Sollers Point Company, Sollers Point Limited Partnership, and Shapiro Family, LLC v. L.M. Zeller and Zeller Elevator Company

CourtIndiana Court of Appeals
DecidedMarch 23, 2020
Docket19A-CC-1156
StatusPublished

This text of Sollers Point Company, Sollers Point Limited Partnership, and Shapiro Family, LLC v. L.M. Zeller and Zeller Elevator Company (Sollers Point Company, Sollers Point Limited Partnership, and Shapiro Family, LLC v. L.M. Zeller and Zeller Elevator Company) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sollers Point Company, Sollers Point Limited Partnership, and Shapiro Family, LLC v. L.M. Zeller and Zeller Elevator Company, (Ind. Ct. App. 2020).

Opinion

FILED Mar 23 2020, 8:41 am

CLERK Indiana Supreme Court Court of Appeals and Tax Court

ATTORNEYS FOR APPELLANTS ATTORNEY FOR APPELLEES Clifford R. Whitehead Douglas K. Briody L. Katherine Boren Evansville, Indiana Ziemer, Stayman, Weitzel & Shoulders, LLP Evansville, Indiana

IN THE COURT OF APPEALS OF INDIANA

Sollers Point Company, March 23, 2020 Sollers Point Limited Court of Appeals Case No. Partnership, and 19A-CC-1156 Shapiro Family, LLC, Appeal from the Vanderburgh Appellants-Defendants, Superior Court The Honorable Richard G. v. D’Amour, Judge Trial Court Cause No. L.M. Zeller and 82D07-1507-CC-3419 Zeller Elevator Company, Appellees-Plaintiffs.

Mathias, Judge.

[1] L.M. Zeller and Zeller Elevator Company (collectively “Zeller”) filed a

complaint in Vanderburgh Superior Court against Sollers Point Company,

Sollers Point Limited Partnership, and Shapiro Family LLC (collectively

Court of Appeals of Indiana | Opinion 19A-CC-1156 | March 23, 2020 Page 1 of 18 “Sollers Point”),1 seeking to recover approximately $45,000 for elevator repair

services Zeller had performed at a commercial building owned by Sollers Point

in Evansville, Indiana. Following a bench trial, the trial court entered judgment

in favor of Zeller in the amount of $26,729, plus pre-judgment interest, but

found that the remaining money sought by Zeller was barred by the statute of

limitations. Sollers Point filed a notice of appeal from this judgment, and Zeller

filed a motion to correct error in the trial court claiming that the trial court had

improperly excluded certain charges from its award of damages. After the trial

court clerk filed its Notice of Completion of Clerk’s Record in this court, the

trial court issued an order purporting to grant Zeller’s motion to correct error.

In this appeal, Sollers Point presents three issues for our review, which we

restate as:

I. Whether the trial court lacked jurisdiction to rule on Zeller’s motion to correct error;

II. Whether Zeller’s claims are barred by the applicable statute of limitations; and

III. Whether the trial court erred by awarding pre-judgment interest.

[2] We affirm in part, reverse in part, and remand.

1 Shapiro Family, LLC is the sole general partner of Sollers Point Limited Partnership.

Court of Appeals of Indiana | Opinion 19A-CC-1156 | March 23, 2020 Page 2 of 18 Facts and Procedural History [3] This case involves a dispute over billing for elevator services Zeller performed at

a commercial building (“the Building”) owned by Sollers Point on Main Street

in Evansville, Indiana. The Building was constructed in the late 1960s, and

Zeller began to work on the elevators in the Building in 1969 as a subcontractor.

In 1972, the company that then owned the Building, Transamerica Investment

Group, hired Zeller directly to work on the elevators in the Building. And, in

early 1973, Transamerica entered into a maintenance agreement with Zeller,

under which Zeller agreed to provide regular maintenance and inspection of the

elevators for $875 per month.

[4] In 1974, Sollers Point purchased the building from Transamerica but did not

assume the maintenance agreement with Zeller from Transamerica. Zeller

nevertheless continued to perform regular maintenance on the elevators for the

same rate as provided in its agreement with Transamerica. Through the years,

Zeller notified Sollers Point in writing that it planned to raise its rates for its

work and invoiced Sollers Point for its regular maintenance. Zeller also

provided separate invoices for work that did not fall within the ambit of regular

maintenance. Sollers Point also regularly asked Zeller to perform other

maintenance and repairs to the Building, including servicing and replacing air

conditioners, smoke detectors, cooling fans, and a boiler. For decades, Sollers

Point paid Zeller’s invoices without conflict.

