Sonat Marine Inc. v. Belcher Oil Co.

629 F. Supp. 1319, 1985 U.S. Dist. LEXIS 18220
CourtDistrict Court, D. New Jersey
DecidedJuly 3, 1985
DocketCiv. A. 83-2563
StatusPublished
Cited by8 cases

This text of 629 F. Supp. 1319 (Sonat Marine Inc. v. Belcher Oil Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sonat Marine Inc. v. Belcher Oil Co., 629 F. Supp. 1319, 1985 U.S. Dist. LEXIS 18220 (D.N.J. 1985).

Opinion

OPINION

DEBEVOISE, District Judge.

This is an admiralty proceeding brought under 28 U.S.C. Section 1333 in which damages are sought for the grounding of the barge Interstate 138 during its approach to the Belcher Marine Terminal in the early morning hours of August 8, 1982.

The barge Interstate 138 was owned by plaintiff Intercities Navigation Corporation and operated by plaintiff Sonat Marine Inc. The barge was under the control of the tug Diplomat, owned by plaintiff Gellenthin Bulk Transport Corporation and operated by Sonat Marine Inc. An assist tug, the Patriot, operated by Sonat Marine Inc., was also aiding the navigation of the Interstate 138. It was stipulated that the damages incurred as a result of the grounding were $535,000 exclusive of prejudgment interest. All of these damages were incurred by Sonat.

The Marine terminal above the water line was and is owned by defendant Belcher Oil Company of New York. Belcher is a lessee of the underwater part of the terminal. It neither leases nor owns the area between the leased portion of the terminal and the government channel over which vessels pass to reach the terminal.

A trial has been held and this constitutes my findings of fact and conclusions of law.

Findings of Fact

The Belcher terminal is located on the north side of the Kill Van Kull waterway. The terminal consists of two main piers, a shipper and a barge pier. I shall attach to the transcribed copy of this opinion copies of deposition Exhibit D-13, an aerial photo of the terminal and of deposition Exhibit D-ll, a portion of the NOAA chart showing the terminal. Reference can be made *1321 to these exhibits when one reads the description of the piers which follows.

The ship pier runs almost perpendicular to the government maintained channel on roughly a north/south axis. The channel end of the ship pier, the southern end, is some 15 feet inshore of the United States pier line. Three mooring cells or dolphins, are located at the channel end of the ship pier. One is located almost immediately to the west of the pier end. Another is located roughly 100 feet to the east of the end of the ship pier. A third, slightly smaller dolphin, is located approximately 100 yards to the east of the ship pier head. These three dolphins run nearly parallel to the channel and together with the end of the pier form the ship berth. Docking space for small barges and vessels is available along the eastern side of the ship pier inshore of the line of the dolphins.

The barge pier consists of a wood and steel catwalk together with a pipe rack which extends first, perpendicular and to the east of the ship pier for a distance of roughly 200 feet and then turns approximately 50 degrees towards the south in the general direction of the main shipping channel. Along the face of and parallel to the barge dock are four breasting dolphins, two of which are located immediately in front of the barge berth face and two of which are located beyond the end of the barge dock catwalk, but generally in line with the first of the two dolphins.

The barge dock was constructed in 1976 by Howard Oil Company (“Howard”), the previous owner of the terminal. The barge dock has been constructed pursuant to a permit issued to Howard by the Corps of Engineers, which permitted the construction of the pier and the dredging of an irregularly shaped area located between the new pier and the pre-existing ship berth. This dredging allowed barges being brought in by Howard to reach the barge dock from the main channel.

Belcher purchased the marine terminal from Howard in 1978. Shortly after purchasing the terminal, Belcher decided to make substantial improvements to the facility. These improvements included both dredging and structural improvements in the ship berth and dredging in and around the barge berth and its approach. Belcher filed an application for a Corps of Engineers’ permit on January 8, 1980. This permit application which was ultimately granted on December 30, 1981, covered Only the proposed improvements to the ship berth. Belcher did not seek or obtain a permit for the work contemplated on the barge berth. Work was performed during the winter of 1981/82, and was completed in February 1982.

Belcher’s terminal is shown on NO A A chart 12333 which generally covers the Kill Van Kull and the northern part of the Arthur Kill. It shows a reported depth of 26 feet at mean low tide from the government maintained channel of the Arthur Kill into the barge dock area of the terminal. On the chart the eastern boundary of the 26 foot area is a line running through the four dolphins at the barge dock and extending out to the edge of the main channel. On the chart the western boundary of the 26 foot area is a line roughly parallel to the eastern boundary running through the most easterly of the ship-dock dolphins and extending out to the edge of the channel. To the east of the 26 foot reported depth area the depth is reported on the chart to be 22 feet or less. Witnesses for Sonat stated that the water around the rock which Interstate 138 grounded is shown by countour lines which have a 30 foot depth, but I must confess that I have trouble discerning this from my examination of the chart. Quite obviously a vessel with a draft of 22 feet or more entering the barge berth would seek to use the reported 26 foot area and would seek to avoid passing over waters to the east.

In 1982 Belcher retained Weeks Dredging and Construction Company to conduct dredging operations. Belcher had obtained from the Corps of Engineers a permit to dredge a large area to the south of the ship pier to a 38 foot depth. This area was shown on Defendant’s Exhibit 12. In addition, in the language of its Vice President *1322 for Operations and Engineering, Belcher “stretched the permit” and had Weeks perform dredging which had the effect of widening to the east the 26 foot area from the barge dock to the government channel. This required dredging from the terminal berth area and in places south of the most southerly barge dock dolphin. Weeks made soundings from the channel to the barge dock and where the depth was already 26 feet or more, it was unnecessary to perform actual dredging operations. I shall attach to the transcript of this opinion a copy of Exhibit P-33A. This sketch shows the approximate Weeks dredge line. The area between the dredge line and the line drawn through the four dolphins to the channel would be the approximate additional area in which Belcher sought to maintain a 26 foot depth. It should be noted that the rocks shown on P-33A are not the rock which caused the difficulty in the present case. They are rocks located during the search for the pertinent obstruction and are at a depth which is greater than 26 feet at mean low water.

Belcher’s reason for widening the approach was that it recognized that larger vessels had problems entering the barge berth and required a greater margin of safety.

To accomplish this Belcher asked Weeks to perform a survey to the east of the barge dock as dredged by Howard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
629 F. Supp. 1319, 1985 U.S. Dist. LEXIS 18220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sonat-marine-inc-v-belcher-oil-co-njd-1985.