (South Carolina Electric & Gas Co. v. Utilities Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Porcella v. TJX Companies, Inc.
D. South Carolina, 2020
Ashley II of Charleston, L.L.C. v. PCS Nitrogen, Inc.
763 S.E.2d 19 (Supreme Court of South Carolina, 2014)
Sherlock Holmes Pub, Inc. v. City of Columbia
697 S.E.2d 619 (Court of Appeals of South Carolina, 2010)
Dent v. Beazer Materials and Services, Inc.
993 F. Supp. 923 (D. South Carolina, 1995)
Rogers v. South Carolina Department of Parole & Community Corrections
464 S.E.2d 330 (Supreme Court of South Carolina, 1995)
Byerly Ex Rel. Estate of Byerly v. Connor
415 S.E.2d 796 (Supreme Court of South Carolina, 1992)
Town of Winnsboro v. Wiedeman-Singleton, Inc.
414 S.E.2d 118 (Supreme Court of South Carolina, 1992)
Cooke v. Allstate Management Corp.
741 F. Supp. 1205 (D. South Carolina, 1990)
Henderson v. St. Francis Community Hospital
369 S.E.2d 652 (Court of Appeals of South Carolina, 1988)
Sharpe Ex Rel. Estate of Sharpe v. South Carolina Department of Mental Health
354 S.E.2d 778 (Court of Appeals of South Carolina, 1987)
South Carolina State Ports Authority v. Booz-Allen & Hamilton, Inc.
346 S.E.2d 324 (Supreme Court of South Carolina, 1986)
Morris v. Mooney
343 S.E.2d 442 (Supreme Court of South Carolina, 1986)
Byrd Motor Lines, Inc. v. Dunlop Tire & Rubber Corp.
304 S.E.2d 773 (Court of Appeals of North Carolina, 1983)
Stuck v. Pioneer Logging MacHinery, Inc.
301 S.E.2d 552 (Supreme Court of South Carolina, 1983)
McCain Manufacturing Corp. v. Rockwell International Corp.
528 F. Supp. 524 (D. South Carolina, 1981)
Richardson-Wayland Electrical Corp. v. Virginia Electric & Power Co.
247 S.E.2d 465 (Supreme Court of Virginia, 1978)