[5] The basis for the present conflict started on January 24, 2009, when a water

main near the Building broke, causing flooding in the basement and part of the Court of Appeals of Indiana | Opinion 19A-CC-1156 | March 23, 2020 Page 3 of 18 elevator shafts. Sollers Point asked Zeller to inspect and repair any damage

done to the elevator equipment. For several weeks, Zeller employees spent

hours cleaning up and repairing damage caused by the flood. These efforts

included removing water from the basement and elevator pits; cleaning and

repairing elevator cars that had been submerged and damaged by water;

disassembling, draining, cleaning, and lubricating various components of the

elevator system; cleaning and lubricating the various wire ropes and cables used

in the elevator system; pressure washing the walls of the elevator pits, the

ladders, sills, doors, and bottoms of the elevator cars, all of which had been

exposed to hydraulic fluid; cleaning all electrical switches; replacing all

bearings; and various other tasks. Zeller also decided that the compensating

cables for the elevators might rust as a result of the water damage and

purchased new cables to replace the older ones.

[6] On February 13, 2009, Zeller submitted an estimate for the costs of the clean-up

and repairs resulting from the flood. The total of the estimate was $58,691.49.

The estimate also stated that the cost of the work performed to date was

$44,996.44, and provided that the cost to install the new cables would be

$16,360.2 Sollers Point submitted this estimate to its insurance carrier, who paid

Sollers point $58,691.49, the exact amount of the estimate. Zeller later

2 We note that, for whatever reason, the cost of the work performed to date ($44,996.44) plus the cost to install the cables ($16,360) equals $61,356.44, not the $58,631.49 total of the estimate.

Court of Appeals of Indiana | Opinion 19A-CC-1156 | March 23, 2020 Page 4 of 18 determined that the cables did not need to be replaced and never installed the

new cables.

[7] After the flood, Zeller continued to send Sollers Point regular invoices for

routine maintenance, which Sollers Point continued to pay. The costs

associated with the flood were not included in these regular invoices, which

Zeller billed under a separate account (“the Flood Event Account”). Although

Zeller provided an estimate shortly after the flood event, Zeller did not submit

an invoice relating the costs of the flood clean-up and repair until December 21,

2011. This December 21 invoice (“the 2011 Invoice”) demanded payment of

$44,996.44, the same as the amount listed in the 2009 estimate for the work

performed to date. Zeller later explained that, because replacement of the cables

was later deemed unnecessary, it decided not to bill Sollers Point for any of the

flood-related work that occurred after the 2009 estimate.3 Sollers Point never

paid this invoice.4

[8] On July 10, 2015, over three and a half years after submitting the 2011 Invoice,

Zeller filed a complaint against Sollers Point, seeking to recover the unpaid

$44,996.44 it had invoiced. Sollers Point filed an answer to the complaint on

September 3, 2015. Sollers Point filed a motion for summary judgment on

3 The 2011 Invoice also includes charges for items and services that occurred before the flood, such as refurbishing elevator doors in 2005 and the purchase of a DC drive in 2004—a drive that was ultimately never installed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper Industries, LLC v. City of South Bend
899 N.E.2d 1274 (Indiana Supreme Court, 2009)
Monroe Guaranty Insurance Co. v. Magwerks Corp.
829 N.E.2d 968 (Indiana Supreme Court, 2005)
Mitchell v. Mitchell
695 N.E.2d 920 (Indiana Supreme Court, 1998)
Kadrmas, Lee & Jackson, P.C. v. Bolken
508 N.W.2d 341 (North Dakota Supreme Court, 1993)
Hughes v. Glaese
659 N.E.2d 516 (Indiana Supreme Court, 1995)
King v. Terry
805 N.E.2d 397 (Indiana Court of Appeals, 2004)
Russo v. Southern Developers, Inc.
868 N.E.2d 46 (Indiana Court of Appeals, 2007)
Ferguson v. Modern Farm Systems, Inc.
555 N.E.2d 1379 (Indiana Court of Appeals, 1990)
Toth v. Mansell
566 N.E.2d 730 (Appellate Court of Illinois, 1991)
Bopp v. Brames
713 N.E.2d 866 (Indiana Court of Appeals, 1999)
Morgan v. Benner
712 N.E.2d 500 (Indiana Court of Appeals, 1999)
Harlan Sprague Dawley, Inc. v. S.E. Lab Group, Inc.
644 N.E.2d 615 (Indiana Court of Appeals, 1994)
Washington County Memorial Hospital v. Hattabaugh
717 N.E.2d 929 (Indiana Court of Appeals, 1999)
Burns Construction, Inc. v. Valley Concrete
322 N.E.2d 404 (Indiana Court of Appeals, 1975)
McMahan v. Snap on Tool Corp.
478 N.E.2d 116 (Indiana Court of Appeals, 1985)
Jackson v. Trancik
953 N.E.2d 1087 (Indiana Court of Appeals, 2011)
Stickdorn v. Zook
957 N.E.2d 1014 (Indiana Court of Appeals, 2011)
Davis v. Shelter Insurance Companies
957 N.E.2d 995 (Indiana Court of Appeals, 2011)
Jeffrey Crider v. Christina Crider
15 N.E.3d 1042 (Indiana Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Sollers Point Company, Sollers Point Limited Partnership, and Shapiro Family, LLC v. L.M. Zeller and Zeller Elevator Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sollers-point-company-sollers-point-limited-partnership-and-shapiro-indctapp-2020.