SOLID STATE CHEMICALS LTD. v. ASHLAND LLC

CourtDistrict Court, W.D. Pennsylvania
DecidedJanuary 27, 2020
Docket2:19-cv-01044
StatusUnknown

This text of SOLID STATE CHEMICALS LTD. v. ASHLAND LLC (SOLID STATE CHEMICALS LTD. v. ASHLAND LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SOLID STATE CHEMICALS LTD. v. ASHLAND LLC, (W.D. Pa. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

SOLID STATE CHEMICALS LTD. and ) SOLID STATE CHEMICALS INC., ) ) Civil Action No. 19-1044 Plaintiffs, ) ) Judge Marilyn J. Horan v. ) ) ASHLAND LLC, ) ) Defendant. )

OPINION AND ORDER Plaintiffs, Solid State Chemicals Ltd. and Solid State Chemicals Inc. (collectively, “Solid State”), filed the present Complaint on August 19, 2019, claiming breach of contract and negligent misrepresentation. (ECF No. 1). On October 7, 2019, Defendant, Ashland LLC, moved to dismiss the Complaint for failure to state a claim. (ECF No. 11). The parties briefed the issues, (ECF No. 12, 16, 17, 20), and the Court heard oral argument on January 6, 2020. The Motion is now ripe for decision. Based on the following reasoning, Ashland’s Motion to Dismiss will be granted in part and denied in part.

I. Background Solid State produces and sells solid maleic anhydride, a chemical often used for manufacturing resins for fiberglass-reinforced products. (ECF No. 1, at ¶¶ 3–4). In February 2017, Solid State and Ashland LLC began discussing moving Solid State’s solid maleic anhydride line from a facility in Alabama to Ashland’s facility at Neville Island, Pennsylvania. Id. at ¶¶ 18–19. After several months of presentations, discussions, and negotiations, id. at ¶¶ 20–37, the parties executed the Manufacturing Services Agreement on October 24, 2017, id. at ¶ 39. The Agreement went into effect on November 1, 2017, for an initial term of sixty months. Id. at ¶ 40. Under the Agreement, Ashland was required to manufacture solid maleic anhydride for Solid State. Id. at ¶ 41. Section 2.9 of the Agreement, however, allowed for Ashland to stop

production of solid maleic anhydride under certain circumstances, namely that, “In no event will Manufacturer be required to perform any of its obligations under this Agreement in[:] (i) an unsafe or imprudent manner; (ii) contravention of Manufacturer’s environmental, health and safety standards; or (iii) violation of applicable laws.” (ECF No. 12, at § 2.9). As for Solid State, the Agreement required it to provide certain equipment to Ashland, subject to a bailment agreement. (ECF No. 1, at ¶ 42). Solid State’s equipment was delivered to Ashland’s facility at Neville Island on November 29 and 30, 2017. Id. at ¶ 43. The parties also anticipated that further capital investments or equipment might be required during the contract term. Section 2.10 of the Agreement consequently provides:

As part of Manufacturer agreeing to manufacture the Products: (i) Manufacturer may be required to make additional capital investment to meet production needs, and (ii) Customer will provide Equipment to Manufacturer for the manufacture of the Products, which shall be subject to the Bailment Agreement attached hereto as Schedule 4. In the event that additional significant capital investments or equipment are required to meet production demands, the Parties will agree on an appropriate cost amortization or bailment agreement to be executed by the Parties and incorporated to the Agreement by reference.

(ECF No. 12, at § 2.10). In January 2018, Ashland decided that an automatic bagging machine was necessary and informed Solid State that “Ashland would be covering the cost because it was being mandated by Ashland.” (ECF No. 1, at ¶¶ 45–46). In early June 2018, in conjunction with a Pre-Start Safety Review and preliminary trials for the systems involved in the manufacturing line, “Ashland confirmed that the air produced by the supplied breathing air system for the line had been tested and approved.” Id. at ¶¶ 50–53. Ashland began manufacturing solid maleic anhydride by the end of June 2018. Id. at ¶ 55. Then, on July 27, 2018, Ashland issued a stop work order. Id. at ¶ 56. Two weeks later, Ashland made a list of action items needed to get the line up and running again. Id. at ¶ 59. The list “focused on training and protective gear for Ashland’s employees” and did not include

