Sorrels Steel Company, Inc. v. Great Southwest Corporation, Fireman's Fund Insurance Company, and the American Insurance Company

906 F.2d 158, 18 Fed. R. Serv. 3d 175, 1990 U.S. App. LEXIS 12048, 1990 WL 90226
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 19, 1990
Docket89-4314
StatusPublished
Cited by23 cases

This text of 906 F.2d 158 (Sorrels Steel Company, Inc. v. Great Southwest Corporation, Fireman's Fund Insurance Company, and the American Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sorrels Steel Company, Inc. v. Great Southwest Corporation, Fireman's Fund Insurance Company, and the American Insurance Company, 906 F.2d 158, 18 Fed. R. Serv. 3d 175, 1990 U.S. App. LEXIS 12048, 1990 WL 90226 (5th Cir. 1990).

Opinion

CLARK, Chief Judge:

I. Introduction.

Great Southwest Corporation (GSW) and its sureties appeal from a district court *161 order denying their motion for judgment notwithstanding the verdict, to alter or amend the judgment, for a new trial, or for remittitur in this breach of contract action. We affirm in part, vacate in part, and remand for further proceedings.

II. Facts.

A. Background.

The City of Tampa, Florida (the City) contracted with GSW to build the Tampa Performing Arts Center. On April 4, 1985, GSW subcontracted with Sorrels Steel Company, a Mississippi corporation, (Sorrels) to provide the detailing, fabrication, and delivery of certain structural and miscellaneous steel. Documentation of the subcontract was in the form of a purchase order (the Purchase Order). The Purchase Order provided for “inspection” of the fabricated steel at Sorrels’ plant but specifically excluded “testing.”

Production under the Purchase Order began in mid to late July 1985. Sorrels soon found that it could not maintain a smooth fabrication schedule because of incomplete and inaccurate contract drawings, slow approval of its shop drawings, and numerous design changes. In addition, the City imposed a rigorous testing program which required ultrasonic testing of 100 percent of all full-penetration welds and magnetic-particle testing of 30 percent of all fillet welds. Sorrels submitted to the testing program but indicated that it would need a change order because testing was specifically excluded from its contract. The testing program significantly increased Sorrels’ production time.

Sorrels sent correspondence and various documents to GSW seeking additional compensation for the delays and extra costs associated with these problems and changes. Sorrels informed GSW that fabrication was proceeding in piecemeal fashion and that Sorrels’ damages were total-ling approximately $200,000 per month. GSW forwarded Sorrels’ claims and documentation to the City and assured Sorrels it would be kept informed of progress on the claims.

On November 8, 1985, Sorrels filed suit against GSW in Mississippi state court for breach of contract because the claims had not been satisfactorily resolved. GSW took the position that Sorrels’ damages were caused by the City and its architect and did not result from a breach of the Purchase Order.

B. The Addendum To Purchase Order.

On November 24, 1985, the parties and their attorneys met in Fort Lauderdale, Florida to discuss the possibility of settling the lawsuit. After negotiations, the parties executed a document entitled “Addendum To Purchase Order” (Addendum). The Addendum stated, among other things, that Sorrels’ “impact” claim for damages from incomplete and inaccurate contract drawings, slow approval of its shop drawings, and numerous design changes, as expressed in the pending action

is the responsibility of parties other than GSW and that GSW will present the claim to the City of Tampa or will cooperate with Sorrels in the event Sorrels elects to present the claim in its own behalf. It is intended that this is a “Pass Thru Agreement” and as against GSW, Sorrels will only be entitled to have and receive the amount of the claim that GSW recovers against other parties....

The Addendum dealt separately with Sorrels’ claim for additional compensation based on the City’s testing program. The Addendum indicated that the City would issue a change order to GSW for the testing program and that GSW would in turn issue a change order to Sorrels. Sorrels agreed to document the value of the testing change. Sorrels also agreed to dismiss its lawsuit against GSW “without prejudice” and to continue fabricating steel. In addition to signing the Addendum, GSW orally agreed to obtain a complete and accurate set of contract drawings for Sorrels and to expedite the orderly approval of Sorrels’ shop drawings, so that Sorrels could fabricate steel in an efficient manner.