significant capital expenditures. Id. On August 20, 2018, Ashland informed Solid State that the line could resume operation. Id. at ¶ 60. Additional emissions testing in September 2018 and air quality monitoring in October 2018 showed that the solid maleic anhydride line complied with applicable permits and OSHA standards. Id. at ¶¶ 61–62. On May 3, 2019, Ashland issued another stop work order. Id. at ¶ 66. On May 30, 2019, Ashland identified “seven broad scope, high capital jobs that each required a plan in place and capital approved before operation could resume.” Id. at ¶ 70. Ashland did not include the automatic bagging machine, which had been delivered to the Neville Island facility the previous month but was not yet installed, among the seven projects. Id. at ¶¶ 65, 70. On July 1, 2019,

Ashland notified Solid State that Ashland would terminate the agreement if Solid State did not commit to contribute toward the seven projects, plus the automatic bagging system. Id. at ¶ 72. Two weeks later, Solid State responded to Ashland, stating that it was Ashland, not Solid State, that was in breach of the Agreement. Id. at ¶ 73. In the meantime, in June 2019, Ashland received test results from additional air monitoring done at the Neville Island facility. Id. at ¶ 71. The test results “showed that while all areas of the facility were in compliance with the OSHA regulations, many areas exceeded Ashland’s purported internal exposure standards.” Id. Ashland continued to operate its Neville Island facility despite those test results. Id. Nevertheless, Ashland did not resume operations of the solid maleic anhydride line following the May 3, 2019 stop work order, and instead considered its Agreement with Solid State terminated as of August 1, 2019. Id. at ¶ 74. Solid State subsequently filed the present Complaint, alleging breach of contract in Count One and negligent misrepresentation in Count Two. Ashland moves for dismissal of the Complaint under Federal Rule of Civil Procedure 12(b)(6).

II. Legal standard In deciding a motion to dismiss a complaint under Rule 12(b)(6), a court must first “accept all factual allegations as true” and “construe the complaint in the light most favorable to the plaintiff.” Eid v. Thompson, 740 F.3d 118, 122 (3d Cir. 2014) (internal quotations omitted). The court then must “determine whether, under any reasonable reading of the complaint, the plaintiff may be entitled to relief.” Id. A complaint is sufficient only when it is facially plausible, meaning that the court is able “to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (citing Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 556 (2007)). To be plausible on its face, the complaint must contain more than “[t]hreadbare recitals of the elements of a cause of action” and “mere conclusory statements.” Id. The court need not “accept unsupported conclusions and unwarranted inferences.” Morrow v. Balaski, 719 F.3d 160, 165 (3d Cir. 2013). When a court grants a motion to dismiss, the court “must permit a curative amendment unless such an amendment would be inequitable or futile.” Great Western Mining & Mineral

Co. v. Fox Rothschild LLP, 615 F.3d 159, 174 (3d Cir. 2010) (internal quotations omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Brittany Morrow v. Barry Balaski
719 F.3d 160 (Third Circuit, 2013)
Elias Eid v. John Thompson
740 F.3d 118 (Third Circuit, 2014)
Paul M. Ellington v. EMI Music, Inc.
21 N.E.3d 1000 (New York Court of Appeals, 2014)
Tuscan/Lehigh Dairies, Inc. v. Beyer Farms, Inc.
136 A.D.3d 799 (Appellate Division of the Supreme Court of New York, 2016)
Gutierrez v. Government Employees Insurance
136 A.D.3d 975 (Appellate Division of the Supreme Court of New York, 2016)
Elmhurst Dairy, Inc. v. Bartlett Dairy, Inc.
97 A.D.3d 781 (Appellate Division of the Supreme Court of New York, 2012)
Ward v. TheLadders.com, Inc.
3 F. Supp. 3d 151 (S.D. New York, 2014)
M.U. ex rel. Urban v. Downingtown High School East
103 F. Supp. 3d 612 (E.D. Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
SOLID STATE CHEMICALS LTD. v. ASHLAND LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/solid-state-chemicals-ltd-v-ashland-llc-pawd-2020.