The situation did not improve for Sorrels after the Addendum was executed. GSW did not provide Sorrels with a complete and accurate set of contract drawings as it had *162 promised, nor did GSW expedite the orderly approval of Sorrels’ shop drawings. Sorrels was again reduced to fabricating- steel on a piecemeal basis at substantial losses. As Sorrels received contract payments from GSW, it executed releases of its claims against GSW and the City. Some of these documents included releases of GSW and the City from all claims for delay and extra work.

On February 21, 1986, Sorrels sent GSW documentation to support the value of its testing claim. GSW forwarded the documentation to the City. Because the City did not quickly resolve the claim, Sorrels sent GSW a second, professionally prepared testing claim, which GSW delivered to the City. Sorrels did not receive a change order reflecting the increased costs of the weld-testing program. Sorrels eventually went out of business and sold its assets at distress prices.

C. The Present Action.

On April 16, 1986, Sorrels again brought suit against GSW in Mississippi state court for breach of contract. Sorrels sought recovery of its “impact and testing” damages and loss-of-going-concern damages. GSW removed the case to federal court based on diversity of citizenship and defended on the grounds that Sorrels’ damages were caused by the City and its architect, that the Addendum precluded Sorrels from recovering its damages from GSW, and that Sorrels had executed written releases of all claims against GSW. GSW also filed a counterclaim against Sorrels for breach of contract.

GSW subsequently filed a motion to transfer the case to the district court in Tampa, Florida so that the City and its architect could be joined as parties. The district court denied the motion. GSW then moved for dismissal under Fed.R. Civ.P. 19(b), claiming that the City and its architect were indispensable parties. That motion was also denied. The case proceeded to trial before a jury.

During the course of the trial, Sorrels sought to introduce evidence of GSW’s oral promise to obtain a complete and accurate set of contract drawings and to expedite the orderly approval of Sorrels' shop drawings. GSW objected to this evidence on the ground that it contradicted the express terms of the Addendum and was therefore barred by the parol evidence rule. The district court overruled GSW’s objection. Sorrels also sought to introduce evidence that the parties did not intend the releases to discharge GSW from all liability for Sorrels’ damages. GSW again objected that the evidence was barred by the parol evidence rule. The court also overruled this objection.

The case was submitted to the jury on special interrogatories.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Origin Bank v. Barrett
S.D. Mississippi, 2019
Asbury MS Gray-Daniels, L.L.C. v. Daniels
812 F. Supp. 2d 771 (S.D. Mississippi, 2011)
O'Fallon v. Encore Receivable Management, Inc.
831 F. Supp. 2d 957 (S.D. Mississippi, 2011)
Cypress Pharmaceuticals, Inc. v. CRS Management, Inc.
827 F. Supp. 2d 710 (S.D. Mississippi, 2011)
PIC Group, Inc. v. LandCoast Insulation, Inc.
718 F. Supp. 2d 795 (S.D. Mississippi, 2010)
Dretchen v. Allan Pharmaceutical, LLC
707 F. Supp. 2d 677 (S.D. Mississippi, 2010)
Perry-McCall Construction, Inc. v. United States
46 Fed. Cl. 664 (Federal Claims, 2000)
Richmond Capital Corp. v. Federal Express Corp.
54 F. Supp. 2d 676 (M.D. Louisiana, 1999)
Cox v. Howard, Weil, Labouisse, Friedrichs, Inc.
619 So. 2d 908 (Mississippi Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
906 F.2d 158, 18 Fed. R. Serv. 3d 175, 1990 U.S. App. LEXIS 12048, 1990 WL 90226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sorrels-steel-company-inc-v-great-southwest-corporation-firemans-fund-ca5-1990.